An operator tells you that it takes 2 minutes for a process to get half way to the final value after a step change in the input. What can you infer about the process time constant (tP)?
Assume dead-time (?P) is negligible and a linear first-order system.

Related Discussions:- Process Control

Report of handling of hazardous, Report Note: What do you observe? Do...

Report Note: What do you observe? Do you realise that the common chemicals you have been hadling casually at your laboratory (if any, with which you are working) are quite

Draw the b-h curve for a ferro-magnetic material, Draw the B-H curve for a ...

Draw the B-H curve for a ferro-magnetic material  and identify the retentivity and the coercive field on the curve.    B-H curve for a ferromagnetic material is drawn a

Project report, how to write project report for chemical engineering

how to write project report for chemical engineering

PROCESS CONTROL, HOW CAN I BE ABLE TO CONTROL AND BALANCE THE INPUT AND OUT...

HOW CAN I BE ABLE TO CONTROL AND BALANCE THE INPUT AND OUT-PUT

Emulsification, Emulsification: Emulsification can be defined as the prope...

Emulsification: Emulsification can be defined as the property of oils to get intimately mixed with water easily. Emulsions can be oil in water emulsion or water in oil emulsion. C

Thermal spelling, Thermal spelling: The breaking or cracking or peeling of...

Thermal spelling: The breaking or cracking or peeling off the refractory is known as spelling. A good refractory must show a good resistance to thermal spelling. Thermal spelling

What, How chemilcal#..

How chemilcal#..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd