Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Evaluate stress in fibre, Evaluate stress in fibre: Example, the matri...

Evaluate stress in fibre: Example, the matrix material can be stressed to its full strength of 80 MPa, calculate the allowable % of broken fibres. What will be the stress in f

Evaluate the magnitude, Evaluate the magnitude, direction and position of t...

Evaluate the magnitude, direction and position of the resultant of the system of forces (using vector method) shown in figure below.

# ic engines, what are the di #Minimum 100 words accepted#

what are the di #Minimum 100 words accepted#

Creep - flat footed rail, Creep: Creep of rails is the forward moveme...

Creep: Creep of rails is the forward movement of rails in the direction of dominant traffic over a period of time. Creep is undesirable because it disturbs the gauge of the t

Electromagnetic conversion device with example., Q.  In every electromagne...

Q.  In every electromagnetic conversion device, both generator and motor action take place simultaneously. Explain. The case the output is mechanical as in a motoring mode, th

Design for a water treatment plant, Design for a water treatment plant: ...

Design for a water treatment plant: Produce as individuals a single tab Excel spreadsheet which shows a rough initial design for a water treatment plant taking 15

I.c.engine, compression ignition engine fore stork with neat daysgram

compression ignition engine fore stork with neat daysgram

Example of manufacturing lead time (mlt), Example of Manufacturing Lead Tim...

Example of Manufacturing Lead Time (MLT) A certain part is generated in a batch size of 100 units. The batch should be routed through five operations to complete the processin

Objectives-computerized scheduling and control manufacturing, Objectives ...

Objectives After studying this section, you should be familiarized about: The typical job shop scheduling problem, Characteristics of computer controlled scheduling,

What do you mean by alloys, Q. What do you mean by Alloys? Metallic mat...

Q. What do you mean by Alloys? Metallic materials that contain alloying elements, including chromium (Cr), cobalt (Co), Columbium or niobium (Cb or Nb), copper (Cu), iron (Fe),

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd