Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Explain about the pedestals as construction engineering, Explain about the ...

Explain about the pedestals as construction engineering. Introduction of pedestals enables the construction engineers to make up levels to supply larger bearing areas to the fo

Explain the welding process, All shell and head joints shall be double-weld...

All shell and head joints shall be double-welded butt joints with full penetration. In cases where double welding is impractical, the root pass shall be made by the GTAW process.

Scalar and vector quantities, Scalar and Vector quantities: A quantity...

Scalar and Vector quantities: A quantity is a scalar if it is completely defined by its magnitude alone. For example: Length, area, and time. While quantity is said to be vect

Time and cost analysis, Time and Cost Analysis This discusses about ce...

Time and Cost Analysis This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities br

Significance of damping coefficient, Physical significance of damping coeff...

Physical significance of damping coefficient and it''s unit.

Creating a new style-autocad, Creating a new style To create a new dime...

Creating a new style To create a new dimension style, make sure the STANDARD style is the current style, click in the Name edit box then type the name of the new style you want

Compound springs how do they work?, Ask Compound springs how do they workqu...

Ask Compound springs how do they workquestion #Minimum 100 words accepted#

Efficiency test on sand blasting, Efficiency Test on Sand Blasting:   ...

Efficiency Test on Sand Blasting:             After the study on sand blasting, the result was acceptable and the next step is planning to make order for new machine and searc

Calculate the cycle and production rate , Calculate the Cycle and Productio...

Calculate the Cycle and Production Rate for Single-Machine Robotic Cell Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the syst

Two wheeler, how to adjust the motorcycle clutch play

how to adjust the motorcycle clutch play

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd