Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Cylinder series test, Cylinder Series Test A series of round bars of ...

Cylinder Series Test A series of round bars of various diameters are austenitized and quenched into oil or water. The bars are long sufficient hence the cooling of section at

Engine, maximum rpm at engine

maximum rpm at engine

Equipment for resistance welding-measurements, EQUIPMENT FOR RESISTANCE WEL...

EQUIPMENT FOR RESISTANCE WELDING-Measurements Measurement of the parameters are important while fixing the parameters or testing a machine. Resistance welding instrumentation s

Illustarte acceptance sampling and oc-curve, Illustarte the following (a...

Illustarte the following (a) Acceptance sampling (b) OC-Curve

Engine management system, A preamble to engine management systems for IC en...

A preamble to engine management systems for IC engines objectives, functionalities and main features

What do you know about direct welds, Q. What do you know about Direct welds...

Q. What do you know about Direct welds? It is a welding method in which one or more electrodes oppose each other, contacting both sides of the work and with the current passing

Different characteristics of the frequently misclassified , Sentiment analy...

Sentiment analysis is a subfield of NLP concerned with the determination of opinion and subjectivity in a text, which has application in the analysis of online product reviews, rec

Project quality plan, Project Quality Plan Design verification require...

Project Quality Plan Design verification requirements for a project are to be established in the Quality Plan sub-section of the Project Execution Plan. The Lead Mechanical E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd