Project contracts, Project Management

Assignment Help:

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  


Related Discussions:- Project contracts

Step in process selection, Step in Process Selection 1. Establish th...

Step in Process Selection 1. Establish the process Selection: A preliminary decision regarding process can be taken from but it stand point of function, economy, appearance

How are carrying costs varied with quantity order, How are carrying costs v...

How are carrying costs varied with quantity order? Carrying Costs, that vary along with quantity ordered, contained as a. There Interest on capital investment b. There Co

How is a network diagram constructed, How is a network diagram constructed?...

How is a network diagram constructed? A network (critical path) diagram constructed by: • Needs a pencil, ruler and 2P coin or some stencil otherwise coin for an ideal circl

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

Backward integration, Backward Integration A strategy in which an orga...

Backward Integration A strategy in which an organization builds competitive benefits by controlling the provider of the raw materials needed to make its products.

Execution of the enterprise resource planning (erp) system, At the last boa...

At the last board meeting of X Company, the Finance Director showed concern for the lack of planning information obtainable to the company. It was accepted that the company needed

Project managment traffic lights, #questionhi i sent my assignment yesterda...

#questionhi i sent my assignment yesterday but havenot recieved any reply yet ..

Projects at times get delayed due to various factors, QUESTION a) Proje...

QUESTION a) Project management activities are carried out in a planned manner. List the distinguishing characteristics of a project? b) During project management meetings, t

Understand strategy of organisation by project manager, Why is it significa...

Why is it significant for project managers to understand the strategy of the organisation which uses their services? This enables the project to be considered in the context of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd