lean operations, Supply Chain Management

Assignment Help:
Kateville Textile Printing Company Ltd
Introduction
Kateville Textile Printing Company Ltd. design company which produces design fashion products and distribute to all branches of Stockwell Supermarket Chain Stores Ltd. The company’s currently functional layout in the shop floor has some operational problems which forced production to use large batch quantities due to the high set up times resulting in high build up in-process stock.
The company is looking to improve their competitiveness through the implementation of lean concepts to improve the manufacture of well designed men’s and women’s wears as well as children’s wear for an overseas market.
Customer Report:
Customer requirement: One daily shipment of 600 units to Stockwell Supermarket Chain Stores Ltd. The buyer, Kateville Textile Printing Company Ltd places weekly orders to Gennie Fabrics Ltd., the supplier by fax for 1,200units inventory to be supplied direct to production site.

Production Control Department:
I. Receives Stockwell Supermarket Chain Stores Ltd. 800 daily forecast and enter them into the MRP system
II. Issue weekly orders to supplier, Kay Fabrics
III. Secure 1,500 unit raw materials delivery by weekly fax order release
IV. Generate weekly department MRP requirement based upon customer order, WIP, F/G inventory levels and anticipate scrap and down tme.
V. WIP between cutting and screen print = 600units
VI. WIP between screen print and sewing = 1,600units
VII. Finished Goods Inventory = 2,500units
VIII. Manual daily directives from Production Supervisor

Based on the week forecasts, production department releases daily manual information through the Factory Supervisor to the shop floor.
Additional Information:
• Movement of production materials through the process is by push system
• Supplier delivery takes 3 days and hold ups between cutting and screen print takes 2 days.
• Queuing between screen print and sewing takes 2 days whilst finish goods remain at the warehouse five days before shipment to Kateville Textile Printing Company Ltd.

Process Information
A. Cuttings
i. 5 operators
ii. Cycle time = 4mins
iii. Changeover time = 65mins
iv. Uptime = 85%
v. 2 Shifts


B. Screen Print
i. 3 operators
ii. Cycle time = 14mins
iii. Changeover = 65mins
iv. Uptime= 80%
v. 3 Shifts

C. Sewing
i. 15 operators
ii. Cycle time= 18mins
iii. Changeover = 35mins
iv. Uptime = 95%
v. 1 shift

D. Shipping Department
Remove sewed dresses from finished goods warehouse and stages them for truck shipment to customer.

Requirement:
Question 1
From the above information create and comment on the current state map of Kateville Textile Printing Company Ltd. (14marks)
Question 2
From Q1 design to improve the manufacturing systems at a cell level using lean techniques to create a future state map and comment with justification any actions taken in arriving at your decision. (15marks)

Related Discussions:- lean operations

Process flow diagrams identify the push-pull interface, The Pampered Puss ...

The Pampered Puss is a company with headquarters in Melbourne, Australia and operates 35 retail shops. These shops are spread throughout the metropolitan area and were established

Tqm implementation programme, Question 1: a. Describe briefly the SWOT ...

Question 1: a. Describe briefly the SWOT analysis. b. Describe the Porter's Five Forces model. Porter's Five Forces model Question 2: Describe the objectives and ty

Logistics, Identify and discuss the primary and secondary activities in sup...

Identify and discuss the primary and secondary activities in suply chain

Value Chains, How might the Internet of Things (Iot) and new emerging data-...

How might the Internet of Things (Iot) and new emerging data-analytical tools be used to disintermediate traditional customs brokers, freight consolidators and other 3PLs from your

What is the composition of the central procurement board, Question 1: A...

Question 1: A Mr Lovebook informs Library Books that he wishes to buy one book "The Great Book" by Mr Bookwriter which is due to come out on 25 April 2009 at 11.00 am at the li

The 7 Principles of Supply Chain Management, refer to the article: 7 Princi...

refer to the article: 7 Principles of supply chain management (by David L. Anderson and etc.). Students are expected to critique the article.

Linear program to optimizes cost , Aerial Products has received a contract ...

Aerial Products has received a contract to construct airframes produced at a client's factory in Tennessee.  There are strict quality control measures in place for the airframes.

Logistics, 1-what are distribution costs? 2- what are lost opportunity cost...

1-what are distribution costs? 2- what are lost opportunity costs? 3-what are ordering costs?

Pricing , Hello, I have one question please. How much per page?

Hello, I have one question please. How much per page?

Strategic International Business Management, Helo I wanted to make payment ...

Helo I wanted to make payment for my final assignment by 12 December 2018

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd