a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Transportation problem, Calculate row or column penalty we take two values ...

Calculate row or column penalty we take two values namely the minimum and 2nd minimum? If 4 4 5 occurs in a problem, we choose 4 as a minimum and 5 the 2nd minimum why not another

Explain business relationship, Joan has been a manager with Argos for the p...

Joan has been a manager with Argos for the past 15 years. She is known to be aggressive and tough and always gets results. She is demanding of her employees and is often brusque wi

Objectives of good layout, Objectives of Good Layout Any of the follow...

Objectives of Good Layout Any of the following objectives might be achieved through a good layout: Provide enough production capacity. Reduce material handlin

Explain decision quality requirement that is significant, A large municipal...

A large municipality (250,000 citizens) is trying to decide where to locate a new community recreational center. The problem is relatively unstructured. There is a decision quality

Explain everything else remaining constant what will occurs, Everything els...

Everything else remaining constant, when the sample size increases, which of the following occurs? The sampling error decreases. The sampling error increases. The sampling

Travael chart, I want some project about travel chart.

I want some project about travel chart.

Explain waste elimination plan, Do a lean waste analysis on the goal and cr...

Do a lean waste analysis on the goal and create a waste elimination plan. (List the seven forms of waste, list items in the goal by waste form, determine what could be done to redu

Explain what is the resulting productivity ratio, The total output from a p...

The total output from a production system in one day is 900 units and the total labor necessary to produce the 900 units is 900 hours. Using the appropriate productivity measure, w

Describe switch read in order to find the mac address, What part of a packe...

What part of a packet does a switch read in order to find the MAC address?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd