Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Form tool design, I want to make a form tool for lathe for making a convex ...

I want to make a form tool for lathe for making a convex groove of 3 mm radius. tool material will be tungsten carbide. I want to know the dimensions of tool. What is the procedure

Screw driver-tool and equipment , Screw Driver: Screwdrivers of different ...

Screw Driver: Screwdrivers of different sizes are used to tighten or loosen screws. These are made of vanadium steels. A typical screw driver is shown in Figure. Fig

Advantages of two stroke engine over a four stroke engine, Advantages of tw...

Advantages of two stroke engine over a four stroke engine: The advantages of two stroke engine over a four stroke engine are stated below: 1. A two stroke engine has twice

Soldering, Soldering This is a group of join process, which generates, co...

Soldering This is a group of join process, which generates, coalescence of materials by heating them to a suitable temperature and by using a filler metal having a melting point

Stress strain curves, Stress Strai n Curves (Tension): When a bar or ...

Stress Strai n Curves (Tension): When a bar or specimen is subjected to a gradually increasing axial tensile load, the strains and stresses can be found out for number of loa

Wedge friction, WEDG E FRICTION: Explain how wedge is used for raisi...

WEDG E FRICTION: Explain how wedge is used for raising heavy loads. Also give principle of it. Sol.: Principle of wedge: A wedge is small piece of material having two

Explain carnot cycle, Illustrate modified Rankine cycle in detail with p-v ...

Illustrate modified Rankine cycle in detail with p-v and T-S diagrams. Explain Carnot cycle in detail with T-S and P-V diagram, and also write expression for thermal efficiency,

Agriculture, i am thinking that neglecting the foot gears and put hand gear...

i am thinking that neglecting the foot gears and put hand gears instead of it in two wheelers .so what is the procedure

Abrasive machining processes, Abrasive Machining Processes Such machin...

Abrasive Machining Processes Such machining processes are precision machining processes. They generate work-piece surfaces along with a high degree of surface smoothness and d

Fluid Mechanics, I would like a help for my fluid mechanics assignment

I would like a help for my fluid mechanics assignment

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd