What is key function of packing resources in joint of concrete pipes in pipe jacking?

Answer

Packing resources are about 10 to 20mm broad and are usually made of plywood, fibreboard or previous materials. In case the packing materials are absent in pipe joints for pipe jacking, after that any deflection in joints reduces contact area of concrete and it leads to spalling of joints due to high pressures induced. With insertion of packing fabric inside pipe joints, the acceptable deflection without damaging joint throughout pipe jacking process is able to be increased.

 

 


Related Discussions:- Packing resources in joint of concrete pipes in pipe jacking

BUILDING CONSTRUCTION, GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH...

GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH FILLING..

What are some facts about concrete, Actually, drying is not directly linked...

Actually, drying is not directly linked to hardness in concrete. After concrete is poured, putting it in a wet environment by spraying it constantly with water will hasten its hard

Explain remote sensing technique, Q. Explain Remote sensing technique? ...

Q. Explain Remote sensing technique? Remote sensing is a science or an art of obtaining the information about an object, area or a phenomenon through analysis of data acquired

Infrastructure railway design, The objective of this module is:- - For t...

The objective of this module is:- - For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibili

Collapse mechanisms in unsymmetrical portal frames, How to find beam,sway a...

How to find beam,sway and combined mechanisms for unsymmetrical portal frames? Also how to find the critical mechanisms by using plotting method?

Arches, construction of arches

construction of arches

Incremental launching mode of bridge construction, In i ncremental launchin...

In i ncremental launching mode of bridge construction, what are ways adopted to increase sufficient resistance of superstructure during launching practice?

Estimation specification and costing, Estimate the single room of size 3m x...

Estimate the single room of size 3m x 4m x height 3m using individual wall method?

Angle&direction, whate does mean bearing?with example

whate does mean bearing?with example

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd