Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain compensation, Explain Compensation. Compensation: An employe...

Explain Compensation. Compensation: An employer is not responsible to pay compensation to an employee under the given circumstances/occasions: - (i) While the injury disa

Linear programming, classification of linear programming on the basis of st...

classification of linear programming on the basis of structure

Explain must prepare a budget for a change initiative, Change plans must co...

Change plans must consider the use of a companys resources to maximize potential and ensure success. Financial resources are a definite consideration for any plan or objective. I

Do you think taylor''s position is similler applicable today, 1. Do you thi...

1. Do you think Taylor's position is equally applicable today? 2. Looking at Taylor's and Grayson's remarks, whick were made approximately 73 years apart, one has to wonder what

Explain detect the presence of assignable causes, If the time order of prod...

If the time order of production has not been recorded in a set of data from a process is it possible to detect the presence of assignable causes?

Why company declines to correct the flaw, Scenario 2: A supervisor discover...

Scenario 2: A supervisor discovers a design flaw, which she believes is a safety hazard. She informs the company through the proper channels. The company declines to correct the fl

LINE BALANCING, . What do you understand by “line balancing”? What happens ...

. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Explain the bargaining unit as technical workers, Jack is a 2nd level manag...

Jack is a 2nd level manager at Johnson Controls. His department includes 2 supervisors, 5 night shift security guards, 5 technical workers, 10 janitorial staff, and 25 manufacturin

Activities and advantage that providing facility to customer, Consider the ...

Consider the Gleneagles Hotel in Scotland - it is unique, not part of a chain. It is a six star hotel with world class sports facilities with two championship golf courses, which h

Explain for bill what an enterprise resource planning, Describe for Bill wh...

Describe for Bill what an Enterprise Resource Planning (ERP) solution would look like for his UMUC Pizza business and how his business could benefit from implementing an ERP soluti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd