Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Define the skid fabrication, Q. Define the skid fabrication? Unless not...

Q. Define the skid fabrication? Unless noted otherwise in this specification, skid fabrication shall be in accordance with GS-904-0510, GS-904-0511 and GS-904-0515. Dimensio

Strengh of material, case study of thermal stresses and composite bar

case study of thermal stresses and composite bar

Dislocation, Diff. B/w edge and screw dislocation

Diff. B/w edge and screw dislocation

Adhesives, Adhesives Adhesives are a substance able of holding materia...

Adhesives Adhesives are a substance able of holding materials together. A joint is formed among two solids is called adherends with a thin layer of adhesive among them. Mainly

Air injection system and solid injection system, (a) Explain a typical fuel...

(a) Explain a typical fuel feed system for a C.I engine, differentiate between air injection system and solid injection system. (b) Why Gasoline injection system has been adopte

Determine steady state error, Derive mathematical equation for the time res...

Derive mathematical equation for the time response of a first order system subjected to ramp input. Draw the response curve and determine steady state error. Give some examples of

Explain side cutting edge angle, Explain Side Cutting Edge Angle It is ...

Explain Side Cutting Edge Angle It is angle between the side cutting edge and the longitudinal axis of the tool. It avoids formation of build up edge, controls the direction of

Product life-cycle management, Product life-cycle management: There ha...

Product life-cycle management: There have also been changes in the use of some pre-existing data formats. Open associations have been formed to encourage some formats to becom

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd