Kateville Textile Printing Company Ltd
Introduction
Kateville Textile Printing Company Ltd. design company which produces design fashion products and distribute to all branches of Stockwell Supermarket Chain Stores Ltd. The company’s currently functional layout in the shop floor has some operational problems which forced production to use large batch quantities due to the high set up times resulting in high build up in-process stock.
The company is looking to improve their competitiveness through the implementation of lean concepts to improve the manufacture of well designed men’s and women’s wears as well as children’s wear for an overseas market.
Customer Report:
Customer requirement: One daily shipment of 600 units to Stockwell Supermarket Chain Stores Ltd. The buyer, Kateville Textile Printing Company Ltd places weekly orders to Gennie Fabrics Ltd., the supplier by fax for 1,200units inventory to be supplied direct to production site.

Production Control Department:
I. Receives Stockwell Supermarket Chain Stores Ltd. 800 daily forecast and enter them into the MRP system
II. Issue weekly orders to supplier, Kay Fabrics
III. Secure 1,500 unit raw materials delivery by weekly fax order release
IV. Generate weekly department MRP requirement based upon customer order, WIP, F/G inventory levels and anticipate scrap and down tme.
V. WIP between cutting and screen print = 600units
VI. WIP between screen print and sewing = 1,600units
VII. Finished Goods Inventory = 2,500units
VIII. Manual daily directives from Production Supervisor

Based on the week forecasts, production department releases daily manual information through the Factory Supervisor to the shop floor.
Additional Information:
• Movement of production materials through the process is by push system
• Supplier delivery takes 3 days and hold ups between cutting and screen print takes 2 days.
• Queuing between screen print and sewing takes 2 days whilst finish goods remain at the warehouse five days before shipment to Kateville Textile Printing Company Ltd.

Process Information
A. Cuttings
i. 5 operators
ii. Cycle time = 4mins
iii. Changeover time = 65mins
iv. Uptime = 85%
v. 2 Shifts


B. Screen Print
i. 3 operators
ii. Cycle time = 14mins
iii. Changeover = 65mins
iv. Uptime= 80%
v. 3 Shifts

C. Sewing
i. 15 operators
ii. Cycle time= 18mins
iii. Changeover = 35mins
iv. Uptime = 95%
v. 1 shift

D. Shipping Department
Remove sewed dresses from finished goods warehouse and stages them for truck shipment to customer.

Requirement:
Question 1
From the above information create and comment on the current state map of Kateville Textile Printing Company Ltd. (14marks)
Question 2
From Q1 design to improve the manufacturing systems at a cell level using lean techniques to create a future state map and comment with justification any actions taken in arriving at your decision. (15marks)

Related Discussions:- lean operations

Discuss the validity in Zimbabwe of the grounds on w, Discuss the validity ...

Discuss the validity in Zimbabwe of the grounds on which the profit maximising model of the firm has been defended.

A local skating rink charges each person $5 to skat, A local skating rink c...

A local skating rink charges each person $5 to skate and another $3 for each skate rental. The rink has determined that on a daily basis, when 100 tickets are sold, the costs per s

Define two major drivers of supply chain performance, QUESTION 1 Ide...

QUESTION 1 Identify and define two major drivers of supply chain performance Discuss the role of two of the drivers in creating strategic fit between the supply chain str

Supply chains and value chains, Supply Chains and Value Chains Supply ...

Supply Chains and Value Chains Supply Chains and Value Chains have been around for many years and Logistics has served as glue to bind the different members. But in the curren

The 3c model by kenichi ohmae, The 3C model by Kenichi Ohmae The 3C mod...

The 3C model by Kenichi Ohmae The 3C model has been given by well known business strategist of Japanese origin, Kenichi Ohmae. The 3 C's of the model stands for: The

Discuss in detail the reasons for bullwhip effect, Discuss in detail the re...

Discuss in detail the reasons for bullwhip effect? Demand forecasting Lead time  • Batch ordering  • Price fluctuation Inflated orders

Appeal mechanisms in the current procurement system, The Public Procurement...

The Public Procurement Act 2006 is based on international procurement best practices that guarantee the rights of all parties involved. For instance, unsatisfied bidders and supp

Bottlenecks - transformation process, Review your transformation process an...

Review your transformation process and identify the major bottlenecks that might be restricting smooth flow of operations, causing delays and impacting process performance.  Exp

LEAN THINKING, #questionCOURSE: LEAN THINKING Read the journal article Spe...

#questionCOURSE: LEAN THINKING Read the journal article Spear, S., & Bowen, H. K. (1999) ‘Decoding the DNA of the Toyota Production System’, Harvard Business Review, 77 (5), p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd