Explain what additional steps should the quality assurance, Operation Management

Assignment Help:

A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that the process standard deviation is two ounces. Each day last week, he randomly selected four packages and weighed each. The data from that activity appears below.

Weight
Day Package 1 Package 2 Package 3 Package 4
Monday 23 22 23 24
Tuesday 23 21 19 21
Wednesday 20 19 20 21
Thursday 18 19 20 19
Friday 18 20 22 20

(a) Calculate upper and lower control limits for both sample means and ranges.

(b) Is this process in control? Explain--a simple Yes or No is insufficient.

(c) What additional steps should the quality assurance team take?


Related Discussions:- Explain what additional steps should the quality assurance

Role or forecasting in capacity planning, Role or Forecasting in capacity P...

Role or Forecasting in capacity Planning The marketing department plays a major role in providing demand forecasts based on which both long term as well as short term capacity p

Explain ongoing risk exists in any project, Ongoing risk exists in any proj...

Ongoing risk exists in any project. Once a project starts, risk increases. How should one monitor and mitigate risk in a rapidly changing project?

Process focused production system, Process Focused Production System Th...

Process Focused Production System This is a form of production system in which production operations are grouped according to the type of process. In other words, all productio

Explain what is the market share, What is the market share, sales levels an...

What is the market share, sales levels and profit for the last 5 years for Subway Restaurant and Chick-Fil-A restaurant?

Explain levels of outsourcing, Why do you think many firms are experiencing...

Why do you think many firms are experiencing an increase in their levels of outsourcing?

Explain ennoblement in addition to the primary deliverable, Almost all proj...

Almost all project have deliverables dealing with documentation and customer ennoblement in addition to the primary deliverable

Explain support of senior management, Project failure can result from all o...

Project failure can result from all of the following causes EXCEPT- A. Support of senior management B. Changes in scope are not agreed upon by all parties involved C. Too

Explain capacity planning involving hiring, Capacity planning involving hir...

Capacity planning involving hiring, layoffs, some new tooling, minor equipment purchases, and subcontracting is considered as which one of the following planning horizons?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd