Explain what is the expected project length, Operation Management

Assignment Help:

Task time estimates for a production line setup project
at Robert Klassen's Ontario factory are as follows:
Immediate
Activity Time (in hours) Predecessors
A 6.0 -
B 7.2 __
C 5.0 A
D 6.0 B, C
E 4.5 B, C
F 7.7 D
G 4.0 E, F
a) Draw the project network using AON.
b) Identify the critical path.
c) What is the expected project length?


Related Discussions:- Explain what is the expected project length

Explain when communicating a change, When communicating a change, which rol...

When communicating a change, which role is more important: reporter of information or sense maker? Why

What must an organization do to prepare for such a risk, Product contaminat...

Product contamination is a catastrophic event, both for the organization at fault and for the victims. Cases of product contamination frequently make the news. Find an example o

Process selection, Process Selection There are many production proces...

Process Selection There are many production processes moreover a part or a component can be manufactured by two or more processes. The process engineer should select a proces

What must a short-term or long-term consequence make, What should a short-t...

What should a short-term or long-term consequence make a difference in resolving an ethical dilemma?

Explain the various types of time-series, Describe the various types of tim...

Describe the various types of time-series and associative forecasting models. Which types of organizations are each of these most applicable to, and why?

Explain cutting edge or don''t have a lot of precedents, In what ways do yo...

In what ways do you think that scoping projects that are cutting edge or don't have a lot of precedents is a problem, and how do you think a project manager can address this

Explain project management best practice, Give five potential underlying re...

Give five potential underlying reasons why projects commonly fail. For each potential failure point that you name, identify at least one project management best practice or techniq

Explain what leadership style dominates at novo nordisk, A wide array of le...

A wide array of leadership perspectives and theories. In order to synthesize the information, it is best to look at a real-life situation and analyze the leadership styles. Case 14

Explain what is the overall reliability of the call center, The service cen...

The service center for a brokerage company provides three functions to callers: account status, order confirmations, and stock quotes. The reliability was measured for each of thes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd