job costing, Cost Accounting

Assignment Help:
XYZ Company is a family-owned bicycle manufacturing company located in Stow, Ohio. Until recently,it had maintained slow but steady growth in producing and marketing its only product, the Tourist bicycle. In 2011, however, demand for this product line had stalled at 9,000 units per year due to heavy price reductions by competitors. Exploring for new business opportunities, Bryan Sanders, the owner, added a high end racing bike, the Racer, to the product mix in 2012.

The company uses a job order costing system to record Racer''s product costs. Table 1 shows the jobs in Work-in-Process Inventory (WIP) on November 30, 2012.


Job No.

# bikes

Accumulated Cost


R025

150

$ 169,500.00


R026

250

206,060.00


R027

200

129,000.00






$ 504,560.00


On November 30, 2012, two jobs were still in the Finished Goods (FG) Inventory. These jobs were expected to be shipped to customers during the first week of December.


Job. No.

# Units

Unit Cost

Accumulated Cost


R023

150

$1,325.00

$ 198,750.00


R024

200

1,410.00

282,000.00








$ 480,750.00


Figure 1 provides the flowchart of the production process of Racer bicycles. A narrative describing the production process is provided below.

Figure 1: Racer''s Production Process

163_Job Order Costing.png

Purchasing/Receiving

The primary materials used in the Racer''s production process consist of lightweight aluminum tubing for bicycle frames and assembled components (e.g., gear assemblies, pedals, wheels, etc.). The company''s accounting system releases purchase orders on line as needed, and the company receives material deliveries on a just in time basis.

Design

Customers purchasing the Racer work with firm technicians to custom design the bicycle frame using the company''s CAD (computer-aided design) program

Cutting/Welding/Sanding

Workers use a laser to precision cut all tubing based on the customer-driven CAD program. Workers then weld the precision cut pieces to form the bicycle frames and sand the joints to prepare the frames for painting. Highly skilled craftsmen hand weld the Racer frames due to the thin walls of the aluminum tubing. After sanding, workers hang the frames on an overhead conveyor that transports them through the next two processes.

Heat Treatment

All bicycle frames undergo a high temperature heat-treating process to strengthen the tubing walls that are weakened during the welding process. The thin walled aluminum used in the Racer requires 3 hours of heat treatment.

Painting

After heat treatment, all frames pass through an electrostatic painting process in which each frame receives an electrical charge that enhances paint adherence. Customers had a choice of red or blue for the Racer.

Assembly

Workers remove the bicycles from the overhead conveyor and partially assemble them at the factory. Workers then self inspect each finished bicycle for quality.

Packaging

Workers pack each bicycle in a box to be loaded on a truck transferring the products to the finished goods warehouse.

Manufacturing overhead are indirect costs to the product lines. Overheads are applied to each job using activity-based costing (ABC). The company has sixoverhead activity pools: (1) material handling, (2) CAD assistance, (3) labor-related, (4) heat treatment,(5) painting, and (6) quality control. The budgeted activity costs and activity driver units for Racer in 2011 were as follows.


Activity Cost Pool

Expected Cost

Activity Driver

Cost Driver Unit


Material handling

$ 360,000

Number of parts issued

180,000


CAD assistance

140,000

Number of jobs (orders)

40


Labor-related

612,000

Number of direct labor hours

48,000


Heat treatment

648,000

Number of treatment hours

12,000


Painting

645,000

Number of bikes painted

4,000


Quality control

75,000

Number of bikes inspected

4,000




$2,480,000








Material handling: This cost pool is for all costs associated with ordering, receiving, and moving materials to production. The number of parts in each Raceris 45.

CAD assistance: The costs in this category consist primarily of salaries for the technicians that assisted customers in designing their customized Racer frames. CAD assistance cost is applied to each job at the beginning of the production process.

Labor-related: This cost pool consists of overhead itemssuch as utilities, equipment depreciation, butane, and indirect materialsincurred to support the time consuming activities of cutting, welding, sanding, assembling, and packaging.

Heat treatement: This cost pool includes utilities and depreciation of the furnace.Each frame unit requires 3 hours of heat treatment.

Painting: This cost pool includes the cost of painting frames and depreciation of painting equipment. Painting cost is incurred equally per bicycle.

Quality control: This pool consists of the training cost of factory workers and the salary of factory supervisors and quality control inspectors.

The company uses a Manufacturing Overhead (MOH) account to accumulate actual overhead costs and to record overhead costs applied to jobs and Work-in Process Inventory. The MOH account balance is closed to the Cost of Goods Sold (COGS) account once a year at the end of each calendar year. Through the first 11 months of the year (January to November), the total overhead applied to all Racer jobs amounted to $2,186,350 and the total actual overhead costs allocated to Racer jobs amounted to $2,210,540. At the end of each month, overhead costs are applied to each job based on the progress made during the month. If the job is finished during the month, the overhead is applied when the job is finished.

The company maintains two direct material inventory accounts for Racer: Aluminum Tubing and Assembled Components, and an indirect material inventory account. On November 30, 2012, the balances in the Aluminum Tubing and Assembled Components accounts were $56,400 and $94,800, respectively. Additions to the direct material inventory accounts and requisitions from jobs worked during December included the following.


.

AluminumTubing

Assembled Components

Total


Purchases

$112,000

$226,000

$ 338,000


Requisitions:








R025

$ 0

$ 0

$ 0


R026

0

68,200

68,200


R027

0

56,500

56,500


R028 (300 bikes)

45,000

76,400

121,400


R029 (400 bikes)

57,600

0

57,600




$ 102,600

$ 201,100

$ 303,700


The balance in the Indirect Material Inventory account on November 30, 2012 was $14,300. Total indirect material purchase during December was $23,600. Indirect material requisitions from all jobs worked in December amounted to $25,150.

During December, the factory payroll for the Racer production consisted of the following:


Job No.

Direct Labor Hours

Factory Payroll Cost


R025

480

$ 9,600


R026

950

19,000


R027

1,230

24,600


R028

2,080

41,600


R029

1,260

25,200


Supervision and quality control



23,400


Other indirect labor



29,200






$172,600


Other operating data for December were summarized as follows.


Job No.

Number of parts issued

CAD assistance cost applied to job in Dec.?

Heat treatment hours

Number of bikes painted

Number of bikes inspected


R025

0

No

0

0

150


R026

11,000

No

0

250

250


R027

8,800

No

600

200

200


R028

13,500

Yes

900

300

0


R029

400

Yes

0

0

0


Jobs R025, R026, and R027 were completed during December. Three jobs, R023, R024, and R026 were shipped to customers during December.

Required:

I. Prepare journal entries, with supporting calculations if necessary, to record the following events during December.

1. Purchased direct materials (aluminum tubing and assembled components) and indirect materials on account.

2. Issued aluminum tubing and assembled components to production to fill job requisitions.

3. Issued indirect materials to production.

4. Incurred direct labor and indirect labor costs for jobs worked during the month.

5. Applied manufacturing overhead using the ABC cost pools and cost drivers to jobs worked during the month. (Hint: First determine the overhead activity rates using the budgeted overhead costs and cost driver information.)

6. Recognized December''s depreciation of trucks used to move materials from the storage area to the manufacturing plant and to move finished goods from the plant to the finished goods warehouse, $61,900.

7. Accrued December''s property taxes for the plant, $18,000. The taxes are scheduled to be paid in March.

8. Recorded December''s depreciation of the company''s office building, $12,500.

9. Recorded completed jobs during December.

10. Shipped jobs to customers and recorded cost of goods sold and sales revenue. All jobs are priced at 140 percent of their cost of goods sold.

11. Received bills for utilities, equipment maintenance, insurance, and other overhead items for the manufacturing plant for December, $67,000.

12. Recognized December''s depreciation of manufacturing assets (property, plant, and equipment), $102,400.

13. Received December''s freight bills for shipping finished goods to customers, $22,450.

14. Recorded December''s rent expense for the material storage area, $25,000. The rent has been prepaid in October 2011for a 12-month period.

15. Closed the balance of the MOH account to the COGS account on December 31.

II. Prepare job cost reports for all jobs worked during December. Use the following format.


Job No.

Beg. Inv., Dec. 1

Added DM Cost

Added DL Cost

MOH Applied

Total Job Cost,

Dec 31

Job Status, Dec 31
































(Note: Job status = WIP, FG, or COGS)

III. Prepare T-accounts for Aluminum Tubing Inventory, Assembled Components Inventory, Indirect Materials Inventory, Manufacturing Overhead, Work-in-Process Inventory, and Finished Goods Inventory. For each T-account, show the balance on December 1, all relevant entries occurred during December (with supporting calculations, if necessary), and the balance on December 31.

Related Discussions:- job costing

Determine the original budget line , The state legislature has voted to dev...

The state legislature has voted to develop a grant-in-aid policy to try and induce local communities to devote more resources to improving their infrastructure. Town O = Has a

Decision making, Decision Making Nature of Decision-making Deci...

Decision Making Nature of Decision-making Decision-making may fall into any type of the following categories as: 1. Short run operational decisions 2. Short run t

Methods for resolving transfer pricing conflicts, what are the advantages a...

what are the advantages and disadvantages of marginal costs plus a fixed lump-sum fee?

Compute the estimated value of inventory stolen at kji, The following are t...

The following are three independent situations where the reporting entity for which financial statements are being prepared are underlined. Every company has a December 31, 2012 ye

Reconciliation of profits, Reconciliation of Profits Reconciliation of...

Reconciliation of Profits Reconciliation of profits disclosed by Financial Accounts and Costing Accounts in an interlocking system, While interlocking cost accounting system

Prepare a cash budget, You have been asked to prepare a cash budget for Whi...

You have been asked to prepare a cash budget for Whitborrow plc for the next three months, October, November and December. The Managers are concerned that they may not have suffici

Variable costs, Variable Costs Are costs such raise or fall proportio...

Variable Costs Are costs such raise or fall proportionately along with the level of activity that is such portion of the cost of an activity which changes along with the leve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd