Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Forces working on dam, Forces working on dam: Let a dam retaining wate...

Forces working on dam: Let a dam retaining water as illustrated in Figure (a). What are the forces working on it? Solution The forces working on dam are as follows:

Cermets-alloys for cutting tools, Cermets Such are the variation of ce...

Cermets Such are the variation of cemented carbides while the carbides of W and Ti are solidified in the softer matrix of Co and Nickel to get high hardness, resistance to hig

What is metal jacketing, Q. What is Metal Jacketing? a) Metal jacketing...

Q. What is Metal Jacketing? a) Metal jacketing shall be Alcan T-3000-H14 series, T-1100-H14 or approved equivalent stucco embossed aluminum with a factory applied moisture barr

What is ifc in project management, Q. What is IFC in project management? ...

Q. What is IFC in project management? This revision is to be used as a basis for preparing detailed design for final checking of IFC drawings by other disciplines, for incorpo

Centre of gravity and centroid, Q.   Explain the terms centre of gravity an...

Q.   Explain the terms centre of gravity and centroid. Sol. : A point can be found out in a body through which resultant of all such parallel forces acts. This point through

Illustrate kinematics links, (a) Illustrate Kinematics Links, Chin, Mechani...

(a) Illustrate Kinematics Links, Chin, Mechanism and Pair with their classification and examples. (b) Compare between structure and Machine.

Newton s rings, how i make assigment for newton s ring

how i make assigment for newton s ring

The auto component sector-automobiles industry growth , The auto component ...

The auto component sector has also posted significant growth of 20 percent in 2003-04, and achieved a sales turnover of Rs. 30,640 crore (US$ 6.7 billion). Further, there is a pote

Computer control system in flexible manufacturing system, Computers control...

Computers control system in flexible manufacturing system

Simple rules-priority rules-conventional priority rules, Simple Rules F...

Simple Rules FIFO (first in first out) PN j = t aj SPT (shortest processing time) PN j = o j ODD (earliest operation due dates) PN j = t dj EDD (earliest job due

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd