Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Expression for the maximum shearing stress, Expression for the maximum shea...

Expression for the maximum shearing stress: Obtain expression for the maximum shearing stress and maximum shearing planes. Sol.: The condition for maximum shearing stress i

Nozzle and turbine - thermodynamics, Nozzle: The pressure energy gets ...

Nozzle: The pressure energy gets converted in to kinetic energy Mass flow rate  Turbine: It is used to generate work.  The work is done by system becaus

Explain side cutting edge angle, Explain Side Cutting Edge Angle It is ...

Explain Side Cutting Edge Angle It is angle between the side cutting edge and the longitudinal axis of the tool. It avoids formation of build up edge, controls the direction of

Thyristor fundamentals of electricity , Thyristor: The thyristor is just l...

Thyristor: The thyristor is just like an ordinary diode. Thyristor

Determine the work done, Determine the work done per minute by a punch tool...

Determine the work done per minute by a punch tool making 20 working strokes min when a 30 mm diameter hole is punched in 5 mm thick plate with ultimate shear strength of 450 MPa i

Quantum mechanics, A ball is dropped from a height .If it takes0.200 second...

A ball is dropped from a height .If it takes0.200 second to cross the last 6.00 m before hitting the ground ,find the height  from which it was dropped . Ans) We need to find H

Radiographic examination of welded joints, Q. Radiographic examination of w...

Q. Radiographic examination of welded joints? Radiographic examination (RT) of welded joints shall be performed as required by the Code. Acceptance criteria shall be in accord

Ed, how to draw projections of planes

how to draw projections of planes

MOS., WHY SHEAR STRESS IS NOT MAXIMUM AT THE NEUTRAL AXIS IN TRIANGLE...ITS...

WHY SHEAR STRESS IS NOT MAXIMUM AT THE NEUTRAL AXIS IN TRIANGLE...ITS MAX IN ALL OTHER CASES BUT Y NOT IN TRIANGLE?#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd