problem, Operation Management

Assignment Help:
a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Explain what is the probability that both are successful, DO NOT WORK A com...

DO NOT WORK A company is considering producing two new electronic games designed for the popular Gameboy toy. Based on market data, management believes there is a 60 percent chance

Describe the differences between utilization and efficiency, Discuss the di...

Discuss the differences between utilization and efficiency as measures of system performance. Which (if any) is the most useful measure for an operations manager? Why?

Explain widget is identical and requires a machining cycle, 3,000 widgets m...

3,000 widgets must be machined on workstation during week. Each widget is identical and requires a machining cycle time (Tc) of 36.5 minutes. All of the machining centres in the sh

Explain communication is a two-way process, Communication is a two-way proc...

Communication is a two-way process. Communication is a series of loops. A message must be sent and the message must be received. However, the message must also be understood and ac

Process flow and layouts, process flow and layout flows are at the core of ...

process flow and layout flows are at the core of lean manufacturing, do you agree or disagree?

Objectivise and benefits of work study, Objectivise and Benefits of Work St...

Objectivise and Benefits of Work Study Objectivise of Work Study a)Provide more and improved physical means to motivate the workers. b)Improve the basic process by resear

Explain what kind of router could connect network, What kind of router coul...

What kind of router could connect network segments that use cat5 utp with other segments that use fibre optic cable? A. Modular router B. Translational router C. Bridge ro

Explain the impacts of consumerism, Describe the impacts of consumerism in ...

Describe the impacts of consumerism in regards to information technology, claims management, and member services when dealing with healthcare providers.

Explain what are the schedule and cost variances, I need to find the schedu...

I need to find the schedule and cost variances for a project Actual cost at month 16 = $540,000 Scheduled cost = $523,000 Earned value = $535,000 Provided this information,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd