Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Thermodaynamic, Ask question #MiThe steam that leaves the super-heater is e...

Ask question #MiThe steam that leaves the super-heater is expanded from 130bar at 535°C to 25.2bar at 310°C in a high pressure turbine. The steam from the exit of the HP turbine is

Show the coating application, Q. Show the Coating Application? Immediat...

Q. Show the Coating Application? Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application tempe

Explain the height adjustment and extension of augers, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Find the maximum allowable size of the milling cutter, Find the Maximum All...

Find the Maximum Allowable Size of the Milling Cutter  Find the maximum allowable size of the milling cutter if it is to rotate at 65 rpm while the cutting speed is 20 m/min.

Determine controllability matrix – open loop control system, An open-loop c...

An open-loop control system has the following state-space model: (a)  Determine the characteristic equation for the open-loop control system. (b)  Determine the characte

Battery-electrical system , Battery: Battery is a device that produces dir...

Battery: Battery is a device that produces direct current (DC). The chemical energy of battery ingredients converts into electrical energy in the form of direct current. This is a

Construction of lacashire boiler, Construction of Lacashire boiler: C...

Construction of Lacashire boiler: CONSTRUCTION : Consists of boiler shell which contains water and steam. Diameter can vary from 1.75 to 2.75 m and length can be 7.25 - 9 m

Projection welding, Projection Welding   This is a modified method o...

Projection Welding   This is a modified method of making single or multiple spot welds. Projection welds are made by providing an embossment or projection on one or both of

Electrodes- cast iron electrodes, Cast Iron Electrodes There are three ty...

Cast Iron Electrodes There are three types of electrodes for welding of cast ions. a) Monel-cored electrodes (30 % Ni 70 % Cu) b) Fe-Ni (40 % Ni) c) Ni-electrodes (97 E) These

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd