Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Injection molding, what are the finishing operation of telephone outer body...

what are the finishing operation of telephone outer body after injection molding

Heat loss in acylindrical pipe, Ask question #Minimum 1. Research the topic...

Ask question #Minimum 1. Research the topic of heat loss in a cylindrical pipe. Explain which laws of physics are used to discuss heat loss in a pipe, and briefly explain how the f

Explain conveyor and auger, Conveyor and auger Two Hydraulic motors are...

Conveyor and auger Two Hydraulic motors are provided for individual control of two conveyors and Auger, which are provided for individual control of material on both the sides

V-block and clamp - angle projection drawing, A V-block clamp consists of 3...

A V-block clamp consists of 3 components, a V-block, yoke and clamping screw.  Using a rule, measure the sketches below and produce a 3rd angle projection drawing for each componen

Determine the acceleration of each block, Determine the acceleration of eac...

Determine the acceleration of each block: In the system of associated blocks shown in figure the coefficient of kinetic friction under blocks A and C is 0.20. Determine the ac

Heat faster steel copper or brass, Which conducts heat faster steel copper ...

Which conducts heat faster steel copper or brass? Ans) Copper conducts heat faster than steel or brass. Any material that is good for conducting heat is also good for electricit

Co2 gas supply-co2 welding, CO 2 Gas Supply The CO 2 shielding gas is...

CO 2 Gas Supply The CO 2 shielding gas is supplied cylinders at high pressure (140 kg / cm 2 ). Therefore pressure regulator and flow meter are connected to reduce the pressu

Turnouts, Turnouts: A turnout is an assembly of various components wh...

Turnouts: A turnout is an assembly of various components whereby a train running on one track may be diverted to another. A sketch of a left-hand turnout is given in Figur

#clutches, #constructional features and working of Multiplate Dry Clutch

#constructional features and working of Multiplate Dry Clutch

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd