A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Explain inadequate parking, The Manchester United Soccer Tournament project...

The Manchester United Soccer Tournament project team (refer to the Manchester United Soccer club case study in chapter 4 of the text) has identified the following potential risks t

How team structure related to the project managers authority, How is the pr...

How is the project team structure related to the project manager's authority level?

Explain what professional credential do professionals, What steps would you...

What steps would you take to prepare yourself for a career as human resources director or vice president for human resources in a U.S. healthcare facility? What professional creden

List any three business areas in the umuc pizza shops, List three business ...

List three business areas and/or processes used in the UMUC Pizza shops that could be supported by an IT solution.

Explain internal resources and capabilities, Analyze Procter & Gamble's (Ca...

Analyze Procter & Gamble's (Case 8) resources and capabilities as well as its structures and systems. Internal resources and capabilities. How should P&G's strengths be leverage

Explain reporting biases can occur, The use of surveys of experts to estima...

The use of surveys of experts to estimate long-run production costs may be undermined by the fact that- Reporting biases can occur It is dependent on the judgments of individ

What are the activities of value chain analysis, What are the activities of...

What are the activities of value chain analysis? Activities are business activities the organisation manages so as to add value for example, the product or service is worth mor

MBA, Describe the various approahes to tqm

Describe the various approahes to tqm

Explain forecast for october percent of capacity, A dry cleaner uses expone...

A dry cleaner uses exponential smoothing to forecast equipment usage at its main plant. August usage was forecasted to be 50 percent of capacity; actual usage was 52 percent of cap

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd