Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Entropy, why entropy always tends to increase?

why entropy always tends to increase?

Stress and deflection analysis in i-beam, You are required to formulate the...

You are required to formulate the loading and boundary conditions using the FE code and evaluate the stress distribution and end deflection of the beam using the ABAQUS code and vi

Nominal strain and true strain, Nominal Strain and True Strain: Nomina...

Nominal Strain and True Strain: Nominal Strain is ratio of change in length per initial length.  Nominal strain =  Change in length / Initial length = Δ L /   L

Calculate the minimum required cross-sectional area, A lifting shackle in a...

A lifting shackle in a glass-making factory is made from a special high-temperature stainless steel. It is expected that the shackle will experience a tensile load of 5kN and th

Copper alloys, Copper Alloys Some alloys of copper are employed in ind...

Copper Alloys Some alloys of copper are employed in industry for varying causes. Copper forms alloys along with zinc or the brasses, tin or the bronzes, along with tin and pho

Describe span of bridge and varying depth, The press tressed bridge structu...

The press tressed bridge structure would look like as shown below,   The following factors influences the decision to select the particular prestressing, 1/Span of br

(APPLIED THERMODYNAMICS, AA steam power plant operates on a reheat Rankine ...

AA steam power plant operates on a reheat Rankine cycle. Steam enters the high-pressure turbine at a pressure of 12.5 MPa and temperature of 550 oC at a rate of 15 kg/s. It leaves

Steps for method of joint, Step s for Method of Joint: To find force ...

Step s for Method of Joint: To find force in member of the truss by this method, the three Steps which are given below are followed. Step-1 : Calculate reaction at su

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd