The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.
Solution
Given Number of machines n = 6
Number of shifts per week S = 10
Number of hours per shift H = 8
Production rate Rp = 17
Production capacity = n x S x H x Rp
∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk
What is the amount of air is supplied to engine via turbochargers and how their sizes vary from engine to engine ?
Answers all questions i. Illustrate Zeroth law of thermodynamics. ii. A gas contained in a cylinder is compressed, the work neede for compression being 5000 KJ. During the pr
(a) Illustrate why a rich mixture is required for the following (i) idling (ii) sudden acceleration (iii) Maximum power (b) A simple jet carburetor is required to supply 5Kg
The critical Temperature of a gas is the highest temperature for which isothermal compression of the gas results in ? Will an adiabatic ?ash result in more, the same, or less va
Explain desirable properties of modeling and differentiate between the process of casting and modeling. Also highlight the advantages and disadvantages of casting process and model
Grinding & Brushing: Grinding is process there has an abrasive wheel that rotating at certain speed to smooth a surface or to give an even finish on material. In this Blade pr
Magnitude of a couple: So l.: For system, magnitude of couple is equal to algebraic sum of the moment about any point If the system reduces to couple, the resultant forc
a) The total estimated time for an operation ie assembly of a pin is 2 minutes. If the rating is 120% determine normal time. If total allowances allowed are 10% for that job, calcu
Those that produce microbial cells e.g.Baker's yeast or mycoprotein. Those that produce microbial enzymes e.g. alpha amylase for starch processing, glucose isomerase for the pro
case study of thermal stresses and composite bar
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd