Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Construction of railway line, Construction of Railway Line: Earthwo...

Construction of Railway Line: Earthwork Earthwork in embankment is made up of soil from nearby borrowpits. The soil is deposited in layers of 25 cm and compacted at o

MOS, limitations of euler''s theory

limitations of euler''s theory

Determine the thermal efficiency of cupola, With the help of neat diagrams ...

With the help of neat diagrams explain various parts of Cupola. Define its operation. How the thermal efficiency of Cupola calculated? What do you mean by Die casting process? G

Determine the interface temperature, A steel pipe with 50 mm OD is covered ...

A steel pipe with 50 mm OD is covered with a 6.4 mm asbestos insulation followed by a 25 mm layer of fiber-glass insulation [K = 0.0485 Wmk]. The pipe temperature is 393 K and the

Explain internal broaching - types of broaching, Explain Internal Broaching...

Explain Internal Broaching - Types of Broaching Internal broaching operation is adopted for producing internal surface such as holes, keyways and teeth of an internal gear for

Shaft in parallel, SHAF T IN PARALLEL: SHAF T IN PARALLEL: The sh...

SHAF T IN PARALLEL: SHAF T IN PARALLEL: The shaft are in parallel when the driving torque is applied at the junction of shafts and resisting torque is at other ends of

Air transportation, AIR TRANSPORTATION: Air transportation has grown r...

AIR TRANSPORTATION: Air transportation has grown rapidly all over the world and in India too. Its main advantages are speed, good safety record, military use, ability to serve

Project quality plan, Project Quality Plan Design verification require...

Project Quality Plan Design verification requirements for a project are to be established in the Quality Plan sub-section of the Project Execution Plan. The Lead Mechanical E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd