Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Electron beam welding-aerospace applications, AEROSPACE APPLICATIONS   ...

AEROSPACE APPLICATIONS   The need for EBW as a critical fabrication process in realising elements and assemblies for spacecraft and launch vehicle programmes due to the foll

CFD PHOENICS, expert with PHOENICS software experience for CFD free convect...

expert with PHOENICS software experience for CFD free convection

Fluid Question, If water is pumped from a pristine stream and piped to a st...

If water is pumped from a pristine stream and piped to a storage tank installed on a tower above the facility, a) What is the minimum dimension for "X" to achieve the required pres

Rotary converters, ROTARY CONVERTERS Historically, these type of power so...

ROTARY CONVERTERS Historically, these type of power sources were developed first for arc welding applications and even now these types are popular. These rotary converters are of

Air conditioning systems., an air conditioning system is to take place in a...

an air conditioning system is to take place in an outdoor air at 10 degrees celcius and 30% 0f relative humidity at a steady rate of 45 m^3/min and to condition it to 25 degrees ce

Newton ring, What is a newton ring excrement

What is a newton ring excrement

Determine the displacement response time, (i) Formulate the equation of mot...

(i) Formulate the equation of motion for the system shown in Figure. List TWO (2) assumptions made in this formulation. (ii) Find the response of this system at t = 3s. The syst

Competency statements , COMPETENCY STATEMENT:  In this programme, every le...

COMPETENCY STATEMENT:  In this programme, every learner shall be assessed on a continuous basis for his/her knowledge and skills during the programme duration. Learners' competenc

Grinding wheels, Grinding Wheels Implicated to be rotated at relativel...

Grinding Wheels Implicated to be rotated at relatively high rotational velocities within grinding machines, grinding wheels contain a surface of rotation about a central axis.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd