Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Explain field winding - dc generator, Field winding Every pole c...

Field winding Every pole core has one or more ?eld windings provided on it to make a magnetic ?eld. Whenever they carry current, they electromagnetic the poles which pro

Calculate number of cycles to fracture, Calculate number of cycles to fract...

Calculate number of cycles to fracture: If the plastic deformation is taken into consideration calculate number of cycles to fracture in above Example. Solution Δ K I

Physics, calculate wavelength fpr monocromatic light using newtons ring exp...

calculate wavelength fpr monocromatic light using newtons ring experiment notes

Determine temperature at inner surface, A long hollow cylinder has outer an...

A long hollow cylinder has outer and inner radii 150 mm and 50mm respectively. It create heat at a rate of 1kW/m³ (k= 0.5 W/m ºC). If the maximum temperature obtain at radius of 10

Determine ratio between mass flow rate to condensing steam, Determine ratio...

Determine ratio between mass flow rate to condensing steam: In steam power plant, the steam 0.1 bar and 0.95 dry enters condenser and leaves as saturated liquid at 0.1 bar an

Analysis of trusses, State the assumptions in pin joined trusses?

State the assumptions in pin joined trusses?

Calculate the torque, (a) Illustrate self-locking and self-energizing brake...

(a) Illustrate self-locking and self-energizing brakes. (b) The diameter of the drum is 250mm and the angle of contact is 90 o , If the operating force of 700 N is applied at th

Calculate the maximum and minimum stress, Calculate the maximum and minimum...

Calculate the maximum and minimum stress: A cast iron column of 200 mm diameter carries a vertical load of 400 kN, at a distance of 50 mm from the centre. Calculate the maximu

Construction activities for plant, Construction Activities for plant Co...

Construction Activities for plant Construction activities, such as shoring and bracing of excavations, lifting and rigging activities and scaffolding need to be considered as p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd