Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Simply supported beam - bending moment, Simply supported beam -  Bending M...

Simply supported beam -  Bending Moment: Sketch the SFD and BMD for a simply supported beam of 15 m span loaded as illustrated in Figure Figure Solution Tak

What is wrap-around, The major purpose of a wrap-a-round is to make a strai...

The major purpose of a wrap-a-round is to make a straight line around a pipe to aid in cutting the pipe to its proper length. It is used mainly as a template or a straight edge.

Forces working on sphere, Forces working on sphere: Let a sphere of ma...

Forces working on sphere: Let a sphere of mass m, suspended by means of a string, resting against a smooth wall, as illustrated in Figure (a). What are the forces working on i

Determine the maximum value of the coefficient of friction, Determine the m...

Determine the maximum value of the coefficient of friction: A force of 200 N inclined at 60 o to the horizontal is applied to the block A weighing 400 N. find out whether blo

TTT of effective normalizing of Ductile tiron, At 1500 degrees F, how much ...

At 1500 degrees F, how much time is required to effectively normalize ductile iron

Explain about active fire protection, Q. Explain about Active Fire Protecti...

Q. Explain about Active Fire Protection? Active Fire Protection - A fire fighting system that is normally dormant and is activated automatically upon detection of a fire hazard

Write the functional element of instrument system, a) Mention typical appli...

a) Mention typical application of instrument system with illustratation. b) Write down about the functional element of instrument system with examples. c) Define the key term

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd