Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Determine the root of equation, Calculate the value of ∫ Π/2 sinx dx by Si...

Calculate the value of ∫ Π/2 sinx dx by Simpson's 1/3 rule using 11 ordinates. Determine the root of equation xe x = cosx using secant method correct to four decimal places.

Give shear force and bending moment diagrams, A simply supported beam ABC w...

A simply supported beam ABC with supports at A and B , 6m apart and with an overhang BC 2 metres long takes uniformly distributed load of 1.5 KN/metre length over the entair length

Calculate the magnitude of forces, The greasted and least resultant of forc...

The greasted and least resultant of forces performing on a body are 35 KN and 5 KN respectively. Calculate the magnitude of forces. What could be the angle between these forces if

What do you mean by risers and downcomers, Q. What do you mean by Risers an...

Q. What do you mean by Risers and Downcomers? Risers and downcomers shall be staggered along the shell of the WHB and steam drum for uniform water/steam circulation in the syst

Determine the percentage increase in power possible, An open belt connects ...

An open belt connects two flat pulleys. The pulley diameters are 300 mm and 450 mm and the corresponding angles of Cap are 160 o and 210 o . The smaller pulley runs at 200 r.p.

Determine the dimensions of the tank, Determine the dimensions of the tank:...

Determine the dimensions of the tank: A conical water tank is to be fabricated from steel plate of 10 mm thickness. The shell should contain an apex angle (α) 15o. If the perm

Torsion of cylinder and torsion rigidity, I want complete information about...

I want complete information about the topic torsion of cylinder and torsion rigidity.if I have to make a project on this topic then how should I make it. Please help me sir.

Special commands for cad, Throughout this project, you'll find questions th...

Throughout this project, you'll find questions that will direct you to think about how you're creating the drawing. Although you should not submit the answers to these questions, a

Composite materials, Composite Materials While two various materials w...

Composite Materials While two various materials which neither react chemically nor dissolve in every other are combined together so they form a composite materials. Individual

Define phase, Define Phase. A phase is a quantity of matter that is hom...

Define Phase. A phase is a quantity of matter that is homogeneous during in chemical composition and physical structure. Determine if the matter is all gas, all liquid or all s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd