Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

What are the basic components of an automobile, What are the basic componen...

What are the basic components of an automobile ? Explain them briefly. Show a schematic diagram showing the layout of the transmission system of a rear wheel driven automobile.

Couple, What are properties of couple

What are properties of couple

Employability skills, Employability skills required for effective employmen...

Employability skills required for effective employment

Load shared by concentric springs, Load shared by concentric springs: ...

Load shared by concentric springs: Two concentric springs are subjected to an axial load of 60 kN. The maximum permissible deflection of the springs is 45 mm & the solid lengt

Dust collector, Dust Collector:             Dust collector system is to...

Dust Collector:             Dust collector system is to collect the blast burrs or waste particle created during the blasting process. During the blasting process, this dust co

Heat removal factor, 1.Calculate the heat-removal factor for a collector ha...

1.Calculate the heat-removal factor for a collector having an overall heat-losscoefficient of 6 W/m2K and constructed of aluminum fins and tubes. Tube-to-tube centered distance is

Determine moment of the force about the origin, (a) What do you understand ...

(a) What do you understand by couple moment. Is it a free vector ? (b) A force F = 10i + 6j - 6k N performs at a position (10, 3, 4) m relative to a coordinates system. Determin

National supply and national demand curves, National supply and national de...

National supply and national demand curves: 1. Explain why neighboring countries tend to trade extensively with each other. 2. Use Table 1.1 to find the five most open econ

Determine the velocity in a moving frame of reference, Determine the veloci...

Determine the velocity in a Moving Frame of Reference: As illustrated in Figure, a ship A moves with a velocity v A = 40 km/hour whereas ship B moves with a velocity of v B

Computer aided synthesis, The basic aim of synthesis in design process is t...

The basic aim of synthesis in design process is to provide information which can tell you how to improve the design. In general the synthesis process gives many alternatives of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd