Why are two gate regulators necessary in regular practice to form washout regulators?


Answer

In fact, situation is analogous to that of fire hydrants in that two gates valves are installed with a on its own fire hydrant. Washout valves are used for regular maintenance work of watermain like allowing flowing out of water throughout cleaning of watermain. At junction anywhere a tee-branch out to a washout point, a gate valve is installed to divide two pipelines. However, this gate valve is open throughout normal operation as another gate valve further downstream is installed. If downstream gate valve is not installed in position, then pipe section of branched-out watermain will be left dry during normal operation and there is a high probability that break to watermain and frequent leakage would happen. With downstream gate control device installed, segment of branched-out watermain consists water in regular operation. In a case there is any leakage, it be able to be readily detected by using two gate regulators.

 


Related Discussions:- Practice to form washout regulators

Vibrocoring in marine ground investigation, Vibrocoring in marine ground in...

Vibrocoring in marine ground investigation If only shallow marine ground geotechnical information is essential for design purpose, vibrocoring is certainly a good choice for s

Solid mensuration, the two sides of a triangle are 17cm and 28 cm long, and...

the two sides of a triangle are 17cm and 28 cm long, and the length of the median drawn to the third side is equal to 19.5. find the distance from an endpoint of this median to the

Timber, defects in timber?

defects in timber?

Diffrence between concrete road and bituminous road, Q. Diffrence between C...

Q. Diffrence between Concrete road and bituminous road? Concrete road belongs to rigid pavement and they don't deflect under traffic loads. Quite the reverse, bituminous pavem

Cost-volume-profit and break even analysis, Cost-Volume-Profit and Break Ev...

Cost-Volume-Profit and Break Even Analysis: Cost-volume-profit analysis helps us to learn the behaviour of cost and profit in response to varying level of business activity. I

EARTH FILL dam, different components of all types of earth fill dam

different components of all types of earth fill dam

Zones of smear around vertical drains, Zones of smear around vertical drain...

Zones of smear around vertical drains Smear zones are produced during the installation of vertical drains in that zone of soils surrounding the band drains are disturbed. Soil

What is the safe bearing capacity of wide strip footing, A loading test was...

A loading test was conducted with a 300 mm square plate at depth of 1 m under the ground surface in pure clay deposit. The water table is situated at a depth of 4 m below the groun

Basic considerations governing selection of road alignment, Basic Considera...

Basic Considerations Governing Selection of Road Alignment: The following considerations shall be kept in view in selecting the road alignment: Roads in Plain Areas (a)

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd