Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Consider some publications of the bureau of standards, Consider some public...

Consider some publications of the Bureau of Standards. The following publications of the Bureau of Standards shall be read along with this section of footings. a. IS 456 in

Find out the axial moment of inertia, Find out the axial moment of inertia:...

Find out the axial moment of inertia: Find out the axial moment of inertia of a rectangular area of base b and height d around centroidal axis GX and the base B 1 B 2 . So

Neutral position-shifting of gears , Shifting of Gears: To obtain differen...

Shifting of Gears: To obtain different size combinations of gears, the gears slide on their shafts to mesh with different gears. The position of different gears, e.g. 1st, 2nd, 3r

Explain the difference between si and ci engines, Difference between SI and...

Difference between SI and CI engines SI engine stands for spark ignition engine while CI engine stands for compression ignition engine. SI engine works on the principle of w

Can you explain corners and fillets, Q. Can you explain Corners and fillets...

Q. Can you explain Corners and fillets ? Corners and fillets The intersection of the surfaces in casting must be smooth and forms no sharp angles. For this, the external a

Two-phase flow in a horizontal pipe, Two-Phase flow In a Horizontal Pipe ...

Two-Phase flow In a Horizontal Pipe While working for an oil company you are asked to produce a report on a two-phase flow problem. A mixture of oil and gas is to be pumped al

Determine mi of unequal angle section, Q .  Determine MI of unequal angl...

Q .  Determine MI of unequal angle section 15cm × 10cm × 1.5cm with longer leg vertical and is flange upwards. Figure Sol. :                      A 1 = 10 ×

Calculate net force on the piston, A vertical petrol engine 100mm diameter ...

A vertical petrol engine 100mm diameter and 120mm stroke has a connecting rod 250mm long. The mass of the  piston is 1.1kg. The speed is 2000 r.p.m. On the expansion stroke with a

Bending stress in curved beams, aframe of punching machine and its varios d...

aframe of punching machine and its varios dimentions. if it has force of85kN determine others

Explain the concept of cell-decomposition, Cell-decomposition In cell-d...

Cell-decomposition In cell-decomposition, an object can be represented as the sum of cells into which it can be decomposed. Each cell-decomposition system defines a set of prim

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd