Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Resource management for project, Q. Resource Management for project? An...

Q. Resource Management for project? An important factor in overall project success is the provision of suitable and adequate resources. The initial estimate of engineering man

Calculate the kic from the data - thick cylinder, Calculate the KIC from th...

Calculate the KIC from the data - thick cylinder: In a fracture test a 3-point bend specimen of thickness 20 mm and depth 25 mm is supported over a span of 100 mm. The specime

Determine the resultant of the loads, Determine the resultant of the loads:...

Determine the resultant of the loads: A system of loads acting on beam is shown in the figure given below. Determine the resultant of the loads. Sol.: Let R be resultant

Heavy load supports, A number of heavy items are to be off-loaded from a He...

A number of heavy items are to be off-loaded from a Heavy-Lift Ship and placed on a series of "support assemblies" on the quayside to await transportation by road to their destinat

Determine the critical load, Determine the critical load (W crit ) to ...

Determine the critical load (W crit ) to cause elastic instability of the rigidly jointed frame shown in Figure Q2. The frame members have constant bending stif

Brazing vs welding, Brazing Vs Welding Following are the differences be...

Brazing Vs Welding Following are the differences between brazing and welding. (i)  In brazing, the joint surfaces are not raised to fusion point (or melted) and the joint is

Calculating the maximum moment, Select a standard rolled steel I-section fo...

Select a standard rolled steel I-section for the simply supported beam shown in figure below.  Select an appropriate factor of safety and material strength.  Include references for

Causeways, Paved Dips: Paved dips, also known as bed level causeways,...

Paved Dips: Paved dips, also known as bed level causeways, are structures consisting of gentle and shallow depressions in the road where the water is allowed to flow over the

What are the two ways of pile foundation, What are the two ways of pile fou...

What are the two ways of pile foundation Pile foundations can be installed in two ways. Timber, steel and precast concrete piles, are driven from the ground using hammers till

Determine maximum shearing stress in shaft, Determine maximum shearing stre...

Determine maximum shearing stress in shaft:   A propeller shaft 100 mm in the diameter, is 45 m long, transmits 10 MW at 80 rotation per minute. Determine maximum shearing str

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd