llean management, Project Management

Assignment Help:
Arvin Automotive, a company that makes muffler assemblies for the Big Three, is committed to the use of Kanban to pull material through its manufacturing cells. Arvin has designed each cell to fabricate a specific family of muffler products. Fabricating a muffler assembly involves cutting and bending pieces of pipe that are welded to a muffler and a catalytic converter. The mufflers and catalytic converters are pulled into the cell based on current demand. The catalytic converters are made in a specialized cell.
Catalytic converters are made in batches of 10 units and are moved in special hand carts to the fabrication cells. The catalytic converter cell is designed so that different types of catalytic converter can be made with virtually no setup loss. The cells respond to an order for a batch of catalytic converters in approximately four hours. Because the catalytic converter cell is right next to the muffler assembly fabrication cell, transportation time is virtually zero.
The muffler assembly fabrication cell averages approximately eight assemblies per hour. Each assembly uses the same catalytic converter. Due to some variability in the process, management has decided to have safety stock equivalent to 10 percent of the needed inventory.
Required:
(a) Determine the average number of units demanded per period. 1mark
(b) Determine the safety stock needed support operation. 1mark
(c) Calculate the number of Kanban sets. 2marks
(d) Comment on the answer in (c).

Related Discussions:- llean management

Audits, A udits Audits are independent examinations to determine wheth...

A udits Audits are independent examinations to determine whether processes and procedures achieve the specified objective. They are an essential tool to identify problem areas

Define project management, QUESTION The project management is an integr...

QUESTION The project management is an integrative endeavour. Projects lead to change and their importance to an organization is also to be understood to differentiate projects

Why is necessary to plan an is project in detail before work, Give three re...

Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

Corporate strategy of a multi-business organisation, Strategy is developed ...

Strategy is developed at different levels in large organisations. The process starts with the corporate strategy which is then translated into the strategy for the business divisio

Identify the critical path by activities and duration, Identify the critica...

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Components of participative management, COMPONENTS OF PARTICIPATIVE MANAGEM...

COMPONENTS OF PARTICIPATIVE MANAGEMENT: The involvement of staff in the decision making process of the organization and having increased awareness of the organization's purpos

Enterprising management, Hi dear my presentation is ready I need to do my B...

Hi dear my presentation is ready I need to do my Business Plan on it for 2500 words.. can u do it please

Illustrate the method of on the job training for managers, Illustrate the m...

Illustrate the method of On the Job Training for managers? Methods of ‘On – the Job Training’ for Managers are illustrated below: a. Experience: Under such method a person

Cycle time, Cycle time and Assign work elements and Delete the assigned ele...

Cycle time and Assign work elements and Delete the assigned elements A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd