Method study, Operation Management

Assignment Help:

Method Study

Work methods analysis method study is a scientific technique recordings and significantly examining the present method of performing a task or job operation along with the aim of improving the present method and developing a new and chapter method. It is also termed as methods improvement or work enhancement. It includes the study of work processes, working conditions and equipments and tools employed to perform the job.

According to British Standard Institute: Method study might be understood like the systematic recording and critical examination of existing and proposed ways of doing work as a means of developing and applying easier and much more effective method and reducing costs.


Related Discussions:- Method study

Explain straight-line depreciation, The expected average rate of return for...

The expected average rate of return for a proposed investment of $500,000 in a fixed asset with a useful life of four years, straight-line depreciation, no residual value, and an e

Explain consumer products into brazil, What steps could a company take to a...

What steps could a company take to avoid making product design and marketing mistakes when introducing new consumer products into Brazil?

Explain description of the purpose of prototyping, A description of the art...

A description of the article and where it was found Identification of the one thing about prototyping that surprised you the most A brief summary of why it surprised you A descript

Compute the line efficiency of longest processing time, Balance the assembl...

Balance the assembly line in Exhibit 8.12 for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an eight-hour shift, and use the rule, choose the assignab

Factors influencing plant layout, Factors Influencing Plant Layout While...

Factors Influencing Plant Layout While choosing the layout for a factory the following factors should be taken into consideration: Management Policy: Management has to de

Explain what is your assessment of the health of the project, On day 51, a ...

On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the he

Describe a manufacturing company preparing to build a plant, A manufacturin...

A manufacturing company preparing to build a new plant is considering three potential locations for it. The fixed and variable costs for each alternative location are presented bel

Explain approach to formulating a wbs for this project, Recommend the most ...

Recommend the most effective approach to formulating a WBS for this project.

Lean Management, Please can u give me case analysis of Sunwind AB(HBC Case)...

Please can u give me case analysis of Sunwind AB(HBC Case)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd