Explain project activity including personal time, Operation Management

Assignment Help:

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Ethical for organizational managers to try to get access, Do you belive it ...

Do you belive it is ethical for organizational managers to try to get access and scrutinize the Facebook pages of employees or job applicants?

Line balancing, what happens if line balancing does not exist

what happens if line balancing does not exist

Difference between performance and productivity measurement, 1. Explain the...

1. Explain the link between productivity and quality?  2. Who do van Biema and Greenwald (1997) and Drucker (1991) suggest are responsible for the slow growth in service sector

Explain is not one of the three types of specifications, Which of the follo...

Which of the following is not one of the three types of specifications discussed in the text? Answer Design specifications Material specifications Performance specifica

Explain efficiency advantages of a new technology, Consider this scenario: ...

Consider this scenario: You are the senior executive responsible for technology innovation for Company A. The company learns of the cost and efficiency advantages of a new technolo

Explain major liability to the organization, The issue of fraud must be con...

The issue of fraud must be considered when managing risk as it could present a major liability to the organization. Fraud is an act that requires an aggressive response and correct

Explain what use of the term sale rather than demand presume, What does use...

What does use of the term sales rather than demand presume?

Describe mpc can run independent of the operation plan, Which of the follow...

Which of the following is true? MPC can run independent of the operation plan. Business failure can result from poor MPC performance. In PAC, order release directly affect

What do you understand by “line balancing”? What happens if , What do you u...

What do you understand by “line balancing”? What happens if balance doesn’t exist?..

Airline implementing a policy that need to buy second seat, Answer the foll...

Answer the following questions: 1. what are the pros and cons of an airline implementing a policy that heavier customers need to buy a second seat? Research an airline and provide

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd