Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Constant mesh type gear box, Constant Mesh Type Gear Box : Most of the ge...

Constant Mesh Type Gear Box : Most of the gearboxes on motorcycles are "constant mesh". That means all the gears are constantly meshed with one another and are always spinning. T

Show the procedure of welding of vessels, Q. Show the procedure of Welding ...

Q. Show the procedure of Welding of vessels? Welding of vessels, including pressure retaining parts and attachments thereto, shall be performed utilizing Welding Procedures, We

Determine the net rate of work output, A piston and a cylinder machine obta...

A piston and a cylinder machine obtains a fluid system, which passes through a complete cycle of four processes. In the mean while a cycle the sum of all heat transfer is 150KJ and

Explain the advantages of automation, Explain the Advantages of Automation ...

Explain the Advantages of Automation 1. There is an increase in productivity. 2. The unit cost is reduced as larger number of components can be manufactured in shorter time

Pressure, relation between fluid pressure and velocity

relation between fluid pressure and velocity

Frames, Frames: You have been introduced to the analysis of frames. By...

Frames: You have been introduced to the analysis of frames. By going through this unit, you may identify frames and differentiate them from trusses. The method for analyzing f

Thermodynamics, Two kg Ammonia (mA) at PA = 300 kPa and TA = -10ºC and 1 kg...

Two kg Ammonia (mA) at PA = 300 kPa and TA = -10ºC and 1 kg Ammonia (mB) at PB = 300 kPa and TB = 100ºC are mixed in a constant pressure and adiabatic process. Find the following:

Find out the quality, Find out the quality: ABC industries manufacture...

Find out the quality: ABC industries manufacture X-band radar scanners utilized to detect speed traps. The printed circuit boards in the scanners are bough from an outside ven

Evaluate the speed of shaft, Two shafts A and B are co-axial. A gear C (50 ...

Two shafts A and B are co-axial. A gear C (50 teeth) is rigidly mounted on shaft A. A compound gear D-E gears with C and an internal gear G. D has 20 teeth and gears with C and E h

Calculate the angle of heel, a) Derive a mathematical expression for stabil...

a) Derive a mathematical expression for stability of an automobile while accelarating in a curved path? b) A motorcycle and its rider together have a mass of 250Kg and their cen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd