Meter field testing and installation practices, Electrical Engineering

Assignment Help:

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.


Related Discussions:- Meter field testing and installation practices

Explain common collector configuration, Q. Explain common collector configu...

Q. Explain common collector configuration? It is called the common-collector configuration because (ignoring the power supply battery) both the signal source and the load share

What is the difference between a tem mode and a te mode, Q. (a) What is the...

Q. (a) What is the difference between a TEM mode and a TE mode? (b) Explain the terms "cutoff wavelength" and "dominant mode" as applied to waveguides. Find the cutoff wavelengt

Calculate efficiency to load at unity power factor, Q. A 300-kVA transforme...

Q. A 300-kVA transformer has a core loss of 1.5 kW and a full-load copper loss of 4.5 kW. (a) Calculate its efficiency corresponding to 25, 50, 75, 100, and 125% loads at unity

Quality control, three reasons why a chamfer shouldn''t be considered an un...

three reasons why a chamfer shouldn''t be considered an unimportant dimension

Find the average power absorbed by each element, Q. Let v(t) = Vmax cos ωt ...

Q. Let v(t) = Vmax cos ωt be applied to (a) a pure resistor, (b) a pure capacitor (with zero initial capacitor voltage, and (c) a pure inductor (with zero initial inductor current)

Explain the energy bands in solids, Explain the energy bands in solids. ...

Explain the energy bands in solids. There are as several energy bands in a solid as there are energy levels in the parent atoms. Many electrical properties of significance

Transfer characteristics of jfets, Q. Give the Shockley's equation for the ...

Q. Give the Shockley's equation for the transfer characteristics of JFET's? Where ID is the drain current and VGS is the voltage across gate and source. The squared term o

Convert number systems from one base to another, Convert number systems fro...

Convert number systems from one base to another, and apply the binary number system to logic circuits 1.   Convert the following decimal numbers to binary a.   81 10 b.

Gunn diode, write the note on gunn diode and ats applications

write the note on gunn diode and ats applications

Find the force-current analog as well as the force voltage, Q. (a) The c...

Q. (a) The concept of duality can be extended to nonelectric physical systems bymeans of analogs. For example, the mechanical system characteristics can be investigated by means

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd