Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Transmission system , Transmission System: In a two-wheeler, the transmiss...

Transmission System: In a two-wheeler, the transmission system means the whole arrangement that transmits the power from the engine crankshaft to the rear wheel.

Design for a water treatment plant, Design for a water treatment plant: ...

Design for a water treatment plant: Produce as individuals a single tab Excel spreadsheet which shows a rough initial design for a water treatment plant taking 15

Storage and handling of hazardous substances, Stores for hazardous substanc...

Stores for hazardous substances shall be segregated from, and located at a safe distance from accommodation spaces and control room. Indoor storage areas require access from an ope

Time and cost analysis, Time and Cost Analysis This discusses about ce...

Time and Cost Analysis This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities br

Calculate the primary voltage and real power measurements, Question: A ...

Question: A 7.2kVA single phase 50Hz, 480Vrms: 240Vrms transformer can be modelled using the primary referred approximate equivalent circuit shown in Figure 1 below. Fi

Design of a filament winding machine, How can I achieve a back and forth mo...

How can I achieve a back and forth movement of carriage system. How can I reverse the motor to go back and forth.

Explain the conventional frame, Show schematic diagram showing the layout o...

Show schematic diagram showing the layout of transmission system of four-wheel driven car. Explain briefly the following types of frame: (a) Conventional frame (b) Integra

What are the basic different air-fuel mixture, Describe carburetion. What a...

Describe carburetion. What are the basic different air-fuel mixture on which an engine can be operated ? Write a short note on sterling cycle. In an engine working on inlet pres

Pliers tool and equipment , Pliers: Pliers are used just for gripping or w...

Pliers: Pliers are used just for gripping or wire cutting and should never be used as substitute for spanners. The following types of plier are used : (a) Side cutting pliers

Performance criteria-aspects of scheduling , Performance Criteria This ...

Performance Criteria This is assumed that an FMS is the part of a superior production process. Consequently the performance of the FMS is not a major goal but imply to attain c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd