Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Draw the p-h diagram for the vapour compression cycle, Draw the P-h and T-S...

Draw the P-h and T-S diagram for the vapour compression cycle when the vapour after compression is : (i) wet region (ii) dry saturated

Annealing temp, hiw can i fix the maximum temp of the aluminium

hiw can i fix the maximum temp of the aluminium

Calculate the force - pulley, Calculate the force - pulley: A string i...

Calculate the force - pulley: A string is passing over a smooth pulley. The string supports the mass m on one side which is to be pulled up with acceleration a. calculate the

Consideration for centrifugal tension, Consideration: 1. From above eq...

Consideration: 1. From above equation, it is clear that centrifugal tension is not dependent of T1 and T2. It depends upon velocity of the belt. For lower belt speed (that is,

Control function in production management, Control Function in Production M...

Control Function in Production Management: Controlling is a sub system of the production system where a part of the output is monitored for feedback signals to give corrective

Boiler, what is boiler. give all things about boiler. 1 specifica 2 mountin...

what is boiler. give all things about boiler. 1 specifica 2 mounting 3 acessories 4 advantages 5 maintinance

Evaluate hydraulic efficiency, A pelton wheel works at the foot of a dam be...

A pelton wheel works at the foot of a dam because of which the head available at the nozzle is 400m. The nozzle diameter is 160mm and the coefficient of velocity is 0.98. The diame

Autocad screen, Autocad screen- The autocad Screen basic chapter of Aut...

Autocad screen- The autocad Screen basic chapter of Autocad course it will show the display of Autocad on computer screen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd