Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

PLC problems, 3. How to illustrate the meaning of control system in control...

3. How to illustrate the meaning of control system in control and automation system? 4. How to illustrate the major role of CPU in a PLC and what is the major role of CPU? 5. How

Carbon and low alloy steels for welding, Q. Carbon and Low Alloy Steels for...

Q. Carbon and Low Alloy Steels for Welding? All welding of pressure retaining equipment must be completed as per the respective code, typically ANSI/ASME B31.1 or Section VIII

Determine the work done, Determine the work done per minute by a punch tool...

Determine the work done per minute by a punch tool making 20 working strokes min when a 30 mm diameter hole is punched in 5 mm thick plate with ultimate shear strength of 450 MPa i

Revited joints, which material is used in production of solid revits

which material is used in production of solid revits

Throttle valve-components of a carburettor , Throttle Valve: The throttle...

Throttle Valve: The throttle valves control the quantity of mixture supplied to the cylinder. This is controlled by throttle grip with the help of a cable. When we open throttle

Calculate all the mass-normalised modal vectors, The body, suspension and e...

The body, suspension and engine mounting system of a vehicle may be idealised as a three degree of freedom system consisting of a bar of mass 1400 kg and the centre of mass at G, 1

Brinell hardness test, Brinel l Hardness Test: Insert the Ball of dia...

Brinel l Hardness Test: Insert the Ball of diameter D in ball holder of machine. Make specimen surface free from dust and dirt. Make contact between the surface and ball b

How can heat be applied to acrylic, In most hardware stores, you can find w...

In most hardware stores, you can find what has known as a Heat Gun. Hold the heat gun about 6 inches away from the acrylic you intend on bending say the bumper on a car. They are p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd