Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

Related Discussions:- Off the shelf company

Full form of httpd, Full form of HTTPd It stands for HTTP daemon. HT...

Full form of HTTPd It stands for HTTP daemon. HTTPd is the program run on a UNIX platform to establish a Web server. On other platforms, such as Microsoft Windows NT, the We

State the list of protocols supported by the intranet, State the list of pr...

State the list of protocols supported by the Intranet The following is the list of protocols supported by the Intranet: ARP: Address resolution Protocol is used to resol

Request to a server, If a client gives a 4096-byte request to a server loca...

If a client gives a 4096-byte request to a server located 50 km away on a 1 Gbps fiber optic, then what is the efficiency of the line during this time? Suppose that the server give

Show the properties of microwaves, Q. Show the properties of Microwaves? ...

Q. Show the properties of Microwaves? Microwaves - Frequencies among 1 and 300 GHz - Unidirectional - Narrow focus requires sending as well as receiving antennas to

The received message - application layer , The Received Message If  we...

The Received Message If  we didn't mention  another  class of header lines that are  inserted by the SMTP receiving  server. The receiving  server upon receiving a message wit

Determine power dissipated in resistor, Question: With Vout not connect...

Question: With Vout not connected to any additional circuitry, what power is dissipated in the 7 kW resistor?

Ku-band earth station, Ku-BAND EARTH STATION This is most recent on-goi...

Ku-BAND EARTH STATION This is most recent on-going project under which 40 remote sites will be installed for CDMA back haul and 60 sites will be installed for GSM back haul. 4

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd