Q. Leak Repair Torquing Procedure?

Attempt to tighten only the bolts contained within an arc that includes the leak area plus one or two bolts either side of the leak to the original torque values. A criss-cross torquing sequence should be used. If the leak does not stop, repeat the torquing procedure using increments of 50 ft-lbs. (68 N-m) up to the maximum over torquing value.

If the bolts cannot be tightened, the stud bolts contained in the arc of the leak shall be removed one at a time and cleaned or replaced if damaged. Lubricate the bolts and reinstall. Torque the bolts to the full torque value. Follow the same torquing sequence as above. Repeat the sequence using increments of 50 ft-lbs. (68 N-m) up to the maximum over torquing value.

If no results are achieved, go to the bolt on the flange directly opposite to the center of the leak, loosen it and retighten it to its proper torque. Ten, working one bolt at a time on opposite sides of the first bolt, readjust all the bolts on the side of the flange opposite the leak. It may be necessary to repeat this operation to get even bolt loading. When this operation is complete, go back to the bolt in the center of the leak and retighten as outlined above.

If these procedures are still not successful in stopping the leak, consider using hot/cold setting compounds with special enclosures or taking the piping system out of service for permanent repair.


Related Discussions:- Leak repair torquing procedure

Chemistry, What is a petroleum gas

What is a petroleum gas

Arc initiation-touch start-high frequency start, ARC INITIATION Touch...

ARC INITIATION Touch Start With the power supply energised and the shielding gas flowing through the cup, the torch is lowered toward the workpiece until the tungsten electr

Concept of temperature - thermodynamics, Concep t of Temperature: The...

Concep t of Temperature: The temperature is thermal state of body which describes the degree of hotness or coldness of body. If the two bodies are brought in contact, heat wi

Design square footing with plan area and soil reaction, A square column 410...

A square column 410 x 410 mm (along with 4 No. 16 mm bars) carries a dead load of 1020 kN and an imposed load of 410 kN. The foundation soil has a safe bearing capacity of 200 kPa.

Example of reduce system to a single force and couple, Example of Reduce sy...

Example of Reduce system to a single force and couple: A system of parallel forces is acting on rigid bar as shown in the figure given below. Reduce this system to  a sing

Find stress intensity factor - thick cylinder, Find stress intensity factor...

Find stress intensity factor - thick cylinder: A thick cylinder of r i = 10 mm, r 0 = 70 mm carried equal and symmetric radial cracks 6 mm long on opposite sides of inner su

Explain Machining allowance, Can you show us - Overall length of external s...

Can you show us - Overall length of external surfaces, cm In image Material Cast Overall length of external surfaces, cm 0 to 30 30 to 60 60 to 105 1

Standard factory formed insulation on flanges and valves, Q. Standard facto...

Q. Standard factory formed insulation on Flanges and Valves? All fittings are to be insulated with standard factory formed insulation. All joints shall be buttered and sealed.

Construct the load displacement diagram, A suspended walkway in an undergr...

A suspended walkway in an underground cavern consists of a deck supported by three tie rods placed symmetrically about the centre as shown below: The rods are each of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd