Illustrate the relationship between time and cost, Software Engineering

Assignment Help:

Q. Illustrate the relationship between Time and cost?

In software projects, time cannot be freely exchanged against cost. Such a trade off is limited by the nature of the software development. For a given organization, developing software of size S, the quantity obtained is constant. We know

K1/3 td4/3 =S/C

If we raise power by 3 afterwards Ktd4 is constant for constant size software. A density of the development time td will produce an increase of manpower cost. If compression is excessive not merely would the software cost much more, but as well the development would become so difficult that it would increase the risk of being unmanageable.


Related Discussions:- Illustrate the relationship between time and cost

State the technique pilot used in software engineering, State the technique...

State the technique Pilot used in software engineering With this approach, new system is introduced into one part of the company (for example into one warehouse of a supermark

What is software engineering, What is software engineering? Software en...

What is software engineering? Software engineering is a regulation in which theories, methods and tools are applied to make professional software.

What are the characteristics of software measurement, What are the characte...

What are the characteristics of software measurement? Measured property Object of measurement Source of measure Purpose measurement Context of measurement.

State the coding standards, State the Coding standards Coding standar...

State the Coding standards Coding standards normally give the guidelines about following: i)  Name of the module ii)  External and Internal documentation of source code

Determine the level 4 of key process areas, Determine the Level 4 of key pr...

Determine the Level 4 of key process areas Level 4 KPAs: 1)      Quantitative Process Management (QP): It states quantitative standards for software process. 2)

Why winrunner may fail to identify an object on a gui, Why WinRunner may fa...

Why WinRunner may fail to identify an object on a GUI? WinRunner may fail to recognize an object in a GUI in below cases: - If it isn't a standard windows object - If the

Explain software measurement, Software measurement Software measuremen...

Software measurement Software measurement is anxious with deriving a numeric value for an attribute of a software product or process. This permits for objective comparisons

What is requirement engineering, What is requirement engineering? Requ...

What is requirement engineering? Requirement engineering is the process of establishing the services that the customer needs from the system and the constraints under which it

Calculate the values of software, Q. For the program given below, calculate...

Q. For the program given below, calculate the values of software science measures like ? , N, V, E and λ . int. sort (int x[], int n) { int i, j, save, im1; /

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd