Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Hydrostatic pressure, can a swimming pool that is full be cracked or lifted...

can a swimming pool that is full be cracked or lifted by hydrostatic pressure?

Steam turbine, Stea m Turbine: INTRODUCTIO N:   Steam turbine is ch...

Stea m Turbine: INTRODUCTIO N:   Steam turbine is chief mover in which rotary motion can be obtained by a gradual change of momentum of steam. The force exerted on blade is

Determine the equivalent evaporation, Illustrate how the efficiency of Rank...

Illustrate how the efficiency of Rankine Cycle can be improved by the use of Regenerative and Reheat heating. (b) During a test on boiler trial the following data were obtained

Coated electrodes and their classifications, COATED ELECTRODES AND THEIR CL...

COATED ELECTRODES AND THEIR CLASSIFICATIONS Welding technology has changed tremendously over the past decades. Its application is found in all sectors of industries, smaller or l

Difference between the open and closed systems, Provide short answers to th...

Provide short answers to the following questions: a)   What the necessary condition for a heat transfer process to occur? b)   What is a difference between the steady state c

Determine the shear stresses, A composite shaft consists of copper rod of 3...

A composite shaft consists of copper rod of 30mm diameter enclosed in a steel tube of external diameter 50mm and 10 mm thick. The shaft is needed to transmit a shaft is required to

Changes in mechanical properties along with tempering, Changes in Mechanica...

Changes in Mechanical Properties along with Tempering: Tempering enhances the toughness and ductility of quenched steel though decreases hardness. Following figure demonstrate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd