a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Estimate the mean and standard deviation, 1. How do variables and attribute...

1. How do variables and attributes differ?  2. Estimate the mean and standard deviation of the following measurements.

Significance of designing for profit in product development, Discuss the im...

Discuss the importance of designing for profit in product development. What happens when there is distortion in these goals?

Generate a system approach to performance appraisal, Develop a system appro...

Develop a system approach to performance appraisal that combines a group of appraisers, various times for appraisal, and a variety of instruments. Identify when each element would

Explain dynamic scheduling problem, Please explain how this works... I'm so...

Please explain how this works... I'm so confused! Suppose SPT rule is being used in a dynamic scheduling problem. There are five jobs A, B, C, D, and E ready to be processed at

Explain security and financial controls, Please explain in detail the answe...

Please explain in detail the answer for the following scenario: You are an IT project manager and have been given an unrealistic deadline. In order to get a project done on the req

Explain re-negotiate a new relationship, You are very annoyed by one of you...

You are very annoyed by one of your third-party service providers (3PL) and want to confront him and re-negotiate a new relationship. How would you go about this important task?

Explain the role of a pilot project in information systems, Petrie's Electr...

Petrie's Electronics Case, Chapter 10, Questions 1%u20135 (page 359). 4. What is the role of a pilot project in information systems analysis? Why do you think the Petrie%u2019s

Depict a layout for the assembly operation, Base on the case study: Weldon ...

Base on the case study: Weldon Hand Tools; Design a layout for the assembly operation (to include the fly press work) including the tasks to be performed at each part of the system

Explain phases in a project life cycle, An important factor used to determi...

An important factor used to determine the phases in a project life cycle are the control needs of the organization(s) involved in the project. True or False

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd