Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Sewage treatment, Q. Sewage Treatment? Unless located in a metropolitan...

Q. Sewage Treatment? Unless located in a metropolitan area, it is common for plants to have sewage treatment facilities for disposal of sewage and grey water generated in the p

Find out the wave retarders in tandem, Wave Retarders in Tandem Write th...

Wave Retarders in Tandem Write the Jones matrices for the following retarders: (a) A π/2 wave retarder with the fast axis along the x direction. (b) A π wave retarder with

Sialons, Sialons Mixture of silicon nitride, aluminium nitride and alu...

Sialons Mixture of silicon nitride, aluminium nitride and alumina is hot pressed to acquire a product largely called as sialon. In the resulting product the structure has part

Revited joints, which material is used in production of solid revits

which material is used in production of solid revits

What are the objectives of the earth pressure, What are the objectives of t...

What are the objectives of the earth pressure and retaining structures? After knowing all concepts about the same you should be able to learn: a. Know the field situations w

Find out m.i. of t section, Q. Find out M.I. of T section as shown in figur...

Q. Find out M.I. of T section as shown in figure given below about X - X and Y - Y axis through center of gravity of the section.   Figure Sol.:

Determine the velocity, Question The three freight cars are rolling alo...

Question The three freight cars are rolling along the horizontal track with the velocities shown in the Figure. After the impacts occur the three cars become coupled together a

What is a positive displacement pump, A positive displacement pump is a liq...

A positive displacement pump is a liquid or gas to move by trapping a fixed amount of fluid or gas and then forcing (displacing) that trapped volume into the discharge pipe. Positi

Angular shear stress.., how is angular shear stress distributed in between ...

how is angular shear stress distributed in between two stanchions

Explain concept of a corner or angled window, Question 1: Retail design...

Question 1: Retail design tends to be rapid turnover business. Your potential client needs a window display for his retail sports wear shop for the summer sales. The assumed bu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd