Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Study and design of pattern, TO Study And Design Of Pattern A pattern i...

TO Study And Design Of Pattern A pattern is an element used for making cavities in the mould, into which molten metal is poured to produce a casting. It is not an exact replica

CO2 welding-equipment, CO 2 WELDING CO 2 welding is one of the variat...

CO 2 WELDING CO 2 welding is one of the variations of t he GMAW (Gas Met al Arc Welding) process which is now used for welding most structural and alloy steels. The operating

Spray transfer, Spray Transfer In a gas shield of argon or argon rich m...

Spray Transfer In a gas shield of argon or argon rich mixture [i.e., Ar+CO 2 gas mixture containing more than 80 % argon] the metal transfer changes from globular to spray typ

Show modular structures layout, Q. Show Modular Structures layout? Outs...

Q. Show Modular Structures layout? Outside dimensions and weight of truckable modules shall not exceed limits specified, Modular Structures in GS-904-0103. Minimum head clearan

Dryness fraction, how do you differentiate between wet steam and dry steam?...

how do you differentiate between wet steam and dry steam?

Explain about the collapsible soils and subsidence, Collapsible Soils and S...

Collapsible Soils and Subsidence There are soils which are quite stable when dry and they show large volume changes on wetting under load. Examples of  these soils are loess (w

Determine the slopes at free end - cantilever beam, Determine the slopes at...

Determine the slopes at free end - cantilever beam: A cantilever beam of length l carries a point load W at a distance l  /4 from free end. Determine the slopes at free end

Applications and disadvantages of electro chemical machining, Applications ...

Applications and Disadvantages of Electro Chemical Machining Disadvantage of Electro Chemical Machining 1. The tools are more difficult to design. 2. Initial cost is hi

Plates-battery components , Plate : These are also known as electrodes. Th...

Plate : These are also known as electrodes. There are two types of group of plates - Positive and Negative. Each group contains more than one plate. A group of positive plates is

Working of torsion dynamometer, Can you explain the principal on which a to...

Can you explain the principal on which a torsion Dynamometer works ? Illustrate with details the evaluation involved in finding the power transmitted.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd