Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Find out horizontal and vertical components of hinge force, Find out horizo...

Find out horizontal and vertical components of hinge force: The frame shown in Figure is supported by a hinge at E and a roller support at D. Find out horizontal and vertical

The diameter dimension command, The Diameter Dimension Command You can ...

The Diameter Dimension Command You can use the Diameter command to annotate a circle or an arc with a diameter dimension. To achieve this simply start the command, pick a point

Break even analysis, Break even analysis: The costs from Shagun Palace...

Break even analysis: The costs from Shagun Palace, a continental restaurant, are shown below. Fixed costs are Rs. 50,000 per month. Break even analysis is applied as a

Pressure at bottom of a cone, I have a tank that has a 30" dia at the top...

I have a tank that has a 30" dia at the top and is 24" deep. It connects to a cone that is 30" dia at the top and goes to a 15" dia in 12". I plan on filling the tank with golf ba

FLUID MECHANICS, A mix of spherical particles of different sizes is to be s...

A mix of spherical particles of different sizes is to be separatedinto two size ranges by passing a liquid of density 1200 kg m-3 and viscosity 0.0015 Pa s upward through the mixtu

Force system, Force system: Defin e Non concurrent force system. Why...

Force system: Defin e Non concurrent force system. Why we find the position of Resultant in Non concurrent force system? Sol.: In Equilibrium of concurrent force syste

Define the polyhedra and euler formula, Polyhedra and Euler's Formula T...

Polyhedra and Euler's Formula The b-rep of a polyhedra that are holomorphic to a sphere are topologically valid if they satisfy the following equations : F - E + V - L = 2 (

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd