Explain in brief about the term - anchorage, Civil Engineering

Assignment Help:

Explain brief about the term - Anchorage

A device used to anchor tendons at the end of a concrete member is called as an anchorage in the case of post-tensioned concrete. In the case of a pre-tensioned concrete member, an anchorage is a device used to anchor stretched tendons during hardening of concrete.

 


Related Discussions:- Explain in brief about the term - anchorage

Determine the co-ordinates of grain-size distribution curve, In a hydromete...

In a hydrometer analysis, 0.5 N of soil was mixed in water to form one litre of uniform suspen- sion. The corrected hydrometer reading after a lapse of 60 min. from the start of se

Bond performance of bar reinforcement, Question Does occurrence of rust hav...

Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo

Stiff or soft fenders be designed for berthing in piers, Question Is it...

Question Is it necessary that stiff or soft fenders be designed for berthing in piers? Answer Elasticity of fenders is related to ability to release stored energy duri

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

Concrete, whats the role of gypsum in concrete?

whats the role of gypsum in concrete?

How can we reduced frictional losses, How can we reduced frictional losses ...

How can we reduced frictional losses Frictional losses can be reduced by several methods, such as : (a) Over-tensioning the tendons by an amount equal to the maximum frictio

Staircase, The Figure 1 below shows a section through a stairway for a gara...

The Figure 1 below shows a section through a stairway for a garage in a new proposed dwelling. The stairway is 3 meters wide with 300 mm wide treads(7 treads) and 170 mm high riser

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Dam, types of dam

types of dam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd