Q. Module Site Installation Preparation?

The following tasks shall be accomplished at the Facility site prior to setting the modules on the piles:

After module support piles have been installed, the cap plate of each pile shall be surveyed to determine the top elevation of the cap plate when flat shim plates are used. Survey each corner of the cap plates when tapered shims are used. Refer to the construction drawings as appropriate, for various site conditions.

The ground between the piles shall be cleared of debris and the entire area shall be levelled as required to suite the placement of module either by crawler, RTVs and/or crane. The Project Site construction support shall obtain from logistics the area and elevation of the ground that needs levelling. In many instances an area in front of RTV or crawler setting the modules must also be levelled.


Related Discussions:- Module site installation preparation

Initial tension in the belt, Initial tension in the belt: Sol: The t...

Initial tension in the belt: Sol: The tension in belt which is passing over the two pulleys (that is driver and follower) when the pulleys are stationary is an initial tensi

Structural steels, Structural Steels Low alloy steels are utilized fo...

Structural Steels Low alloy steels are utilized for structural causes. That type of steels is needed to possess high yield stress, excellent ductility and high fatigue resist

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Group technology, comparing the different coding systems ?

comparing the different coding systems ?

Mechanics of solid, determine crippling load for T section dims 12cm??12cm?...

determine crippling load for T section dims 12cm??12cm??2m and of length 6m it used as colum with one of its end fixed and other hinged E=2??10 power 5 N/mm2

Discover the fixing torques set up at the ends of the shaft, Discover the f...

Discover the fixing torques set up at the ends of the shaft: A solid shaft 6.5 m long is securely fixed at each of the end. A torque of 91 Nm is applied to the shaft at a sect

Soil conditions for plant layout, Q. Soil conditions for plant layout? ...

Q. Soil conditions for plant layout? Soil conditions affect the foundation requirements, drainage, type of substructure used and may limit the size and shape of the facility. T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd