Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Mechanical properties of materials, A tensile test on a specimen having an ...

A tensile test on a specimen having an initial diameter of 13.11 mm and an initial gauge length of 200.0 mm, gave the following data:

Battery-electrical system , Battery: Battery is a device that produces dir...

Battery: Battery is a device that produces direct current (DC). The chemical energy of battery ingredients converts into electrical energy in the form of direct current. This is a

Quantum mechanics, A ball is dropped from a height .If it takes0.200 second...

A ball is dropped from a height .If it takes0.200 second to cross the last 6.00 m before hitting the ground ,find the height  from which it was dropped . Ans) We need to find H

Manufacturing technology, Details of rolling process,Different rolling meth...

Details of rolling process,Different rolling methods,

Need of a spectrophotometer, Need of a spectrophotometer: The specific...

Need of a spectrophotometer: The specific instructions will differ with other models, but the principles remain. 1. The instrument must have been warm for at least 15 min.

Cutting technology., can you explain about merchant circle,cutting forces

can you explain about merchant circle,cutting forces

What is windsocks, Windsocks shall be installed at plant facilities handlin...

Windsocks shall be installed at plant facilities handling flammable gases, volatile liquids or toxic materials and also at helipads (may require lighting if night flights are inten

Flow work and flow energy - thermodynamics, Flow Work and Flow Energy - the...

Flow Work and Flow Energy - thermodynamics: Flo w Work:  The flow work is energy needed to move the working substance against its pressure It is called as flow or displac

Prove the fourier series expansion, (a) Prove that the fourier series expan...

(a) Prove that the fourier series expansion for the function x(t) described in the finite interval -π ≤ t≤ π x(t) = 0 -π ≤ t ≤ 0 x(t) = sint 0 ≤ t ≤ π (b) Represent t

Evaluate plant load factor, a) Illustrate principal of magneto hydro dynami...

a) Illustrate principal of magneto hydro dynamic system (MHD) with diagram? b) a thermal power plant has two 60 MW units each running for 8000hrs and one 30MW unit running for 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd