Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Equilibrium diagram, what do understand by the term equilibrium diagram

what do understand by the term equilibrium diagram

Copper-nickel alloys, Copper-Nickel Alloys Complete solubility arises ...

Copper-Nickel Alloys Complete solubility arises between nickel and copper. All alloys have same microstructure and may be cold or hot worked. Cupro-nickel also termed as Ge

Contents of cast iron, Contents of Cast Iron: Cast Iron or CI is prep...

Contents of Cast Iron: Cast Iron or CI is prepared form melting pig iron in cupola furnace or in electric furnace. This furnace offers better quality. CI contains various

String vibration fixed ends, String Vibration Fixed Ends In case of the...

String Vibration Fixed Ends In case of the vibrations of a string, both its ends at  x = 0  and  x = L  may be permanently fixed;  y (x = 0) = 0 , and  y (x = L) = 0 at all  t

He- ne laser, constructing and working of he- ne laser

constructing and working of he- ne laser

Austempering, Austempering: The component to be hardened is initialy ...

Austempering: The component to be hardened is initialy austenised and after that quenched into a lead or salt bath held at just over the martensite transformation temperature

Types of cooling system , Types of Cooling System: Two types of cooling sy...

Types of Cooling System: Two types of cooling system are used in two wheelers. (a) Natural air-cooling. (b) Forced air-cooling.

Explain principle of design of jig and fixture, Explain Principle of Design...

Explain Principle of Design of Jig and Fixture While designing jigs and fixtures following considerations should kept in mind: Reduction of idle time. Rigidity

Evaluate the composite transformation matrix, A triangle ABC with vertices ...

A triangle ABC with vertices A (30,20), B(90,20), C(30,80) is to be scaled by a factor of 0.5 about a point X(50,40). Calculate :- (i) The composite transformation matrix; and

Kelvin plank statement - thermodynamics, Kelvi n Plank Statement: ...

Kelvi n Plank Statement: Sol: It is impossible to construct this type of H.E. that operates on cyclic process and converts all the heat supplied to it into equivalent

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd