Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Find the weight percent of austenite present in the steel, Find the weight ...

Find the weight percent of austenite present in the steel: A 0.4% C hypoeutectoid plain carbon steel is slowly cooled from 1540 o C to (i) slightly above 723 o C and (ii) s

Explain field winding - dc generator, Field winding Every pole c...

Field winding Every pole core has one or more ?eld windings provided on it to make a magnetic ?eld. Whenever they carry current, they electromagnetic the poles which pro

Time dilation, Time Dilation The measurement of time involves the conce...

Time Dilation The measurement of time involves the concept of clocks attached at each position co-ordinate of a Lorentz frame. As a consequence of Lorentz transformations, it i

Piercing press tool, computer aided design of piercing press tool

computer aided design of piercing press tool

Maximal conductances and reversal potentials, By introducing their model of...

By introducing their model of neural excitability in 1952, Alan Lloyd Hodgkin and Andrew Huxley not only shed light on the mechanism underlying a very important phenomenon in Physi

Tolerance analysis, Tolerance Analysis This discusses the importance o...

Tolerance Analysis This discusses the importance of assigning tolerances to the dimensions. Tolerance analysis is the process of assigning suitable tolerances. Proper assignme

How is varignons theorem useful in engineerin mechanics, how is varignons t...

how is varignons theorem useful in engineering mechanics

Chemistry, What is a petroleum gas

What is a petroleum gas

Piston and piston rings - part of combustion engine, Piston and Piston Ring...

Piston and Piston Rings - Part of combustion engine: Piston: The piston reciprocates within cylinder and transmits force exerted by expanding gases to crank by means of conn

Forecasting, Forecasting: Forecasts play a vital role in determining m...

Forecasting: Forecasts play a vital role in determining material needs that constitute inventories and in establishing production plans. In this unit, you have studied the imp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd