Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Find out maximum bending stress induced in beam, Q. A beam made of C.I. hav...

Q. A beam made of C.I. having section of 50mm external diameter and 25 mm internal diameter is supported at 2 points 4 m apart. The beam carries concentrated load of 100N at the ce

#title.THERMODYNAMICS., what are the limitations of first law of thermodyna...

what are the limitations of first law of thermodynamics?

Computer integrated manufacturing, methods involved in grouping the parts i...

methods involved in grouping the parts into families?

Determine the increase in pressure in vessel, Determine the increase in pre...

Determine the increase in pressure in vessel: A thin spherical vessel of diameter 750 mm & wall thickness 8 mm is filled through water at atmospheric pressure. Determine the i

Parts of wilson hartnell governor, what are the parts of wilson hartnell go...

what are the parts of wilson hartnell governor with their designation?

Main features of laser cutting process, Main Features of Laser Cutting Proc...

Main Features of Laser Cutting Process   1) Laser cut kerf is very narrow resulting in material saving. 2) Has very narrow heat affected zone (HAZ) and therefore gives low

Concept of continuum - thermodynamics, Concept of continuum - thermodynamic...

Concept of continuum - thermodynamics: Sol: Even the simplification of matter into molecules, atoms, electrons, etc. is too complex a picture for many problems of thermodyna

Design varies with scale of operation, Design varies with scale of operatio...

Design varies with scale of operation The design of a fermenter varies with scale of operation from lab (1-20L), to pilot (up to 5000L) to production (to >200,000L) scales. Th

Process selection and sequencing, Process Selection and Sequencing In th...

Process Selection and Sequencing In this, some factors, which have an influence in all processes, are discussed. The factors include size, shape complexity, tolerances and produ

What is the basic working of cooling tower, Q. What is the basic working of...

Q. What is the basic working of Cooling Tower? Cooling towers are generally located downwind from process units to adequately disperse vapors (from exchanger leaks) and minimiz

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd