Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Show the vessel supports, Q. Show the Vessel Supports? Approved materia...

Q. Show the Vessel Supports? Approved materials and allowable stresses, shall be used for vessels and their supports. For structural shape support members in compression, wh

Define economics order quantity, a) Define Economics Order Quantity. Derive...

a) Define Economics Order Quantity. Derive, using neat diagram, the mathematical formula for economic order quantity. b) The purchase manager of an industrial unit is placing on

What is interference, a) What is Interference and show the relation for the...

a) What is Interference and show the relation for the minimum number of teeth required for a wheel. b) Show the relations for Maximum length of path of contact and Maximum lengt

Calculated the slope of the cantilever, Calculated the slope of the cantile...

Calculated the slope of the cantilever: Calculated the slope of the cantilever given in Example 6 at its free end. Solution To find out rotation in a beam we must have

Borides, Borides Borides of Mo, W, Cr, Ti and Zr find extensive indust...

Borides Borides of Mo, W, Cr, Ti and Zr find extensive industrial application. They exhibit extremely high hardness, melting point from 1800 to 3000 o C and good chemical resi

Determine the moment of forces, Determine the moment of forces: The si...

Determine the moment of forces: The side of a square ABCD is 1.60 m long .Four forces equal to 6, 5, 4 and 8 N acts respectively along with the line CB, BA, DA, DB. Determine

Quasi static process - thermodynamics, Quasi static process - thermodynamic...

Quasi static process - thermodynamics: Thermodynamic equilibrium of a system is very difficult to be realized during the occurrence of a thermodynamic process. 'Quasi-static'

Rankine cycle - thermodynamics, Rankine cycle - Thermodynamics: The ma...

Rankine cycle - Thermodynamics: The major problems of Carnot cycle is compressing very wet steam mixture from the condenser pressure up to boiler pressure. The trouble can be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd