A PAPER MILL PRODUCES TWO GRADES OF PAPER VIZ., X AND Y. BECAUSE OF RAW
MATERIAL RESTRICTIONS, IT CANNOT PRODUCE MORE THAN 400 TONS OF GRADE X PAPER
AND 300 TONS OF GRADE Y PAPER IN A WEEK. THERE ARE 160 PRODUCTION HOURS IN A
WEEK. IT REQUIRES 0.20 AND 0.40 HOURS TO PRODUCE A TON OF GRADE X AND Y PAPERS.
THE MILL EARNS A PROFIT OF RS. 200 AND RS. 500 PER TON OF GRADE X AND Y PAPER
RESPECTIVELY. FORMULATE THIS AS A LINEAR PROGRAMMING PROBLEM.

Related Discussions:- LP

., The following process is designed to handle 120 customers a day. The cus...

The following process is designed to handle 120 customers a day. The customer is “processed” through each of the two operations, A and B, in sequence form. The average rate of each

Why company declines to correct the flaw, Scenario 2: A supervisor discover...

Scenario 2: A supervisor discovers a design flaw, which she believes is a safety hazard. She informs the company through the proper channels. The company declines to correct the fl

Explain forecast week 7 using a six-week moving average, Weekly sales of ry...

Weekly sales of rye bread at the corner store are shown below. Using this data, forecast Week 7 using a six-week moving average. Week Sales 1 415 2 389 3 420 4 382 5

Estimate the mean and standard deviation, 1. How do variables and attribute...

1. How do variables and attributes differ?  2. Estimate the mean and standard deviation of the following measurements.

Explain objectives of organisational development, Explain objectives of org...

Explain objectives of organisational development. Objectives of Organisational Development (i) Enhancement in the performance of the organisation. (ii) Enhancement in t

Schmenner''s service-process matrix - operation strategy, Schmenner's Servi...

Schmenner's Service-Process Matrix The service-process matrix was introduced earlier. It is Schmenner's service industry equivalent of the product-process matrix. The service

What means the problem may be solved with pom, Michael Plumb's job shop has...

Michael Plumb's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A - 4 9 7 B - - 6 8 C - - - 10 D - - - - means the pr

#operational performance, what are the 5 operational performance objectives...

what are the 5 operational performance objectives may influence decision making associated to process design and layouts

Define the amount of fabric she needs is to forecast, The percentage of val...

The percentage of value of shipments that come from materials for the average manufacturer is: a. greater than or equal to 40 and less than or equal to 49 percent. b. greater than

Explain stock outstanding, Assume a company has 10 million shares of stock ...

Assume a company has 10 million shares of stock outstanding and that its Income Statement for Year 12 is as follows: Income Statement Data Year 12 (in 000s) Net Revenues from Footw

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd