Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Vitrification-manufacturing methods of ceramics, Vitrification This is...

Vitrification This is liquid phase sintering. It is achieved via incorporating a component that melts to viscous liquid during sintering. Such viscous liquid solidifies in gla

Solved numarical, The following observations were made during a tensile tes...

The following observations were made during a tensile test on mild steel specimen 60 mm in diameter and X mm long. Elongation with 50 KN load (within the limit of proportionality)

Flux feeding & recovery system, FLUX FEEDING & RECOVERY SYSTEM The flux i...

FLUX FEEDING & RECOVERY SYSTEM The flux is fed by gravity from the flux delivery hopper mounted on the welding head through a tube into the welding zone. Flux feeding is normally

Determine the maximum uniformly distributed load, Determine the maximum uni...

Determine the maximum uniformly distributed load: A timber beam 150 mm wide & 300 mm deep is supported simply over a span of 4 m. determine the maximum uniformly distribute

Stress distribution diagram, why stress distribution diagram is different f...

why stress distribution diagram is different for I section, T section andcircular section?

Fracton steam, calculate the dryness fractin of steam which has 1.5kg of wa...

calculate the dryness fractin of steam which has 1.5kg of water in suspension with 50kg of steam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd