Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Projectles on an inclined plane, a misile is fired at speed v and an angle ...

a misile is fired at speed v and an angle m that is inclide at an angle r to the horizontal.calculate the range

What are the basic use of sand rammer, Q. What are the basic use of Sand ra...

Q. What are the basic use of Sand rammer? It is the apparatus of make specimens of moulding sand, for tests such as - permeable test, the various strength tests, and shatter te

Cooling system, Cooling System: A cooling system is designed to remove a p...

Cooling System: A cooling system is designed to remove a part of heat generated inside the cylinder that may be harmful to engine parts. The heat is produced in the engine cylinde

Plates-battery components , Plate : These are also known as electrodes. Th...

Plate : These are also known as electrodes. There are two types of group of plates - Positive and Negative. Each group contains more than one plate. A group of positive plates is

Describe about water disposal system, Q. Describe about Water disposal syst...

Q. Describe about Water disposal system? Disposal water from the Evaporator Package is cooled down to 50°C by the Disposal Cooler and is sent to Disposal Water Tank(s). Disp

THERMODYNAMICS, what is second law of thermodynamics

what is second law of thermodynamics

Fermenter dimensions and mechanical design, Once the total volume of an ind...

Once the total volume of an individual vessel has been established the detailed dimensions or mechanical design can be performed. Much of this is based on "Rules of Thumb"  built f

How do we calculate the productivity, Describe productivity. How do we calc...

Describe productivity. How do we calculate the productivity? Enumerate various factors effecting the productivity. Define various ways for the improvement of productivity.

Current-fundamentals of electricity , Fundamentals of Electricity Cu...

Fundamentals of Electricity Current: The flow rate of charge or electrons with respect to time is known as current. It is measured in ampere (A).

AOC, The objective of the project is to protect damage of the DC motors. If...

The objective of the project is to protect damage of the DC motors. If the motor is not working it will be shown with red light, if working normally then green and if working at a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd