Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Rough-cut capacity planning, A small producer of specialist vehicles is bui...

A small producer of specialist vehicles is building a new workshop to meet expected demand for its products over a period of 5 years.  The workshop will contain three workcentres,

Define lap or fillet joint, Lap or fillet joint Lap joint is obtained b...

Lap or fillet joint Lap joint is obtained by overlapping the plates and welding their edges. The fillet joints may  be single transverse fillet, double transverse fillet or par

Explain the study of readial drilling machine with spindle, Explain the stu...

Explain the study of readial Drilling machine with spindle The objective of this study is to study of readial Drilling machine with spindle. As in Radial Drilling machine th

Answer, give me an example of law of superposition

give me an example of law of superposition

Turbines, Illustrate governing Mechanism of Francis turbine.

Illustrate governing Mechanism of Francis turbine.

#title.THERMODYNAMICS., what are the limitations of first law of thermodyna...

what are the limitations of first law of thermodynamics?

IDE101, Polygon law of forces

Polygon law of forces

Mechanical design, The second stage of the design process is to evaluate th...

The second stage of the design process is to evaluate the oxygen requirement for the organism. This is necessary so that we can establish if the vessel we construct will be capable

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd