Maintenance of water bound macadam roads, Civil Engineering

Assignment Help:

Maintenance of Water Bound Macadam Roads:

The maintenance of water bound macadam surface consists of :

  • filling potholes, ruts with additional material and adequately compacting.
  • removing corrugations by dragging.
  • repairing lavelled surface (in which loose aggregates appear on the road) by adding fresh binding material, watering and compacting.
  • restoring broken edges by fresh material.
  • renewal of surface (50-75 mm) once in 2-6 years depending upon traffic.

 


Related Discussions:- Maintenance of water bound macadam roads

Changeable depth bridge decks, Question What is the sucker deck principle f...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greater tha

Ironmongery, fabrication methods of ironmongery

fabrication methods of ironmongery

Cost of utilities and taxes, The cost of utilities, taxes and maintenance o...

The cost of utilities, taxes and maintenance on a home is $3,000 per year.  The amount of money that would have to be invested now at 8% to cover these expenses for the next 5 year

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

High Sulfate Soils, How do you treat High Sulfate soils, Gypsum? Is it good...

How do you treat High Sulfate soils, Gypsum? Is it good practice to build on it?

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd