market beta, Portfolio Management

Assignment Help:
The management of Nelson plc wish to estimate their firm’s equity beta. Nelson has had a stock market quotation for only two months and the financial management feels that it would be inappropriate to estimate beta from the actual share price behavior over such a short period. Instead it is proposed to ascertain, and where necessary adjust, the observed equity betas of other companies operating in the same industry, and with the same operating characteristics as Nelson, as these should be based on similar levels of systematic risk and be capable of providing an accurate estimate of Nelson’s beta

Three companies have been identified as firms having operations in the same industry as Nelson with identical operating characteristics. However, only one company, Oak plc, operates exclusively in the same industry as Nelson. The other two companies have some dissimilar activities or opportunities in additional to those which are the same as those of Nelson.

Details of the three companies are as follows;

a. Oak plc has an observed equity beta of 1.12. The capital structure at market value is 60% equity, 40% debt.

b. Beech plc has an observed equity beta of 1.11. It is estimated that 30% of the current market value of Beech is caused by risky growth opportunities which have an estimated beta of 1.9. The growth opportunities are reflected in the observed beta. Beech’s other activities are the same as Nelson’s. Beech is financed entirely by equity.


c. Pine plc has an observed equity beta of 1.14. Pine has two divisions, East and West. East’s operating characteristics are considered to be identical to those of Nelson. The operating characteristics of West are considered to be 50% more risky than those of East. In terms of financial valuation East is estimated as being twice as valuable as west. The capital structure of Pine at market values is 75% equity, 25% debt.

Nelson is financed by equity. The tax rate is 40%.

Required

a. Assuming all debt is virtually risk-free, make three estimate of the equity beta of Nelson plc. The three estimates should be based, separately, on the information provided for Oak, Beech and Pine.

b. Explain why the estimated beta of Nelson, when eventually determined from observed share price movements, may differ from the value derived from the approach in (a) above.

c. State the reason why a company has a very volatile share price and is generally considered to be extremely risky can have a lower beta value, and therefore lower financial risk, than an equally geared firm whose share price is much less volatile.

Related Discussions:- market beta

Arbitrage pricing theory, looking for questions with answers given on arbit...

looking for questions with answers given on arbitrage pricing theory

Multi asset/matlab code, solve the mean variance problem to construct a por...

solve the mean variance problem to construct a portfolio f a securities consider in ar least 5 securities:no short salling and with lending & borrowing

Mm, 4. Mrs. Mary Atkins, age 66, has been your firm’s client for five years...

4. Mrs. Mary Atkins, age 66, has been your firm’s client for five years, since the death of her husband, Dr. Charles Atkins. Dr. Atkins had built a successful newspaper business th

Portfolio Construction, Hello I was wondering how can I construct a portfol...

Hello I was wondering how can I construct a portfolio for analyzing momentum effect. The portfolio should include four stocks out of 40 with highest returns

Adjustable-rate preferred stock - arps, It is a kind of preferred stock whe...

It is a kind of preferred stock where the dividends issued will change with a benchmark, most often a T-bill rate. The price of the dividend from the preferred share is set by a fi

Investment decision, An investment manager at TD Ameritrade is making a dec...

An investment manager at TD Ameritrade is making a decision about a $10,000,000 investment.  There are four portfolio options available and she is looking at annual return of these

Types of inventory control systems, Problem 1: The procurement concept ...

Problem 1: The procurement concept encompasses a wide range of supply activities including all stages of the procurement cycle. Explain briefly these stages. Describe why the

Investment, what is portfolio management and how can we calculate it?

what is portfolio management and how can we calculate it?

Estimate of bond rating, Estimate of Bond Rating The score for UNH bas...

Estimate of Bond Rating The score for UNH based on the Altman model is a score of 3.23. Based on the bankruptcy range for this model, the bond rating for UNH is estimated in t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd