Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Railways, RAILWAYS: Railway transport is one of the important modes of...

RAILWAYS: Railway transport is one of the important modes of transport in India. Its technology is based on the traction of a group of wagons or coaches over a fixed track, co

Governors, how to find mass of sleeve in porter governor

how to find mass of sleeve in porter governor

calculate the arc-belt length-distance and ratio , A powered metal-working...

A powered metal-working crank press (a generic press is shown at the end) has been designed to be capable of punching blanks from mild steel sheet up to 3 mm thick. 1. the ultim

Displacement or swept volume, Displacement or Swept Volume ( V s ) : The ...

Displacement or Swept Volume ( V s ) : The nominal volume swept by the working piston when travelling from one dead centre to the other is called the displacement volume. It is e

Design evacuation systems for plant, Q. Design evacuation systems for plant...

Q. Design evacuation systems for plant? The plant will have designated Muster areas where personnel can go during an emergency and be accounted for and from which they can then

Calculate the time required to complete the job, Five jobs are performed fi...

Five jobs are performed first-on Machine-I and then on Machine-II. Time in hours taken by each job on each machine is given below :

Welding, Differentiate between porosity & blowholes in welding

Differentiate between porosity & blowholes in welding

Calculate the probable wall thickness of the tank, The background for the o...

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd