Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Pmi testing of alloy materials, Q. Show PMI testing of alloy materials? ...

Q. Show PMI testing of alloy materials? Suppliers and Construction Subcontractors are required to verify or conduct PMI testing of alloy materials that they procure and use and

Seismometer-accelerometer-accelerometer, Seismometer : this is a transduc...

Seismometer : this is a transducer in which signal is proportional to the displacement. Accelerometer : This is a transducer in which signals is proportional to the a

Biofluids mechanics, in fontan circulation that is represented as a circuit...

in fontan circulation that is represented as a circuit

Classification of internal combustion models of engine, CLASSIFIC A TIO ...

CLASSIFIC A TIO N: 1.     In accordance to number of strokes per cycle: (a) Two stroke          (b) Four stroke. 2.     In accordance to the fuel being used: (a)

Roller conveyors, Roller conveyors are flat circular or spiral. They con...

Roller conveyors are flat circular or spiral. They consist of rollers supported in frames over which materials are allowed to move. They are driven through gravity. Genera

Moment of couple - mechanics, Moment of couple: Sol.: The moment of ...

Moment of couple: Sol.: The moment of couple is the product of the force (that is one of the forces of two equal and opposite parallel forces) and the arm of couple. Math

Evaluate stress in fibre, Evaluate stress in fibre: Example, the matri...

Evaluate stress in fibre: Example, the matrix material can be stressed to its full strength of 80 MPa, calculate the allowable % of broken fibres. What will be the stress in f

Calculate force required for equilibrium, Calculate force required for equi...

Calculate force required for equilibrium: A member ABCD is subjected to the point loads P 1 , P 2 , P 3   an d P 4   as shown in the figure given below

Determine the springs needed to absorb the energy, Determine the springs ne...

Determine the springs needed to absorb the energy: A vehicle weighing 28 kN and running at 2.5 m/sec is to be brought to rest by a buffer springs. Determine the number of spri

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd