Explain what are the boundary points of the feasible region, Operation Management

Assignment Help:

Maxwell Manufacturing makes two models of felt tip marking pens. Requirements for each lot of pens are given below.

Fliptop Model Tiptop Model Available

Plastic 3 4 36

Ink Assembly 5 4 40

Molding Time 5 2 30

The profit for either model is $1000 per lot.

1. What is the linear programming model for this problem?

2. What are the boundary points of the feasible region?

3. What is the profitability at each boundary point of the feasible region?

4. Find the optimal solution.

5. Will there be excess capacity in any resource? If so, how much excess capacity?


Related Discussions:- Explain what are the boundary points of the feasible region

Explain how might you prevent and fix such issues, Finding solutions to pro...

Finding solutions to problems is affected by how one frames the problem. In other words, what one thinks is wrong will influence what one believes the available solution(s) to be.

Explain projected return on the owner''s equity investment, Carter Dalton i...

Carter Dalton is well on his way to starting a new venture-- Max, Inc. He has projected a need for $350,000 in initial capital. He plans to invest $150,000 himself and either borro

Industrial production, Industrial Production The output of U.S. factori...

Industrial Production The output of U.S. factories is mines, and utilities. This output constitutes the production of things like the goods, portion of goods, and the services.

Calculate the economic order quantity, The Managing Director of Beauty Soap...

The Managing Director of Beauty Soaps Ltd just visited a soap manufacturing firm in Malaysia and he was immensely impressed by its raw materials stock management System. He wanted

Find which among the following statements are correct, If random variable X...

If random variable X follows the Normal distribution. X~Normal(10,10). Which among the following statements are correct? Answer a. P(X b. P(X=10)=0 c. P(X>8)=1-P(X

Explain implementation of a transnational strategy, What do you see as the ...

What do you see as the main organizational problems that are likely to be associated with implementation of a transnational strategy? Explain

Explain cutting edge or don''t have a lot of precedents, In what ways do yo...

In what ways do you think that scoping projects that are cutting edge or don't have a lot of precedents is a problem, and how do you think a project manager can address this

What is business process re-engineering, What is Business process re-engine...

What is Business process re-engineering? Business process re-engineering (BPR): The basic redesign of existing business processes to attain enhancements in critical areas

Presume the restaurant operates 360 days per year, A fast-food restaurant b...

A fast-food restaurant buys hamburger buns from a national bakery supplier. The daily usage of buns at the restaurant is normally distributed with an average of 160 and standard de

Explain project activity including personal time, A cost estimate for a giv...

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd