Measuring Kanban

 Two commonly cited methods of measuring the performance of a manufacturing process are flow through time and work in progress inventory levels.

Flow through time is takes once unit to pass through the entire process from start to finish ( on average) . in the kanban system both of these measures are at least partially dependent upon lot sizes.

For example if a kanban system uses 25 workstations and a lot size of 54th the average WIP will be near 100 units. If the cycle time for a balanced load is say two minutes per item ( using the lot size of 4 ) . flow through time will be close to 200 minutes (allowing for some variation) : one unit of product will flow through the system in 200 minutes.


Related Discussions:- Measuring kanban

Strengths and weaknesses of the existing system, The system analyst must un...

The system analyst must understand the existing problems and strengths and weaknesses of the existing system. Other activities comprise identifying the overall implications and ben

Research on environmental attitudes, Research on environmental attitudes in...

Research on environmental attitudes in the context of nature-based tourism and ecotourism in particular have emerged as an interesting topic among tourism researchers in recent yea

What is the role of leadership in the management literature, What is the ro...

What is the role of leadership in the management literature? In the management literature, each manager is a leader there. Leadership is a procedure of interpersonal affect. Th

Safety and environmental issues, You must present a complete HAZOP for one ...

You must present a complete HAZOP for one part of the process. The HAZOP should be accompanied by a commentary explaining what decisions were made? Why? What changes are required?

BUSINESS PLAN, L NEEP HELP TO DETERMINE THE PRICE OF CONCIERGE SERVICE TO T...

L NEEP HELP TO DETERMINE THE PRICE OF CONCIERGE SERVICE TO THE SENIORS AND NURSING MOTHERS

Managerial Economics, calculate point elasticity of demand for demand funct...

calculate point elasticity of demand for demand function Q=10-2p for decrease in price from Rs.3 to Rs.2

Financing to bankrupt corporations, Suppose you gave a party and 60 minutes...

Suppose you gave a party and 60 minutes showed up at the door. Would you let them in? Would you evict them? Would you commit hara-kiri? Those were the choices that confronted th

Qestion, How will you inform your managers and supervisors about budgets, r...

How will you inform your managers and supervisors about budgets, reporting requirements and financial delegations? I just want to know

Explain the characteristics of a traditional society, Question 1 Explai...

Question 1 Explain the four assumptions made by modernization theory about the process of social change in the Third World. Give your own examples to explain your discussion.

Business process analysis, Business Process Analysis 1. Comprehensive b...

Business Process Analysis 1. Comprehensive business process analysis with suggested improvements. Must include projected quantitative results. Report must include use of analyt

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd