Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Deflection at the centre - maximum deflection, Deflection at the centre - m...

Deflection at the centre - maximum deflection: A simply supported beam of span 6 m is subjected to Udl of 24 kN/m for a length of 2 m from left support. Discover the deflectio

Friction, Friction: When a body moves or tends to move over the other ...

Friction: When a body moves or tends to move over the other body, a force opposing the motion develops at the contact surfaces. This force that opposes the movement or the ten

Limitations of fusion bond epoxy coatings, Q. Limitations of fusion bond ep...

Q. Limitations of fusion bond epoxy coatings? The application of fusion bond epoxy coatings shall be limited to specially equipped coating yards or plants. The plant operations

Determine the initial radius of curvature, Determine the initial radius of ...

Determine the initial radius of curvature:  A carriage spring, defiantly loaded and simply supported at its ends, has 12 steel plates each 60 mm wide by 6 mm thick. If the lon

Applications of high temperature materials, Q. Applications of high tempera...

Q. Applications of high temperature materials? A brief description of materials of construction used for common high temperature components in furnaces, boilers, superheaters,

Rubber, Rubber Rubber is a plastic that is largely derived from natura...

Rubber Rubber is a plastic that is largely derived from natural sources and utilized in a modified form. For automobile tyres, Rubber is well identified as material. Rubber re

Determine mass of air needed for complete combustion, How are fuels divided...

How are fuels divided ? Write disadvantages and advantages of each types. (b) A sample of coal supplied to a boiler has the following composition by mass : Carbon = 88%, Hydr

Evaluate the deflection at the free end of the cantilever, Evaluate the def...

Evaluate the deflection at the free end of the cantilever: Discover the slope and deflection at the free end of the cantilever illustrated in Figure . Take EI = 200 × 10 6 N-

Determine the maximum uniformly distributed load, Determine the maximum uni...

Determine the maximum uniformly distributed load: A timber beam 150 mm wide & 300 mm deep is supported simply over a span of 4 m. determine the maximum uniformly distribute

Calculate pressure - temperature at all points of the cycle, An aircraft mo...

An aircraft moving with speed of 1200 Km/hr, uses simple air refrigeration cycle for air conditioning. The ambient temperature and pressure are 0.35 bar and - 10 o C respectively.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd