Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Automobile, what is internal combustion engine

what is internal combustion engine

Manufacturing process for reinforced plastic parts, Manufacturing Process F...

Manufacturing Process For Reinforced Plastic Parts Two processes that are open mould and close mould are commonly utilized for manufacture of reinforced parts. Hand layup proce

What are the basic different air-fuel mixture, Describe carburetion. What a...

Describe carburetion. What are the basic different air-fuel mixture on which an engine can be operated ? Write a short note on sterling cycle. In an engine working on inlet pres

Electric resistance welding, ELECTRIC RESISTANCE WELDING Electric resis...

ELECTRIC RESISTANCE WELDING Electric resistance welding is an important and widely applied non fusion welding process. This write up covers the basic principles of various resi

Causes and remedies of motorcycle problems , CAUSES AND REMEDIES OF MOTORCY...

CAUSES AND REMEDIES OF MOTORCYCLE PROBLEMS  If Engine Overheats Causes of Problem Remedy   Incorrect spark plug make/model

Teory of machine, When doescortiles componant of acceleration occurs

When doescortiles componant of acceleration occurs

Design transfer facilities in plant, Q. Design Transfer Facilities in plant...

Q. Design Transfer Facilities in plant? Transfer facilities (e.g. pumps, piping, and conveyers) must be arranged so that no leaks can escape the confines of the bund / dike, an

Expression for the maximum shearing stress, Expression for the maximum shea...

Expression for the maximum shearing stress: Obtain expression for the maximum shearing stress and maximum shearing planes. Sol.: The condition for maximum shearing stress i

Define phase, Define Phase. A phase is a quantity of matter that is hom...

Define Phase. A phase is a quantity of matter that is homogeneous during in chemical composition and physical structure. Determine if the matter is all gas, all liquid or all s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd