Explain what is the assembly line efficiency, Operation Management

Assignment Help:

An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest takes .3 minutes. The line will operate for 480 minutes per day In Problem 5, suppose the line is balanced using 10 workstations and a finished product (unit) can be produced every 4.2 minutes. a. What is the production rate in units per day? b. What is the assembly line efficiency?


Related Discussions:- Explain what is the assembly line efficiency

Which factors influence the choice of evaluation design, What factors influ...

What factors influence the choice of evaluation design? Which of these factors would have the greatest influence on your choice of an evaluation design? Which would have the smalle

Explain people discriminate when prejudice impacts their, People discrimina...

People discriminate when prejudice impacts their Answer beliefs. attitudes. intentions. behavior.

Find associated costs and revenues increase the capacity, A small firm inte...

A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives, A and B, have been identified, and the associated costs and reven

Explain capacity planning and how a company benefits, Please give your opin...

Please give your opinion on the paragraph below in just a few short sentences. Advertisers use case studies to add credibility to what they're saying their product is capable of do

Describe the basic idea underlying the contingency view, Explain the basic ...

Explain the basic idea underlying the contingency view

Explain how effective are actions by project managers, Provide two examples...

Provide two examples of current leaders and describe how they demonstrate their leadership characteristics. What separates these characteristics from management techniques? How eff

Explain benefits of using qualitative and quantitative data, Compare and co...

Compare and contrast the benefits of using qualitative and quantitative data collection methods as they apply to organizational development (OD).

Explain what is the minimum sales quantity, Ski Boards, Inc., wants to ente...

Ski Boards, Inc., wants to enter the market quickly with a new finish on its ski boards. It has two choices: (A) make major modifications at a fixed cost of $26,000, or (B) purchas

Explain the training and explain the method that was used, Traditional lear...

Traditional learning methods include lectures, hands-on, on-the-job training, self-directed learning, apprenticeship, case studies, business games, role plays, behaviour modelling,

Explain drum-buffer-rope, According to Elyahu Goldratt, the TOC system uses...

According to Elyahu Goldratt, the TOC system uses a scheduling approach called _____. drum-buffer-rope drum-buffer-string drum-rope-buffer drum-buffer-line

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd