Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  


Related Discussions:- Project contracts

5. Reduction in Length of Stay for Heart Failure & Shock Pat, ABOUT THE CAS...

ABOUT THE CASE STUDY. This explains about the case study in general, its purpose, the problem identified, and the proposed solution (500-word count) V. PROJECT MANAGEMENT INTEGRAT

Critical reasoning, Ask question #MinimA new client of theirs named “ S&Y ”...

Ask question #MinimA new client of theirs named “ S&Y ” has started handing good amount of projects to them. It is estimated that in the upcoming year this crucial client will be g

Project cycle time optimisation, C y c le Time Optimisation Cycle ti...

C y c le Time Optimisation Cycle time optimisation is an operating philosophy of maximising the efficiency of the sub optimal value-added activities while reducing the non-

Project Initiation and Planning Report, Task As the project manager you ar...

Task As the project manager you are required to present an initial project report to the project sponsor that shows how you propose to implement this project. As the project manag

Disadvantages of product layout - demerits of breakdown, Disadvantages of P...

Disadvantages of Product Layout - Demerits of Breakdown The production line is vulnerable to interruption and shutdowns. A breakdown of a machine will render the entire line i

Contingency planning-planning function, Contingency planning Contingenc...

Contingency planning Contingency planning is the part of the planning process that identifies alternative courses of action that an organization might follow if various differe

Organisational style - participative management , Organisational Style: ...

Organisational Style: Whether the participative approach can  really work depends upon the type of organisation and its' functioning. An open organisation is more likely to en

Project management, Project managers can become more successful when they d...

Project managers can become more successful when they develop their understanding of organizations. Any organization can be viewed as having four different frames: structural, huma

Risk breakdown structure (rbs) , Risk Breakdown Structure (RBS)  R isk...

Risk Breakdown Structure (RBS)  R isk Breakdown Structure (RBS) is a tool developed by Dr. David Hillson that is used to guide the risk management process. He describes RBS as

What does mpmm contain, This product not only having more than 1000 pages o...

This product not only having more than 1000 pages of content explaining how projects should be undertaken successfully, but it also includes: 51 detailed project management temp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd