Students are to undertake a tunnel blast design for the following conditions:
• Tunnel is 5.5m wide by 5.5.m high
• Rock is a granite with a UCS of 300 MPa
• Drill hole diameter is 51 mm, hole length is 4m
• The cut is to contain 2 relief holes of 75mm diameter
• Dry conditions are anticipated, ANFO to be used with a density of 800 kg/m3 and a powder factor of 0.6 kg/m3
• Nonel detonators are to be used
Students are to determine:
1. The design of the cut, including burden and spacing for each element of the cut.
2. Burden and spacing of the easer, perimeter and lifer holes
3. Stemming length required
4. Method of hole priming
5. Firing sequence timings for the holes
6. Explosive utilisation
Results should be presented in a report format, including diagram s as required and details of calculations undertaken.

Related Discussions:- Mining

Miller sweep generator, I want circuit diagram of miller sweep generator wi...

I want circuit diagram of miller sweep generator with components using two transistor bc547

Chemical engineering project, Hello, I have a chemical engineering project...

Hello, I have a chemical engineering project and I need help.

Oil supply failure - propeller, Oil supply failure - Propeller: To prev...

Oil supply failure - Propeller: To prevent an overspeed caused by an oil supply failure, one of two methods may be employed: • Hydraulic lock valve The pitch lock mecha

Depletion mode mosfet, DEPLETION MODE MOSFET: In the depletion-mode typ...

DEPLETION MODE MOSFET: In the depletion-mode type, charge carriers are present in the channel at "Zero" gate bias and the device is, therefore, conducting.  The application of

Hot and cold working, advantages and disadvantages of cold and hot working

advantages and disadvantages of cold and hot working

Case1, Flifla sells tomatoes every day in Suk al Marqazi, the downtown frui...

Flifla sells tomatoes every day in Suk al Marqazi, the downtown fruit and vegetable market. He finds that he can order tomatoes in crates of 25 kg and he is able to stock a maximum

Procedures for starting and ground running of aircraft , Procedures for sta...

Procedures for starting and ground running: Before starting and ground running any gas turbine powered aircraft, several considerations must be taken into account. The first an

Net present value method: npv, Discounted cash flow methods Net present val...

Discounted cash flow methods Net present value method: NPV It is one of the classic methods of evaluating the investment project. Here each potential projects value is find out its

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd