Meaning of driving succession of driven piles, Civil Engineering

Assignment Help:

Question

What is meaning of driving succession of driven piles?


Answer

In Basement construction, if piles are driven from centre to perimeter, there is a propensity of soils to move away from. Such lateral group of soil might cause break to nearby structures and utilities.

Though, if piles are driven from outside perimeter inwards, there are slight soil lateral movements. These results in a well-compacted core with an excess pore water pressure built up to resist loading of piles. So, shorter pile lengths than original designed ones might result. Still, some time after pile driving operation, excess pore water stress is dissipated and shorter driven piles might not be able to take up the original design loads. In this state redriving is required to drive piles to deeper depths after indulgence of excess pore water pressure.

 


Related Discussions:- Meaning of driving succession of driven piles

Landing stages - water transportation, Landing Stages: A landing stage...

Landing Stages: A landing stage is a floating structure, usually a pontoon or a barge, which is secured to the shore by mooring chains. Small ships can dock against the landin

Describe the boussinesq theory, A raft of size 4 m-square carries a load of...

A raft of size 4 m-square carries a load of 200 kN/m 2 . Verify the vertical stress increment at a point 4 m below the centre of the loaded area using Boussinesq's theory. Compare

Marine facilities, define and explain various marine facilities

define and explain various marine facilities

Construction of embankment, Construction of Embankment: The following...

Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed

Two property rule , The state of a pure substance of given mass is defined ...

The state of a pure substance of given mass is defined by specifying two appropriate properties provided that 1. The system is in equilibrium 2. Gravity, motion, electricity,

Surveying, what is meant by geodetic survey

what is meant by geodetic survey

Estimate the net present worth - construction management, Three alternative...

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection wi

How can rock sockets take up loads, Question How can rock sockets take ...

Question How can rock sockets take up loads? Answer Load transfer mechanism is brief as follows- While a socketed basis is loaded, conflict is provided by together

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd