Give an example of demonstrating a network or critical path by given activity and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 3 B
Every activity is denoted through a letter and the expected duration specified. A and B could begin instantly, thus can start on the similar circle. C should be preceded from B for example C cannot start till B has been finished.Network (critical path) diagram:
a. The elapsed or expected completion time of the project is seven weeks
b. The critical path activities are of B and C for example both must be finished within their predicted durations, or else the project will be longer into duration than seven weeks.
c. Activity A is a non-critical activity and it would have a float time of two weeks, which is since it only takes 5 weeks to finish, has nothing preceding or succeeding this, hence specified the elapsed time of the project is 7 weeks; this could finish as late as this.
The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines
Question: (a) The purpose of Project Monitoring and Control is to evaluate and provide an understanding of the evolution and progress of a project. This enables measurement of
Question 1: (a) Explain briefly the different steps in an Environmental Impact Assessment study. (b) Give the constraints of the process of Environmental Impact Assessment (
Empowering the staff assists to accomplish optimal business results through team work. Empowerment occurs when employees are adequately trained, provided with all relevant inf
T Company has identified a need for, and made a decision to open, a new training centre in one of the major cities in E Country. This is a large scale project for T Company and it
doing research for six sigma
ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to
Q. How do I organize and apply resources? A. The first moreover most important step in the implementation phase is to re-visit the project plan (or the project brief) and to
o Is the business problem that the project addresses clearly defined? o Is the list of stakeholders (ie people affected) by the project complete and correct? o Is the scope o
Question 1: (a) Outline some of the management principles that Project Managers need to adopt while managing a project team. (b) Resistance to change is inevitable, and th
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd