Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Define boot strap air evaporative system, Define the following : (a) Boo...

Define the following : (a) Boot Strap Air Evaporative System (b) Simple VCR System (c) Advantage and disadvantage of VCR system over Air Refrigeration System (d) Reduce

Manual engineering drawing , Manual Engineering Drawing: The physical o...

Manual Engineering Drawing: The physical object is to be drawn (Do not take photographs of the object or use it as a template that you trace with) in class as an isometric dra

Computer control of machines and processes, Consider a car of mass m1 is to...

Consider a car of mass m1 is towing a trailer of mass m2 through a tow bar of stiffness k. Drag forces proportional to the car velocity (b1 v1) and the trailer velocity (b2 v2) a

Determine the heat transfer coefficient, The average heat transfer co effic...

The average heat transfer co efficient for flow of 100 o C air over a flat plate is calculated by observing the temperature time history of a 3mm thick copper slab exposed 100 o

Explain working of nozzles, Q. Explain working of Nozzles? Nozzles supp...

Q. Explain working of Nozzles? Nozzles supporting agitators, pumps, or other mechanical equipment, shall be suitably reinforced to withstand the mechanical loadings, specified

Potential energy and kinetic energy- thermodynamics, Potential energy (PE) ...

Potential energy (PE) The energy possessed by body or system by virtue of its position above the datum level. The work done is because of its falling on earth's surface. Po

Explain about wire-frame model, Q. Explain about wire-frame model? A wi...

Q. Explain about wire-frame model? A wire-frame model of an object is the simplest, but more verbose, geometric model that can be used to represent it mathematically in the com

Strength of material and engineering mechanics, Di fferentiate between str...

Di fferentiate between strength of material and engineering mechanics Sol.: Three primary areas of mechanics of solids are statics, dynamics and the strength of materials.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd