Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Working of impulse turbine, Working of Impulse turbine: The technique ...

Working of Impulse turbine: The technique in which multiple system of rotors are keyed to a common shaft, in series and the steam pressure of jet velocity is absorbed in stage

The auto component sector-automobiles industry growth , The auto component ...

The auto component sector has also posted significant growth of 20 percent in 2003-04, and achieved a sales turnover of Rs. 30,640 crore (US$ 6.7 billion). Further, there is a pote

What is hopper unit, What is Hopper unit Two hydraulically operated fol...

What is Hopper unit Two hydraulically operated folding type hoppers are provided on the front side of the machine. The capacity of the hopper is 4.25 CM.

Design pumps for plant layout, Q. Design Pumps for plant layout? Pumps ...

Q. Design Pumps for plant layout? Pumps handling flammable or combustible materials are relatively frequent sources of leakage and should therefore be located as far as practic

Micrometer or screw gauge-measuring tools , Micrometer (or Screw Gauge): T...

Micrometer (or Screw Gauge): There are two different types of micrometers - inside and outside micrometers. A micrometer also has two scales - Main scale and Vernier scale (Figure

K, Ask okokopkpk#Minimum 100 words accepted#

Ask okokopkpk#Minimum 100 words accepted#

Joint details and preparations, Joint Details and Preparations Joints s...

Joint Details and Preparations Joints shall be prepared by machining, flame cutting with grinding to bright metal or air-carbon arc gouging with grinding to bright metal such t

Sales incentives-AUTOMOBILES INDUSTRY GROWTH , Sales incentives , introduct...

Sales incentives , introduction of new models as well as variants coupled with easy availability of low cost finance with comfortable repayment options continues to drive demand an

Engine oil replacement and top-up, Engine Oil Replacement and Top-up :   Th...

Engine Oil Replacement and Top-up :   The engine oil has to be changed at a periodic interval because after some point of time it loses its viscosity and cooling, anti rust, and se

Plasma welding, PLASMA WELDING This is an extension of TIG welding. In...

PLASMA WELDING This is an extension of TIG welding. In plasma welding torch, plasma energy is constricated and ensures its most efficient utilisation for welding cutting and s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd