Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Laminar flow, Consider fully developed laminar flow with constant propertie...

Consider fully developed laminar flow with constant properties in a circular tube. Let there be heat transfered  to or from  the fluid at a constant rate per unit of tube length.Ad

Describe polythionic acid corrosion, Q. Describe Polythionic Acid Corrosion...

Q. Describe Polythionic Acid Corrosion? Although it is not typically thought of as high temperature corrosion, polythionic acid stress corrosion cracking occurs in areas where

Describe the type of facing and backing sand, Q. Describe the type of Facin...

Q. Describe the type of Facing and Backing sand? Facing sand. This sand is used directly next to the surface of the pattern and comes into contact with the molten metal when th

Mechanical design of the blowdown systems, Q. Mechanical design of the blow...

Q. Mechanical design of the blowdown systems? Mechanical design of the blowdown systems shall be sized for a continuous blowdown of a minimum of 1.0% of MCR. Fabricator may re

V pulley design, #wHAT WILL BE THE PULLEY CRITERIA TO DECIDE THE RPM

#wHAT WILL BE THE PULLEY CRITERIA TO DECIDE THE RPM

Total tension in cable of the elevator, Total tension in cable of the eleva...

Total tension in cable of the elevator: An elevator having weight 5000N is ascending with an acceleration of 3m/sec 2 . During this ascent its operator which is having weig

Maintenance requirement at storage tanks, Q. Maintenance requirement at sto...

Q. Maintenance requirement at storage tanks? Little maintenance is required at storage tanks; sometimes access is required for equipment used to remove accumulated solids (this

Forces working on dam, Forces working on dam: Let a dam retaining wate...

Forces working on dam: Let a dam retaining water as illustrated in Figure (a). What are the forces working on it? Solution The forces working on dam are as follows:

Capp for machining process, CAPP for Machining Process This explained ...

CAPP for Machining Process This explained mainly two different approaches to Computer Aided Process Planning, i.e.  (a) Variant approach, and  (b) Generative approach.

Importance of molliers diagram, Describe the key terms i. Write two diff...

Describe the key terms i. Write two differences between turbine and boiler. ii. Write importance of mollier's diagram iii. Compare the rankine cycle with carnot cycle in k

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd