Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain how many items need to be counted each day, Howard Electronics, a s...

Howard Electronics, a small manufacturer of electronic research equipment, has approximately 7,000 items in its inventory and has hired Joan Blasco-Paul to manage its inventory. Jo

Why analysis phase in an hpt project is the most important, Some HPT practi...

Some HPT practicioners believe that the analysis phase in an HPT project is the most important. Do you agree? Why?

Define conflict within a project team, What are the consequences of ignorin...

What are the consequences of ignoring a conflict within a project team?

Explain each component and final scissor assembly, Prepare an MRP for sciss...

Prepare an MRP for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. 634 pairs of scissors are needed on Day 6. No

Explain human resource role, A program that provides employee relocation an...

A program that provides employee relocation and trailing spouse employment assistance is an example of which human resource role: Answer A) counsellor B) employee advocate C) strat

Public and private service sector - education, Public and Private Service S...

Public and Private Service Sector - Education 1. Life long learning; increased personal cost 2. Increase in competency/vocational qualifications 3. Global study on the

Typical financial performance measures, Typical Financial Performance Measu...

Typical Financial Performance Measures  Profitability - Profit margin, return on capital invested, return on equity Liquidity - Current ratio, cash position, working ca

Discuss how an operations manager can make operations, Question: (a) I...

Question: (a) In relation to an organisation with which you are familiar, critically discuss how an operations manager can make operations different using the five operatio

Assignment, transformation process in an organization

transformation process in an organization

Describe traffic accidents requiring medical assistance, It has been observ...

It has been observed that the average number of traffic accidents requiring medical assistance in Santa Clara between 7 and 8 AM on Wednesday mornings is 1. What, then, is the chan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd