Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Hazardous and safe areas in plant layout, Q. Hazardous and Safe Areas in pl...

Q. Hazardous and Safe Areas in plant layout? Plants implicitly involve identifiable hazards in respect to the environment, location and presence of potentially explosive materi

Airport layout - planning a new airport, Airport Layout: The main com...

Airport Layout: The main components of an airport are: (a)        Runways (b)       Taxiways (c)        Apron (d)       Terminal area (i)        Terminal build

Illustarte acceptance sampling and oc-curve, Illustarte the following (a...

Illustarte the following (a) Acceptance sampling (b) OC-Curve

Effects of air resistance. , Traveling at a speed of 16.0 m/s, the driver o...

Traveling at a speed of 16.0 m/s, the driver of an automobile suddenly locks the wheels by slamming on the brakes. The coefficient of kinetic friction between the tires and the roa

Find out the moment of inertia of a triangular area, Find out the Moment of...

Find out the Moment of Inertia of a triangular area: Find out the Moment of Inertia of a triangular area ABC with base b and height d around its base BC. Therefore or otherwis

Determine the reactions at the points of supports, Two identical rollers, e...

Two identical rollers, each of weight W= 1000N are placed by an inclined plane and a vertical wall as shown below. Determine the reactions at the points of supports A, B, and C. Su

What is data unification, What is Data Unification To optimize the UPR ...

What is Data Unification To optimize the UPR data structures, during design we study the semantics of each data type of the supported CAD systems and identify data types that a

Newer approaches to on-line scheduling, Newer Approaches To On-Line Schedul...

Newer Approaches To On-Line Scheduling  The on-line scheduling has established to be superior option than off-line scheduling upon the shop floor. The on-line scheduling looks

Input tolerance of motor, Motor shall operate successfully at rated load wi...

Motor shall operate successfully at rated load with a voltage variation of plus or minus ten percent and frequency variation of plus or minus five percent, or combined variation of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd