Explain project activity including personal time, Operation Management

Assignment Help:

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Compute expected value for the add assembly line option, Howard Weiss, Inc....

Howard Weiss, Inc., is considering building a sensitive new airport scanning device.His managers believe that there is a probability of 0.40 that the ATR Co. will come out with a c

Explain characteristics of organisational development, Explain characterist...

Explain characteristics of organisational development. Characteristics of Organisational Development (i) Organisational progress is an educational strategy for bringing a

Define effectiveness and identify three businesses, From the video the frui...

From the video the fruit guys, determine the Fruit Guys business strategy. Identify three other businesses that could use the five questions the Fruit Guys used to determine effect

Describe expected monetary value, XYZ coating company has reviewed four new...

XYZ coating company has reviewed four new processes for improving their coating line. The four processes, labeled A, B, C, and D use different technology and have different capacit

Compute the value of the tax shield that the cost-depletion, You have a lea...

You have a lease on an oil and gas property with 87.5% NRI that delivers your firm annual profits of $400,000 for five years, with equal production in each year (you will need to t

Explain what do your contingency plan, What do your contingency plan in cas...

What do your contingency plan in case your plan of action doesn't work?

Explain because the confidence interval includes zero, A study was done to ...

A study was done to examine whether the perception of service quality at hotels differed by gender. Hotels were randomly selected to rate service items on a 50point scale. The sum

Give a specific definition of time study, Give a specific definition of tim...

Give a specific definition of time study. Time study It is defined as a work measurement technique for recording the times and rate of working for the component of a speci

Describe expect it to take for the customer to wait in line, A toll tunnel ...

A toll tunnel has decided to experiment with the use of a debit card for the collection of tolls. Initially, only one lane will be used. Cars are estimated to arrive at this experi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd