Project contracts, Project Management

Assignment Help:

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  


Related Discussions:- Project contracts

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

Framework for organisational culture, According to Schein (2004),culture is...

According to Schein (2004),culture is essentially an established pattern of behavior built on shared basic assumptions generated by tackling crucial external adaptions and internal

Performance measurement - elements of tqm, Performance measurement: Pe...

Performance measurement: Performance measurement needs to be based upontimely measures of, and feedback on, performance. It provides information ontoday's service and gives an

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Increasing interest in employ of application development, Increasing intere...

Increasing interest is being taken in the employ of quick application development. Why is that, and are there any dangers related with the RAD approach? RAD has come to promine

Explain about privatisation of public sector undertakings, Explain about th...

Explain about the privatisation of public sector undertakings. The privatisation of public sector undertakings : After independence India opted for mixed economy. The priv

What value does project management add, Q. What value does project manageme...

Q. What value does project management add? This is extremely difficult to answer in traditional accounting terms for the reason that the real value is in the quality of the end

Histograms, H i stograms Histograms show a visual summary of the data...

H i stograms Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understa

Production control system, Question 1: What is understand by a producti...

Question 1: What is understand by a production control system and how are the elements of control systems categorized? Description of production control system Catego

Benefits of quality, B enefits of quality The benefits of quality in p...

B enefits of quality The benefits of quality in project performance are: C ustomer satisfaction: is the result of a quality product or project. If customers requirem

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd