Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What is crest gauges explain, Q. What is Crest gauges explain? In case ...

Q. What is Crest gauges explain? In case of bridges, it is sometimes necessary to observe high flood levels rather than daily gauges to ensure that minimum clearance is not enc

Utm machine, hazard and safety measures when using utm machine

hazard and safety measures when using utm machine

Estimate the air flow velocity , A smooth glass plate is coated with a spec...

A smooth glass plate is coated with a special electrically conductive film that may be used to produce a constant heat flux on the plate. Estimate the air flow velocity which must

Nature of distribution of bending stress, Natur e of Distribution of Bendi...

Natur e of Distribution of Bending Stress Figure Nature of stress distribution in section of a beam It will be proved that bending stress at any layer of section o

Calculate strength coefficient - true stress and true strain, Calculate str...

Calculate strength coefficient: A copper specimen of 64 mm gauge length and 12.80 mm dia. was tested in tension. Following two diameters were recorded in the plastic range of

Either wheel is wobbling motorcycle problem, If Either Wheel is Wobbling ...

If Either Wheel is Wobbling Causes of Problem Remedy Excessive wheel bearing play Distorted rim Improperly

Define flavorings in iges, Define Flavorings in IGES Flavorings : IGE...

Define Flavorings in IGES Flavorings : IGES contained several ways to capture the same information, which made proper interpretation largely dependent on the particular  "fla

Product life-cycle management, Product life-cycle management: There ha...

Product life-cycle management: There have also been changes in the use of some pre-existing data formats. Open associations have been formed to encourage some formats to becom

Determine the actual average pressure, A multiple disc clutch, steel on bro...

A multiple disc clutch, steel on bronze, is to transmit 4.5 kW at 750 r.p.m. The inner radius of contact is 40mm and outer radius of the contact is 70 mm. The clutch operates in oi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd