Raft base of pumping stations, Civil Engineering

Assignment Help:

Question

Why are voids filled with lightweight infilling material in raft base of pumping stations?


Answer


To decrease dead load and therefore to decrease settlement of pumping stations, voids inside raft foundations are overflowing with light material. If in its place concrete is placed in these voids, it poses harsh thermal cracking difficulty and drastically increases loads to pumping stations. Use of general fill is also not desirable since its self-weight is comparable to that of concrete. On contrary, if these voids are left vacant, water might penetrate into these voids during future operation and increases dead load of pumping stations during its standard operation. So, lightweight infill material that is non-water-absorbing and non-biodegradable is intended inside these voids to stay away from ingress of water and to reduce dead load of structure.

 


Related Discussions:- Raft base of pumping stations

Soil structure, what is soil structure and types of soil structure?

what is soil structure and types of soil structure?

Various operations involved in maintenance by beater packing, Q. Explain in...

Q. Explain in details the various operations involved in Through Packing - conventional Maintenance by beater packing. Explain the various operations as per the Permanent Way

An alternative test to confirm concrete strength, Question If concrete comp...

Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is

Hydraulics, The atmospheric pressure is given 680 mm Hg at a certain mounta...

The atmospheric pressure is given 680 mm Hg at a certain mountain location of elevation 2000 m. air density is 1.007 kg/m3. Find the pressure in kPa.

Road base and base course in flexible carriageway, Road base vs. base cours...

Road base vs. base course in flexible carriageway Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributi

Glazed tiles for construction material, Q. Glazed tiles for Construction Ma...

Q. Glazed tiles for Construction Material? Glazed tiles are only meant for dadoes of bath room, Toilet and kitchens etc as they have no strength . Normally 8'' x 4'' g

Control reinforcement corrosion, Crack width limitation ( In many stand...

Crack width limitation ( In many standards and code of practice of numerous countries, allowable size of crack width is generally limited to less than 0.5mm for reinforced conc

Instruments, description and details about distomat

description and details about distomat

Finite elemenst, can you do finite elements using the weighted residual for...

can you do finite elements using the weighted residual formulation-galerkin method?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd