Explain dynamic scheduling problem, Operation Management

Assignment Help:

Please explain how this works... I'm so confused!

Suppose SPT rule is being used in a dynamic scheduling problem. There are five jobs A, B, C, D, and E ready to be processed at the present time. The processing times for the five jobs are 1, 9, 7, 2, and 6 days respectively. A new job F will arrive on the 8th day. The processing time for job F is 5 days. On which day (from present time) job F will be completed?


Related Discussions:- Explain dynamic scheduling problem

Explain the most appropriate for domino''s to consider, Evaluate alternativ...

Evaluate alternative structures to determine which one would be most appropriate for Domino's to consider and discuss likely benefits Domino%u2019s would realize from adopting that

Explain management developer, Business knowledge competencies are particula...

Business knowledge competencies are particularly important for which human resource role? Answer A) management developer B) employee advocate C) strategic partner D) functional exp

Briefly analyze two opportunities, Thoroughly research and analyze two oppo...

Thoroughly research and analyze two opportunities and two major threats that united airlines is facing

Linear programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Qualitative and quantitative justification, 1.  Maggie Company produces a l...

1.  Maggie Company produces a light fixture with the following unit costs:   Direct Materials: $2 Direct Labour: $2 Variable Cost: $3 Fixed Cost: $2 UNIT TOTAL COST: $9   The

Effect on costs and employer, Effect on Costs and Employer: Accidents  are...

Effect on Costs and Employer: Accidents  are harmful when  we take into account  the business  of the  concern.  It adds to the  costs of production  directly  as well  as  indire

Explain safety stock would provide a stock out risk, The injection moulding...

The injection moulding department of a company uses an average of 30 gallons of special lubricant a day. The supply of the lubricant is replenished when the amount on hand is 170 g

Explain jit and lean, When linking marketing requirements and manufacturing...

When linking marketing requirements and manufacturing strategy, what design approaches for shop floor system should be considered? JIT and Lean MRP and PAC MRP and JIT

What is benchmark for future comparison, Cunningham Performance Auto, Inc.,...

Cunningham Performance Auto, Inc., modifies 375 autos per year. The manager, Peter Cunningham, is interested in obtaining a measure of overall performance. He has asked you to prov

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd