Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Compute the total drag force on the plate , A uniform air stream with veloc...

A uniform air stream with velocity U = 10m/s flows over a flat plate of length 10 meters in the first meter the boundary layer is laminar but beyond this point boundary layer is fu

Define heat for electrical resistance welding, Q. Define Heat for electrica...

Q. Define Heat for electrical resistance welding? The heat, H for electrical resistance welding is generated by passing a large electrical current ( of the order of 3000 to 100

Vectors, Resolving vectors into I j k component

Resolving vectors into I j k component

Derive steady flow energy equation, Derive steady flow energy equation?Also...

Derive steady flow energy equation?Also give applications of steady of steady flow energy mathematical equation?

Find out moment of inertia, Find out Moment of Inertia: Find out Momen...

Find out Moment of Inertia: Find out Moment of Inertia of an I shaped area around its centroidal axis as illustrated in Figure.  Solution  (i)        The area of

Electrodes- storage and handling of electrodes, STORAGE AND HANDLING OF ELE...

STORAGE AND HANDLING OF ELECTRODES It is recommended that the electrodes should be stored in a warm and dry place. Generally, conditions of storage in the shop are not very condu

Motion of two bodies - smooth surface and smooth pulley, Motion of two bodi...

Motion of two bodies - Smooth surface and smooth pulley: THE HORIZONTAL SURFACE IS SMOOTH AND STRING IS PASSING OVER SMOOTH PULLEY: Figure shows two weights W 1 and W 2 c

Why is stress relieving in post-weld treatment necesaary, In case of welded...

In case of welded vessels why is stress relieving in the form of post-weld treatment necessary? When a metal is welded together the point at which two surfaces are joined are s

Determine the thermal conductivity of the rod, One end of a rod, 35 mm in d...

One end of a rod, 35 mm in diameter, is diped into a furnace with the other end projecting in the outer air. After the steady state is obtained, the temperature of the rod is evalu

Computer control system in flexible manufacturing system, Computers control...

Computers control system in flexible manufacturing system

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd