Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Calculate transmitted force, A machine having a mass of 100 Kg and supporte...

A machine having a mass of 100 Kg and supported on springs of total stiffness 7.84 x 105 n/m has an unbalanced rotating element which results in a disturbing force of 400 N at a sp

Calculate the normal force, Problem You are playing tetherball because ...

Problem You are playing tetherball because you are seven years old and you have nothing better to do.  If the tetherball has a mass of 1 kg and the rope is 1.5 m long and can w

Material selection by temperature range, Q. Material selection by temperatu...

Q. Material selection by temperature range 750° to 1100°F (400° to 600°C) ? Plain carbon steels are usually limited to a maximum operating temperature of 750°F (400°C).  There

Wilson hartnell governor, how to design and fabricate wilson hartnell gover...

how to design and fabricate wilson hartnell governor?

Determine tension in horizontal rope , Determine tension in horizontal rope...

Determine tension in horizontal rope: Q:  A 500N cylinder, 1 m in diameter is loaded between cross pieces AE and BD that make an angle of 60º with each other and are pinn

Determine the reaction - cantilever, Determine the reaction: The cant...

Determine the reaction: The cantilever is shown in the figure given below; determine the reaction when it is loaded.   In cantilever at fixed end ( A ) there is three reac

Monte Calro for aerodynamic load simulation.., I have experimental results ...

I have experimental results for a 2D model and a matlab script that computes the aerodynamic loads on that 2D model.When we compare experiment with the theory I have noted that the

Determine moment of the force about the origin, (a) What do you understand ...

(a) What do you understand by couple moment. Is it a free vector ? (b) A force F = 10i + 6j - 6k N performs at a position (10, 3, 4) m relative to a coordinates system. Determin

Cad-cam data exchange, CAD-CAM Data Exchange: The interface SET transf...

CAD-CAM Data Exchange: The interface SET transferred information on wire-frames, surfaces, B-representation and FEM models as well as technical drawings and scientific data. I

Illustrate the first law of thermodynamics, (a) Illustrate the First Law of...

(a) Illustrate the First Law of Thermodynamics for a closed system undergoing a cycle. (b) A piston and cylinder machine contains a fluid system which passes through a complete

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd