Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Power sources for arc welding, POWER SOURCES FOR ARC WELDING Electric ...

POWER SOURCES FOR ARC WELDING Electric arc welding processes constitute a majority of all the welding processes. Most of the weldable materials can be joined by arc welding. D

Open belt drive, Open belt drive: An open belt drive connects the two...

Open belt drive: An open belt drive connects the two pulleys 120cm and 50cm diameter on parallel shafts which are apart 4m. The maximum tension in belt is 1855.3N. Coefficien

Flange facing and surface finish, Q. Flange Facing and Surface Finish? ...

Q. Flange Facing and Surface Finish? Raised face flange facings are preferred. Flat face flanges to be used only when mating with like equipment (fabricated from brittle mat

Scissors crossing, Scissors Crossing: A scissors crossing consists of...

Scissors Crossing: A scissors crossing consists of two crossovers overlapping each other. It is shown in Figure. Figure: Scissors Crossover Triangles

Evaluate secure axial load, Evaluate secure axial load: A small piece ...

Evaluate secure axial load: A small piece of ISA (200 × 100 × 15) angle carries a compressive load, the line of action of which coincides along the intersection of the middle

Resultant of non-coplanar force system, Resultant of Non-coplanar Force Sys...

Resultant of Non-coplanar Force System: The resultant of a system of coplanar forces can be attained by adding up two forces through law of parallelogram at a time and after t

Thermodynamic process - thermodynamics, Thermodynamic process - Thermodynam...

Thermodynamic process - Thermodynamics: Thermodynamic system undergoes changes because of the energy and mass interactions. Thermodynamic state of system changes because of th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd