Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine minimum value of weigh to cause motion, Determine minimum value o...

Determine minimum value of weigh to cause motion: Determine minimum value of weight W required to cause motion of block, which rests on a horizontal plane. The block weighs 3

Mircometer, How is a micrometer used?

How is a micrometer used?

Nitrides-silicides and sulfides, Nitrides, Silicides and Sulfides Nitr...

Nitrides, Silicides and Sulfides Nitrides contain very high melting point but initiate to oxidize at low temperature. They have poor resistance also to chemicals. Boron nitrid

Dthd, Ask question #Minimvchfchd jftdysrtttttttttgsghxum 100 words accepted...

Ask question #Minimvchfchd jftdysrtttttttttgsghxum 100 words accepted#

What do you mean by levelling procedure, Q. What do you mean by Levelling P...

Q. What do you mean by Levelling Procedure? The Surveyor shall calculate required field adjustment in module elevation based on data from survey in conjunction with correspondi

Interference, construction and working of michelsons interferometer

construction and working of michelsons interferometer

Fluids, show a schematic circuit diagram of a electric hydraulic gear pump...

show a schematic circuit diagram of a electric hydraulic gear pump with adjustable with one direction flow and explain the operation

Water turbine, what are the types of water turbine and its application ?

what are the types of water turbine and its application ?

Automobiles industry growth , AUTOMOBILES INDUSTRY GROWTH: The Indian auto...

AUTOMOBILES INDUSTRY GROWTH: The Indian automobile industry has a significant labour cost advantage. India's automotive sector has the world's second largest pool of skilled labou

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd