Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Construction of boiler, CONSTRUCTIO N FEATURES : Comprises of a water ...

CONSTRUCTIO N FEATURES : Comprises of a water drum which is connected to two headers at the front and back ends. The headers are connected by large number of water tubes which

Files tool and equipment , Files: Files are used to remove excess metal by...

Files: Files are used to remove excess metal by cutting action. These can be classified according to their length, shape, cross-section.

What is the pressure difference between the stations , (Bernoulli equation ...

(Bernoulli equation along a streamline) Water flows from station (1) to (2) around an expanding corner pipe, 3m high. The speed along the center streamline is 10 m/s at (1) and 5

Determine the deflection at free end, Determine the deflection at free end:...

Determine the deflection at free end: For the beam illustrated in Figure, determine the deflection at free end and the maximum deflection. Figure Solution R

Access and maintenance for pumps, Pumps should be grouped together with goo...

Pumps should be grouped together with good maintenance access to the motor, and good personnel access to seals and suction / discharge valves. Maintenance access should allow for r

Computer control of machines and processes, Consider a car of mass m1 is to...

Consider a car of mass m1 is towing a trailer of mass m2 through a tow bar of stiffness k. Drag forces proportional to the car velocity (b1 v1) and the trailer velocity (b2 v2) a

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Physics, Explain the super position of waves with neat diagrams

Explain the super position of waves with neat diagrams

Determine the angular-velocity of uniform bar, Determine the angular-veloci...

Determine the angular-velocity of uniform bar: A uniform bar of length l and mass M is hinged at its end B and is released from its horizontal position BA. Determine its angul

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd