Question
What is key function of packing resources in joint of concrete pipes in pipe jacking?
Answer
Packing resources are about 10 to 20mm broad and are usually made of plywood, fibreboard or previous materials. In case the packing materials are absent in pipe joints for pipe jacking, after that any deflection in joints reduces contact area of concrete and it leads to spalling of joints due to high pressures induced. With insertion of packing fabric inside pipe joints, the acceptable deflection without damaging joint throughout pipe jacking process is able to be increased.
State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s
Q. Corner reinforcement for concrete pavement? Let's consider a panel of concrete slab without any load transferring devices at it edges. When concrete panel is subjected to tr
Basic things used in road construction: Water Absorption : The quantity of water absorbed by aggregates. Aggregate Impact Value : The percentage by weight of crushed ma
Q. Illustrate Weld Failures in Track? These are failures occurring to defects in welding the joint. These defects are either because of improper composition of thermit metal or
what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3
What is 'contact pressure'? How does it depend on the type of structure and type of soil? What is 'active zone' in soil? Define it with reference to the pressure bulb concept.
Dimensions of trusses
Q. Principle of airlifting for cleaning pile bores? Airlifting is generally carried out before concreting to remove debris and clean the base of pile bores. It basically acts a
terms of least cost method
We need eng. calcs for a deck 17''x 10 feet.attach to the guest house. calculations will be for 230 psi snow load . in the city of Mammoth lakes Ca. deck is supported for 3 girder
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd