Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Tools and equipment , In Tools and equipment we studied about the various t...

In Tools and equipment we studied about the various tools and equipment used in service and repair of a motorcycle and for the troubleshooting. Acquainting with these will help you

Pyrolysis-manufacturing methods of ceramics, Pyrolysis Pyrolysis is th...

Pyrolysis Pyrolysis is the procedure of depositing a ceramic on a heated substrate. The process is used to deposit coating or generate thin walled components of graphite or si

Brittle fracture, Dear Sir I would to know what is the min. time required...

Dear Sir I would to know what is the min. time required for carbon steel tube A214 @ zero C to 50 C

Maximal conductances and reversal potentials, By introducing their model of...

By introducing their model of neural excitability in 1952, Alan Lloyd Hodgkin and Andrew Huxley not only shed light on the mechanism underlying a very important phenomenon in Physi

Material engineering, State the four classes of engineering materials 3 (b)...

State the four classes of engineering materials 3 (b) Identify the class which each of the following materials belong to. Present your answer in table form Silicone, concrete, chro

__, what is magnetostriction?

what is magnetostriction?

Mechanics materials , 1) Factor of Safety is calculated by using which of t...

1) Factor of Safety is calculated by using which of the following set of values? [Select the one best answer from the choices given below.] Answer a. Yield Stress and Allowable St

Hartnell Governor, How we could build the working model of hartnell governo...

How we could build the working model of hartnell governor?

Explain the cushion materials which used in moulding sand, Q. Explain the C...

Q. Explain the Cushion Materials which used in moulding sand? These materials when added to the moulding sand burn and from gases when the molten metal is poured into the mould

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd