Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Creep, Creep in belt drive

Creep in belt drive

Determine the time response for the system, For two waves period, determine...

For two waves period, determine the time response x(t) for the system (ignoring viscous damping effect only)  Give=n: X0=0.09615 , θ(radians)=0.110*π , μk=0.80000 , μs=0.90000 , K=

Applications of high temperature materials, Q. Applications of high tempera...

Q. Applications of high temperature materials? A brief description of materials of construction used for common high temperature components in furnaces, boilers, superheaters,

Compute the deflection and maximum bending stress, For the beam shown in Fi...

For the beam shown in Figure compute the deflection at the element nodes. The modulus of elasticity is psi and the cross section is as shown in the figure. Also compute the maximum

What are the special considerations in planning, What are the Special Consi...

What are the Special Considerations in Planning The dimensions of the foundation should be such that for low-speed machines (operating speed less than 500  rpm) the natural fre

Show conceptual layout of plant, Q. Show Conceptual Layout of plant ? D...

Q. Show Conceptual Layout of plant ? During the Evaluate phase of a project, the early concept design considers broad information of the expected installation, and its basic cr

Evaluate the power output of turbine, Evaluate the power output of turbine:...

Evaluate the power output of turbine: Q: A turbine in steam power plant operating under steady state conditions receives the superheated steam at 3MPa and 350ºC at the rate o

Steam generator piping, Q. Steam Generator Piping? Control valves shall...

Q. Steam Generator Piping? Control valves shall be Fisher or Purchaser-approved equal. All valves shall be detailed by size, rating, make, model number, and materials Two

Quantum mechanics, A ball is dropped from a height .If it takes0.200 second...

A ball is dropped from a height .If it takes0.200 second to cross the last 6.00 m before hitting the ground ,find the height  from which it was dropped . Ans) We need to find H

Write down the maintenance schedule spark plug replacement, Write down the ...

Write down the maintenance schedule for the following : (a) Spark plug replacement. (b) Engine oil change/ top up period. (c) Steering head bearing.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd