Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Determine the orientation of neutral axis, The resultant moment M acts thro...

The resultant moment M acts through the centroid of the aluminum strut, inclined as shown.  (a) Determine the orientation of the neutral axis and show the neutral axis on a sket

Degree of super heat - thermodynamics, Degre e of Super Heat: It is d...

Degre e of Super Heat: It is difference between the temperature of superheated steam and saturation temperature resultant to the given pressure. So, the degree of superhea

Spot welding of different metals-aluminium and its alloys, Spot welding of ...

Spot welding of different metals-Aluminium and its alloys High currents and shorter welding times are necessary for these materials. Special cleaning of the surface is warrante

Explain the use of bare electrode, Q. Explain the use of bare electrode? ...

Q. Explain the use of bare electrode? This type of electrode is also known as plain electrode. No flux covers on this electrode. These types of electrodes are used for D.C. sup

Rotary converters, ROTARY CONVERTERS Historically, these type of power so...

ROTARY CONVERTERS Historically, these type of power sources were developed first for arc welding applications and even now these types are popular. These rotary converters are of

Turbine, What is the definition of stall

What is the definition of stall

What is one way shear, What is one way shear? Explain with a suitable demon...

What is one way shear? Explain with a suitable demonstration. One Way Shear This worked out seen a similar case is the case of wall footings. For square footings also the cr

Couples, explain the properties of acouple

explain the properties of acouple

Calculate the kic from the data - thick cylinder, Calculate the KIC from th...

Calculate the KIC from the data - thick cylinder: In a fracture test a 3-point bend specimen of thickness 20 mm and depth 25 mm is supported over a span of 100 mm. The specime

Define stress, Define stress: Sol.: When body is acted upon by load ...

Define stress: Sol.: When body is acted upon by load or external force, it undergoes deformation (that is, change in shape or dimension) which increases gradually. At the ti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd