Movement accommodation factor for joint sealant, Civil Engineering

Assignment Help:

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint sealant can tolerate and is typically expressed as a percentage of the minimumdesign joint width. Failure to fulfil this requirement results in overstressing the joint sealants. 

For example if the expected movement to be accommodated by a certain movement joint is 4mm, the minimum design joint width can be computed as 4÷30% = 13.3mm when the movement accommodation factor is 30%. If the calculated joint width is too large, designers can either select another brand of joint sealants with higher movement accommodation factor or to redesign arrangement and locations of joints.


Related Discussions:- Movement accommodation factor for joint sealant

Abrasion test - tests on stones, Abrasion Test:   This test is carri...

Abrasion Test:   This test is carried out on stones used as aggregates for road construction. The test result shows the suitability of stones against   the grinding action u

Plane table sureying, discuss the resection method of plane table sureying ...

discuss the resection method of plane table sureying in detail

Uses of medain mode and mean, what is the uses of mean mode and medain in c...

what is the uses of mean mode and medain in civil engineering

Explain the ion exchange water softening, Explain the Ion Exchange water So...

Explain the Ion Exchange water Softening Softening is usually done using a resin (natural or synthetic long chain chemical with a sodium ion attached). When water containing ha

State the term axial prestressingin - Concrete, State the term Axial Prestr...

State the term Axial Prestressingin Concrete If the centroid of cross-sectional areas of tendons is at the location of the centroid of the cross-section of the concrete member,

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Physical classification of stones, Physical Classification Based on the...

Physical Classification Based on the structure, the rocks can be classified as following: Stratified rocks Un -stratified rocks A.   Stratified Rocks: These ro

Base isolation, why base isolation is not good for tall building

why base isolation is not good for tall building

Explain about void ratio drops, A clay layer 25 metres thick has a saturate...

A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m 2 . Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete founda

Design approach for the spacing of min-piles, Design approach for the spaci...

Design approach for the spacing of min-piles For close spacing of min-piles, it would provide substantial cost savings with reduction of pile cap size. Though close spacing of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd