Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Fuel feed system, Fuel Feed System: Fuel feed system is provided to serve ...

Fuel Feed System: Fuel feed system is provided to serve the air fuel mixture to the engine in an appropriate ratio so that it can burn efficiently and transmit power to crank shaf

Varignon theorem - mechanics, Varignon theorem: State Varignon's theo...

Varignon theorem: State Varignon's theorem. How it helps in determining of the moments? In which type of condition is it used? Sol.: Varignon's theorem also called Law

Material science.., Briefly explain the process of age hardening in metals

Briefly explain the process of age hardening in metals

Design of a filament winding machine, How can I achieve a back and forth mo...

How can I achieve a back and forth movement of carriage system. How can I reverse the motor to go back and forth.

Locomotive boiler, advantages and disadvantages of locomotive boiler

advantages and disadvantages of locomotive boiler

Results for the underlying problem-conventional priority , Results for the ...

Results for the Underlying Problem The rules mentioned above and several variants of these rules that became out to be inferior are tested for eight various conditions of the

Explain about the footings how it is transmit loads, Explain about the foot...

Explain about the footings how it is transmit loads. Footings are generally the lowermost supporting part of the structure known as sub-structure and are the last structural e

Evaluation of heat required - thermodynamics, Evaluation of heat Required: ...

Evaluation of heat Required: Heat which is required to generate steam is different from 'total heat' or enthalpy of steam. Heat required for generating steam means heat needed

Determine the initial radius of curvature, Determine the initial radius of ...

Determine the initial radius of curvature:  A carriage spring, defiantly loaded and simply supported at its ends, has 12 steel plates each 60 mm wide by 6 mm thick. If the lon

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd