Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Determine the eigen values, Determine the eigen values and eigen vectors of...

Determine the eigen values and eigen vectors of the matrix

Stress strain curves, Stress Strai n Curves (Tension): When a bar or ...

Stress Strai n Curves (Tension): When a bar or specimen is subjected to a gradually increasing axial tensile load, the strains and stresses can be found out for number of loa

Physics, State and explain parallelogram law of vectors

State and explain parallelogram law of vectors

Tungsten inclusions, Tungsten Inclusions Tungsten inclusion is a disconti...

Tungsten Inclusions Tungsten inclusion is a discontinuity found only in TIG welding. Particles of tungsten from the electrode can be embedded in a weld when improper welding proc

Melting point, What is melting point of aluminium?

What is melting point of aluminium?

Define CAD and its applications, Computer-Aided Design (CAD) CAD is use...

Computer-Aided Design (CAD) CAD is used in design and development of new products in a diversity of applications both at commercial/industrial and on a home basis. Illustration

Pressure at bottom of a cone, I have a tank that has a 30" dia at the top...

I have a tank that has a 30" dia at the top and is 24" deep. It connects to a cone that is 30" dia at the top and goes to a 15" dia in 12". I plan on filling the tank with golf ba

Level of safety organization, Level of Safety Organization This level ...

Level of Safety Organization This level comprises representatives of safety departments working at shop floor level or along with workers. The personnel will in fact implement

What is windsocks, Windsocks shall be installed at plant facilities handlin...

Windsocks shall be installed at plant facilities handling flammable gases, volatile liquids or toxic materials and also at helipads (may require lighting if night flights are inten

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd