Q. Leak Repair Torquing Procedure?

Attempt to tighten only the bolts contained within an arc that includes the leak area plus one or two bolts either side of the leak to the original torque values. A criss-cross torquing sequence should be used. If the leak does not stop, repeat the torquing procedure using increments of 50 ft-lbs. (68 N-m) up to the maximum over torquing value.

If the bolts cannot be tightened, the stud bolts contained in the arc of the leak shall be removed one at a time and cleaned or replaced if damaged. Lubricate the bolts and reinstall. Torque the bolts to the full torque value. Follow the same torquing sequence as above. Repeat the sequence using increments of 50 ft-lbs. (68 N-m) up to the maximum over torquing value.

If no results are achieved, go to the bolt on the flange directly opposite to the center of the leak, loosen it and retighten it to its proper torque. Ten, working one bolt at a time on opposite sides of the first bolt, readjust all the bolts on the side of the flange opposite the leak. It may be necessary to repeat this operation to get even bolt loading. When this operation is complete, go back to the bolt in the center of the leak and retighten as outlined above.

If these procedures are still not successful in stopping the leak, consider using hot/cold setting compounds with special enclosures or taking the piping system out of service for permanent repair.


Related Discussions:- Leak repair torquing procedure

Editing dimensions-autocad, Editing Dimensions The dimension edit comma...

Editing Dimensions The dimension edit commands, DIMEDIT and DIMTEDIT are used basically to adjust the position of the text part of a dimension. This is usually only necessary,

Determine velocity at a cross section of the pipe, Consider a fully develop...

Consider a fully developed laminar flow of a fluid through a 200 m long and 4 cm diameter horizontal and circular pipe. The density and the viscosity of the fluid are 1400 kg/m 3

Computer integrated manufacturing, methods involved in grouping the parts i...

methods involved in grouping the parts into families?

What do you understand by pele box, What do you understand by PELE box and ...

What do you understand by PELE box and when it is utilized? Ans. The equipments required in PELE box are: i. HOLDER ii. TRIPOD STAND iii. BULBS iv. CROCODILE CLIP

Noise attenuation in ventilating, Indicate size, capacity and noise reducin...

Indicate size, capacity and noise reducing characteristics of all silencers on plans, including silencers for vane-axial fans. Indicate all acoustical lining on drawings, genera

Mechanical properties of materials, A tensile test on a specimen having an ...

A tensile test on a specimen having an initial diameter of 13.11 mm and an initial gauge length of 200.0 mm, gave the following data:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd