Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Acceleration of the two blocks, In the drawing, the weight of the block on ...

In the drawing, the weight of the block on the table is 380 N and that of the hanging block is 215 N. Ignore all frictional effects, and assuming the pulley to be massless.

Define the process of otto cycle, Define the process of Otto cycle The...

Define the process of Otto cycle The Otto cycle is the ideal air standard cycle for petrol and gas engine. It having of four processes. Process 1 to 2 is isentropic comp

Theory of machine, analytical method for determining the acceleration and v...

analytical method for determining the acceleration and velocity?

Effects of air resistance. , Traveling at a speed of 16.0 m/s, the driver o...

Traveling at a speed of 16.0 m/s, the driver of an automobile suddenly locks the wheels by slamming on the brakes. The coefficient of kinetic friction between the tires and the roa

What do you mean by levelling procedure, Q. What do you mean by Levelling P...

Q. What do you mean by Levelling Procedure? The Surveyor shall calculate required field adjustment in module elevation based on data from survey in conjunction with correspondi

Evaluate the angle of heel, A motor cycle with rider, weight of 250 Kg., th...

A motor cycle with rider, weight of 250 Kg., the centre of Gravity of the machine and rider combined being 60 cm above from ground level when the machine is standing upright. Each

What are the specific issues with plant layout, Q. What are the Specific Is...

Q. What are the Specific Issues with plant Layout? There are a large number of regulations and related material that impact the operating plant. API (American Petroleum Institu

Purpose of corrosion assessment design, Q. Purpose of Corrosion assessment ...

Q. Purpose of Corrosion assessment design? The purpose of this design guide is to ensure that Material Selection for Steam Assisted Gravity Drainage (SAGD) projects is carried

Determine the number of leaves and initial curvature, Determine the number ...

Determine the number of leaves and initial curvature: A leaf spring with a span of 1.40 m consist width and thickness of leaves to be 100 mm and 12 mm respectively. The maximu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd