Project contracts, Project Management

Assignment Help:

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  


Related Discussions:- Project contracts

Reporting style, The Integrated Management Project is not intended to be an...

The Integrated Management Project is not intended to be an academic research report and the markers will not normally expect inclusion of a literature review or hypothesis testing.

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Responsibilities of an event manager, Question 1: a) Outline the key r...

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

Principle of parity of authority and responsibility, What is the principle ...

What is the principle of parity of authority and responsibility? The principle of parity of authority and responsibility states which in delegating; managers should match the r

What level of project management do i need, Q. What level of project manage...

Q. What level of project management do I need? A. This is a complicated question to answer for the reason that it very much depends on the size duration and technical complex

Evaluation of the prototype, At this stage of design the designer will...

At this stage of design the designer will invariably by under tremendous pressure to quickly finish the design and pass it on for production. This is so because even w

TQM, Value Engineering

Value Engineering

MSc PM, Hi I would like to know if you assist on the dissertation or what s...

Hi I would like to know if you assist on the dissertation or what services you can provide. Thanks,

Outline at least three steps common to pert and cpm, QUESTION (a) Feasi...

QUESTION (a) Feasibility Study is a preliminary study undertaken before a real work of a project start what factors should the project manager take into consideration while con

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd