Project contracts, Project Management

Assignment Help:

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  


Related Discussions:- Project contracts

Define the resource histograms in short, Define the Resource Histograms in ...

Define the Resource Histograms in short. Resource histograms A resource histogram is a column (or bar) chart which demonstrates the number of resources allocated to a pro

Advantages of quality control system, Reduction in Costs : An efficient qua...

Reduction in Costs : An efficient quality control system reduces the cost of production of the product due to reduction in wastage of raw materials, semi finished and finished good

What is the meaning of exception reports, What is the meaning of exception ...

What is the meaning of exception reports? Progress (or exception reports) can be utilized to monitor and to control the project. It permits the project board or project manager

Objectives of a work breakdown structure, Question: (a) Explain the typ...

Question: (a) Explain the typical contents of the project selection rationale document, drafted at the end of the conception phase. (b) (i) Describe the purpose and objecti

Introduction to syringe management plan, Introduction The project 'Syri...

Introduction The project 'Syringe Management Plan' is created to protect the community against misplace of syringe that causes accidental needle injury. This project is introdu

Characteristics of flexible manufacturing system, Characteristics of Flexib...

Characteristics of Flexible Manufacturing System An FMS is a process technology that can product a moderate variety of products in modest volumes and can do so quickly and wit

Objectives of iso 9000, Objectives of ISO 9000 The basic objectives o...

Objectives of ISO 9000 The basic objectives of ISO 9000are : 1. To facilitate international trade of goods and services. 2. To obtain competitiveness by obtaining

Project management process, Project management Process According to PMB...

Project management Process According to PMBoK, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed

Draw an activity-on-arrow network diagram for the project, Question: (a...

Question: (a) Back~to~Future International, a recently setup non-profit organization by the students of Fashion & Design Institute, has decided to organize a fashion show. The

What are the disadvantage of top-down centralised approaches, What are the ...

What are the disadvantages of top-down centralised approaches? The disadvantages top-down centralised approaches: Project budgets can be imposed by using top-down which is c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd