Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Railway station - transport engineering, Railway Station: Types of ...

Railway Station: Types of Stations There are the following types of stations: (a) Terminal stations, Howrah station in Kolkata and Mumbai Central being good exampl

Compute the displacement of the particle, Compute the displacement of the p...

Compute the displacement of the particle: The acceleration time diagram for particle is as specified below .Computed velocity of the particle at several time intervals, plot v

Diode-fundamentals of electricity , Diode: It allows the current to flow ...

Diode: It allows the current to flow in one direction only and offers infinite resistance in other direction. It rectifies the alternating current that is why we call it rectifie

Can you explain corners and fillets, Q. Can you explain Corners and fillets...

Q. Can you explain Corners and fillets ? Corners and fillets The intersection of the surfaces in casting must be smooth and forms no sharp angles. For this, the external a

Boiler, boiler water hammering

boiler water hammering

Clutch free play adjustment of motorcycle, Clutch Free Play Adjustment : A...

Clutch Free Play Adjustment : A smooth operation of clutch ensures the smooth running of motorcycle; hence it is essential to maintain a proper clutch free play. STEPS

Stages in making a spot welding, Q.Show the procedure of spot welding ? ...

Q.Show the procedure of spot welding ? The steps involved in making a spot weld are listed below and shown but before spot welding one must make sure that (i) The job is clea

Determine the average time in the queue, A machine machines parts in exactl...

A machine machines parts in exactly 1.5 minutes. The machine requires tool change according to an exponential distribution with a mean of 12 minutes between occurrences. The tool c

Low lube oil pressure security in API612 , What type of low lube oil securi...

What type of low lube oil security recommended for API612 steam turbines.(Electronic/Mechanical). Please give refrences

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd