Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Find the maximum shear stress at free end, Find the maximum shear stress at...

Find the maximum shear stress at free end: A stepped shaft ABCD, with A is fixed end and D is free end. AB = 1 m, BC = 2 m, CD = 1 m. AB is a hollow shaft of 100 mm outer diam

Define plastics molding processes, There are various methods of producing c...

There are various methods of producing components from the plastics materials which are supplied in the granular, power and other forms. Various plastics molding processes discu

Expression for the maximum shearing stress, Expression for the maximum shea...

Expression for the maximum shearing stress: Obtain expression for the maximum shearing stress and maximum shearing planes. Sol.: The condition for maximum shearing stress i

Steam turbine, calculation of stage wise specific steam consumption and pow...

calculation of stage wise specific steam consumption and power output

External coatings on vessels, Q. External coatings on vessels? All pres...

Q. External coatings on vessels? All pressure vessels that will be installed underground shall have an external coating applied according to the following procedure: • All e

Compute the diameter of a solid shaft, Compute the diameter of a solid shaf...

Compute the diameter of a solid shaft: Compute the diameter of a solid shaft transmitting 150 kW at 25 rpm, if the maximum shear stress in the shaft is not to exceed 70 MPa. C

Calculate for the resultant of the force system, Calculate for the resultan...

Calculate for the resultant of the force system: A rectangle ABCD is having sides AB = CD = 80 mm and BC = DA = 60 mm. Forces of 150 N each of them act along AB a

Governors, how to find mass of sleeve in porter governor

how to find mass of sleeve in porter governor

Applications of Numerical Methods in Mechanical Engineering, Various applic...

Various applications of numerical methods in the field of m=numerical engineering.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd