Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Changes in mechanical properties along with tempering, Changes in Mechanica...

Changes in Mechanical Properties along with Tempering: Tempering enhances the toughness and ductility of quenched steel though decreases hardness. Following figure demonstrate

Welding variables-welding current, WELDING VARIABLES The following major ...

WELDING VARIABLES The following major process variable play an important role in shaping the weld bead and the resultant weld metal in submerged arc welding: a. Welding cu

Importance of angle of twist, Importance of angle of twist: Q: What i...

Importance of angle of twist: Q: What is the importance of angle of twist? From relation T / J = G. θ / L ;  we have               θ= T . L / G . J As G , L , J

Firecracker welding, Firecracker Welding This is a semi automatic vers...

Firecracker Welding This is a semi automatic version of SMAW. A specially designed heavy - coated electrode, which can be of any length upto 2 m, is laid on the seam of a groo

Loosening a part with multiple fasteners services tips, Loosening a Part wi...

Loosening a Part with Multiple Fasteners: Loosening a part with multiple fasteners should be done from the outside to inside in a criss-cross pattern, loosening the small fastener

Objectives of tools and equipment , Objective: After studying tools and eq...

Objective: After studying tools and equipment, you should be able to list various tools, measuring equipment required in a motorcycle workshop, and identify and use ap

WELDING, WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

Explain the information phase of radial drilling machine, Information Phase...

Information Phase: Step: To secure all and complete information and gather facts and from best sources.   Our project is selected based on the current problem face by the

Constant pressure cycle, Diesel (Constant Pressure Cycle): 5-1...

Diesel (Constant Pressure Cycle): 5-1 Suction Stroke at constant pressure 1-2 Adiabatic Compression 2-3 Heat Addition at constant pressure 3-4 Adiabatic Expan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd