a. You are chartered to set a time standard for a worker assembling 96 piece jigsaw puzzles. The following times have been collected from five different operators with one observation per operator. The times and ratings for the job are

Operator Time (in minutes) Rating
1 9 120
2 11.1 100
3 12 95
4 10.9 100
5 12.3 85

What is the normal time for this job? What is the standard time for this job with the assumption of a 20% allowance for personal, fatigue and delay? What are the value judgments you must make for the standard to be useful and implementable?


Related Discussions:- Explain fatigue and delay

Explain equal employment and affirmative action, Select a business of your ...

Select a business of your choice and visit their websites. From the website only, can you determine if the company supports workplace diversity, equal employment, affirmative actio

Explain simulation software such as crystal ball, Given the ease of use of ...

Given the ease of use of simulation software such as Crystal Ball, what other data used in project management should probably be simulated?

Explain how does mobile technology address day-to-day, How does mobile tech...

How does mobile technology address day-to-day business pressures?

Explain what is the utilization of pharma, Pharma Blitz develops and market...

Pharma Blitz develops and markets new technological products to be used in health care. The development of a new product operates as follows. When a new technology meets the requis

Explain bebts, Champ Sports Corporation buys the assets of Delta Athletic C...

Champ Sports Corporation buys the assets of Delta Athletic Corporation. Champ continues Delta's business and retains the same personnel. Is Champ liable for Delta's debts?

Explain project selection, "Project Selection" •For the purpose of completi...

"Project Selection" •For the purpose of completing the requirements of this course, select an actual business or personal project that assumes duration of 15 months and a functiona

What are the three sequential operations, A manufacturing process consists ...

A manufacturing process consists of three sequential operations. At maximum capacity operation A can output 125 units per hour, Operation B can output 120 units per hour, and Opera

Explain what are the legal and ethical ramifications, What are the legal an...

What are the legal and ethical ramifications for falsifying a resume?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd