Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

If engine does not start at cranking speed troubleshooting , If Engine Does...

If Engine Does Not Start at Cranking Speed Causes of Problem Remedy Incorrect electrode gap of spark plug Fouled spar

Basic requirements of a control scheme of steam generators, Q. Basic requir...

Q. Basic requirements of a control scheme of steam generators? The basic requirements of a control scheme are: • Master steam pressure control by feedback to the water flow

Tempering and stabilization, Tempering and Stabilization: Tempering o...

Tempering and Stabilization: Tempering of tool steel in heat treatment is again a significant step. The quenching of such steels reasons the existence of untempered martensit

Applications, applications of dynamically induced emf

applications of dynamically induced emf

Entropy, why entropy always tends to increase?

why entropy always tends to increase?

Dry saturated steam - thermodynamics, Dry Saturated Steam - thermodynamics:...

Dry Saturated Steam - thermodynamics: A dry saturated steam is single phase medium. It does not have any water particle. It can be obtained on complete evaporation of water at

Write the differences between reaction and impulse turbine, (a) Show that t...

(a) Show that the force exerted by a jet of water on an inclined fixed plate in the dissection of jet is given by fx = .a.v 2 . sin 2 θ. Where a is area of jet, v is velocity of j

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd