Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Imperfect frame - truss, Imperfect Frame - truss: Imperfec t Frame ...

Imperfect Frame - truss: Imperfec t Frame An Imperfect frame is one that does not satisfies relation between numbers of members and number of joints given by equation

Analog control system for steam generator, Q. Analog Control System for ste...

Q. Analog Control System for steam generator ? The analog (modulating) control of the Steam Generators will be performed using a Process Control System (by Buyer). Detailed fun

Determine the brake power of an engine, Determine the Brake power of an Eng...

Determine the Brake power of an Engine which is running at a fixed speed of 300 r.p.m. and carries a rope brake Dynamometer. The Dead weight on the spring balance and engine readin

Resistant body-mechanism-curvilinear motion-machine, Resistant Body: A bo...

Resistant Body: A body is called resistant body if this is capable of transmitting the needed forces with negligible deformation. Machine: A machine is a mechanism or a se

Show gasket compression, Q. Show Gasket Compression? Gasket compression...

Q. Show Gasket Compression? Gasket compression can also be used as a guide for limiting bolt torque. Spiral wound gaskets should be compressed to an average of 75% of origin

Metals and melting practices - ladle, Metals and Melting Practices - Ladle,...

Metals and Melting Practices - Ladle, Limestone,Ore,Sinter Ladle : A big bucket utilized as a carrier for molten metal. Limestone : A Blast Furnace raw material that elimi

find the machine fraction, Two machining operations, A (3 minutes per part...

Two machining operations, A (3 minutes per part) and B (10 minutes per part), are performed sequentially to manufacture a part. Machines A and B produce 5% and 6% defective items,

Define verband der automobilindustries flachenschnittstelle, Verband der Au...

Verband der Automobilindustries Flachenschnittstelle (VDAFS) This interface was developed by the Association of the German Automobile Industry for the transfer of 3-D curves an

High duty tool and die steels, High Duty Tool and Die Steels: High du...

High Duty Tool and Die Steels: High duty punching tools or dies are made out of a lot of various steels of fairly high alloying contents. High-carbon high-chromium die steel

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd