Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Slider crank mechanism, What is the mathematical displacement equation and ...

What is the mathematical displacement equation and its derivatives?

Thermodynamics, in a closed cycle steam enters the turbine at a temperature...

in a closed cycle steam enters the turbine at a temperature of 400oc and a pressure of 4000kpa and is condensed at 10kpa

Evaluate tension in the string, A smooth sphere of radius 15 cm and weight ...

A smooth sphere of radius 15 cm and weight 2 N is supported in contact with a smooth vertical wall by a string whose length simlar the radius of sphere. The string joins a point on

Explain the 3-2-1 principle of location, Explain the 3-2-1 Principle of Loc...

Explain the 3-2-1 Principle of Location A work piece can be positively located by means of 6 pins so positioned that collectively they restrict the work piece in nine of it

The force of friction, During paddling of a bicycle,the force of friction e...

During paddling of a bicycle,the force of friction exerted by the ground on the two wheels is? Ans) Since the rear wheel rotates by itself (we only paddle to rotate the fron wheel

Define cases in which automation is done, Define Cases in which Automation ...

Define Cases in which Automation is Done Automation is done in following cases:- a) Loading and unloading of parts. b) Automatic production lines. c) Automatic tool ch

What are major cutting tools used for machining of metals, a) What are majo...

a) What are major kinds of cutting tools used for machining of metals? b) What important role the chip breakers play during machining of metals? c) Write four important requi

Important terms related to boiler, IMPO R T AN T TERMS: Fi r e ...

IMPO R T AN T TERMS: Fi r e Box: Place where fuel is burnt. Grat e : The fuel is burnt on this. Baffles : Plates are used for directing the flow of flue gass

Phenomena useful for electromechanical energy conversion, Q.   State and br...

Q.   State and briefly explain the various phenomena useful for electromechanical energy conversion in rotating machines.   Sol. In the rotating machines there are mainly tw

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd