Explain the unit hydrograph - hydrology, Civil Engineering

Assignment Help:

Define Unit Hydrograph

Hydrograph of one inch or 1cm of precipitation over a drainage basin area (watershed). It is the base hydrograph from which other hydrographs can be determined by ratio when other precipitation quantities( < or > l inch or 1 cm) are known for the same drainage basin area. Also, calculating the "storm", or "surface water", or "overland flow" hydrograph and knowing the precipitation quantity, this method can be used to determine the plot points for a unit hydrograph for the same drainage basin area.

 


Related Discussions:- Explain the unit hydrograph - hydrology

Strength of materials, Didtribution of shear stree over a triangular sectio...

Didtribution of shear stree over a triangular section

Concrete technology, why strength of transition zone is less than bulk past...

why strength of transition zone is less than bulk paste

Reason in checking the ratio, Reason in checking the ratio (i.e. design flo...

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design For checking of self-cleansing velocity for pipes, there is another criterion t

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Determine the size of the standpipe which should be used, A sample in a var...

A sample in a variable head permeameter is 8 cm in diameter and 10 cm high. The permeability of the sample is estimated to be 10 × 10 -4 cm/s. If it is desired that the head in th

Concrete pavement, Question In case of concrete pavement, why is requir...

Question In case of concrete pavement, why is requirement of 95% by mass of quartz grains are specified in contract? Answer In universal Specification of Civil Enginee

State the coulomb wedge theory, A retaining wall is battered away from the ...

A retaining wall is battered away from the fill from bottom to top at an angle of 15° with the vertical. Height of the wall is 6 m. The fill slopes upwards at an angle 15° away fro

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Structural engg, how static and dynamic frames are works?

how static and dynamic frames are works?

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd