Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Refrigeration, A refrigeration system produces 40 kg/hr of ice at 0oC from ...

A refrigeration system produces 40 kg/hr of ice at 0oC from water at 25oC. Find the refrigeration effect per hour and TR. If it consumes 1 kW of energy to produce the ice,

Machine design, how an axial thrust is a generated in a helical gear

how an axial thrust is a generated in a helical gear

Computer aided manufacturing, Computer systems to plan manage, and control...

Computer systems to plan manage, and control the operations of a manufacturing plant through either direct or indirect computer interface with the plants production resource

E=mc2, why this great equation does not apply(involved) in nuclear reaction...

why this great equation does not apply(involved) in nuclear reaction ?

Define flavorings in iges, Define Flavorings in IGES Flavorings : IGE...

Define Flavorings in IGES Flavorings : IGES contained several ways to capture the same information, which made proper interpretation largely dependent on the particular  "fla

Effect of parameters in flash butt welding, Effect of parameters in flash b...

Effect of parameters in flash butt welding Flashing Feed Rate : If excessive, there is a probability of the parts freezing together without welding. If this is insuffic

Theory of machine, write short note on''coefficient of insensitiveness''of ...

write short note on''coefficient of insensitiveness''of governors.

Shm, How we say that motion of the follower is simple harmonic motion descr...

How we say that motion of the follower is simple harmonic motion describe in practical approch

Acceleration of the two blocks, In the drawing, the weight of the block on ...

In the drawing, the weight of the block on the table is 380 N and that of the hanging block is 215 N. Ignore all frictional effects, and assuming the pulley to be massless.

Electron beam welding-nuclear applications, NUCLEAR APPLICATIONS OF ELECTRO...

NUCLEAR APPLICATIONS OF ELECTRON BEAM WELDING   Electron beam has been applied to the fabrication of fuel elements for pressurised water reactors and the distinct advantages

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd