Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Can you explain pneumatic gauges, Q. Can you explain Pneumatic gauges? ...

Q. Can you explain Pneumatic gauges? Pneumatic gauges permit reading or recording water level at some distance from the river, say up to about 305 m. In a diaphragm type gauge,

Describe root-finding techniques, In mechanics, stress is a measure of the ...

In mechanics, stress is a measure of the internal forces acting within a deformable body. Quantitatively, it is a measure of the average force per unit area of a surface within the

Breather tube-stator plate oil seal complaints, Breather tube : Check brea...

Breather tube : Check breather tube for blockage and also air filter box hole where breather tube is connected, for any blockage.

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Hydrostatic pressure, can a swimming pool that is full be cracked or lifted...

can a swimming pool that is full be cracked or lifted by hydrostatic pressure?

Explain the methods of solid modeling, Explain the Methods of solid modelin...

Explain the Methods of solid modeling The various methods for representing the solids are : (i)  Half-space method (ii)  Boundary representation method (b-rep) (iii)

Determine the rankine efficiency, A simple Rankine cycle works between pres...

A simple Rankine cycle works between pressures 0.06 bar and 28 bar, the initial condition of steam being dry saturated. Determine the cycle efficiency, specific steam consumption a

Principals, do you know the grade to the answers of the questions in the pr...

do you know the grade to the answers of the questions in the pre paid solutions..?? and what if the answers are wrong..?? as i need all working out shown

Assumptions made in deriving torsional formulas, Assumptions made in derivi...

Assumptions made in deriving torsional formulas: What are assumptions made in deriving torsional formulas?                                           Sol.: The torsion

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd