a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Internet often depicted as a cloud on network diagrams, Why is the internet...

Why is the internet often depicted as a cloud on network diagrams?

Explain recommendations with the external distribution, Lucille Jenkins, th...

Lucille Jenkins, the CEO for the Durham International Manufacturing Company (DIMCO), believes that the company can significantly increase its operating profit by implementing suppl

How do we link strategic and operational change, 1. How do we link strategi...

1. How do we link strategic and operational change?  Answer: Hambrick and Cannella present a 5-step approach:  1. obtain broad inputs at the formulation stage  2. assess o

Explain the term total quality management, Explain the term Total Quality M...

Explain the term Total Quality Management (TQM). Total Quality Management (TQM): It is a system approach to quality in all spheres of the organisation. TQM implies meeting th

Process strategy at wheeled coach, Why do you think major auto manufacturer...

Why do you think major auto manufacturers do not build ambulances?

Provide description of the business model, Create the document with conside...

Create the document with consideration to the following: E-Commerce business plan Use Word Title Page Table of Contents Use of the auto generated table of contents

Explain bottleneck operation by adding a new machine, A small firm intends ...

A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives, A and B, have been identified, and the associated costs and reven

Natural extrinsic reward comparises all the following except, Natural extri...

Natural extrinsic reward include all the following except/1.compliment/2.special Jon/3.asking advice/4.recognition/5. Merit pay increase/ which of these-answer is correct

Compute the schedule variance or cost performance index, A project to build...

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached wh

Operational Management, I have a take home exam that I need to be solved 10...

I have a take home exam that I need to be solved 100 % correct , please . I need it within 23 hours EXACTLY from now please . Thank you so much and I am really looking forward to s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd