a. You are chartered to set a time standard for a worker assembling 96 piece jigsaw puzzles. The following times have been collected from five different operators with one observation per operator. The times and ratings for the job are

Operator Time (in minutes) Rating
1 9 120
2 11.1 100
3 12 95
4 10.9 100
5 12.3 85

What is the normal time for this job? What is the standard time for this job with the assumption of a 20% allowance for personal, fatigue and delay? What are the value judgments you must make for the standard to be useful and implementable?


Related Discussions:- Explain fatigue and delay

Explain what is the efficiency of line balance, 1). Some tasks and the orde...

1). Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to be combined into workstations t

Explain health care information systems, 1. Analyze the basic technology un...

1. Analyze the basic technology underlying health care information systems and determine the most pressing need for innovation. 2. Explain (with specific examples using local hospi

Explain what assignment minimizes the total traffic flow, Please kindly sho...

Please kindly show step by step solutions. Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting Services. The distance between adjacent

Explain why should be performed before signing a contract, What due diligen...

What due diligence should be performed before signing a contract?

Explain ennoblement in addition to the primary deliverable, Almost all proj...

Almost all project have deliverables dealing with documentation and customer ennoblement in addition to the primary deliverable

Explain what kind of warning signals would you like, 1. What kind of warnin...

1. What kind of warning signals would you like fed back from PAC to MRP? 2. Lead times are sometimes called rubbery. What accounts for this concept of elasticity in lead times?

Explain service quality addresses, 1. Can some please help me with these f...

1. Can some please help me with these fill in's? I am not sure I have the right answers One Way to identidy goals is to identify best practices through a process known as________

Describe welding machine by manufacturing bike frames, Management believes ...

Management believes 6,000 WVD drums could be sold each year if the company had sufficient manufacturing capacity. As an alternative to adding another welding machine, management ha

Machine load chart, Machine Load Chart In machine load chart time is m...

Machine Load Chart In machine load chart time is marked along horizontal axis and various machines are marked along the vertical axis. The orders by their number Have been mar

Exam of Operation Management, I will have an exam which has 100 Questions. ...

I will have an exam which has 100 Questions. I will have just 24 hours to complete it. My question about that is if you can answer them within this time and handle the answers to m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd