Illustrate the relationship between time and cost, Software Engineering

Assignment Help:

Q. Illustrate the relationship between Time and cost?

In software projects, time cannot be freely exchanged against cost. Such a trade off is limited by the nature of the software development. For a given organization, developing software of size S, the quantity obtained is constant. We know

K1/3 td4/3 =S/C

If we raise power by 3 afterwards Ktd4 is constant for constant size software. A density of the development time td will produce an increase of manpower cost. If compression is excessive not merely would the software cost much more, but as well the development would become so difficult that it would increase the risk of being unmanageable.


Related Discussions:- Illustrate the relationship between time and cost

Why is maintenance of a software important, Q. Why is maintenance of a soft...

Q. Why is maintenance of a software important? Discuss some of the problems that are faced during maintenance of software. Ans: The modification of a software product subsequ

Classify the techniques into dynamic or static, Classify the below techniqu...

Classify the below techniques into dynamic or static. i. Data Flow Analysis. ii. Use Case Testing. iii. Equivalence Partitioning. iv. Exploratory Testing. v. Inspec

Explain data accuracy, Data accuracy Don't collect redundant data  T...

Data accuracy Don't collect redundant data  The questions to be answered should be decided in advance and the needed data identified. Tell people why the data is being co

State the term software is engineered, Justify the term "Software is engine...

Justify the term "Software is engineered" Software is engineered not manufactured. Although some similarities exist between software development and hardware manufacture, the t

Explain iso 9000 certification, ISO 9000 certification Quality standard...

ISO 9000 certification Quality standards and procedures should be documented in an organisational quality manual. An external body might be certify that an organisation's qu

How many types of metrics, What are the types of metrics? Direct metric...

What are the types of metrics? Direct metrics - It refers to immediately measurable attributes. Example -Execution speed, Lines of code. Indirect metrics - It refers to the

Differentiate between failures and faults, Q. Differentiate between failu...

Q. Differentiate between failures and faults? Ans. Failure: -Failure is the disappearance of external results of program operation from requirements. Consequently failure is

What is compatibility testing, What is Compatibility testing - It's a n...

What is Compatibility testing - It's a non-functional test performed on a software system or component for checking its compatibility with the other parts in computing environm

Data dictionary , data dictionary diagram for library management system

data dictionary diagram for library management system

Contrast between project logic evaluation and networking, QUESTION (a) ...

QUESTION (a) Compare and contrast between Project logic evaluation (PLE), Networking and Scheduling (b) Discuss how the true cost of defects can often be higher than the ini

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd