Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Two coplanar forces are acting on the rigid body, Steps for solving the pro...

Steps for solving the problems when more than two coplanar forces are acting on the rigid body: The steps are as; 1. Check the Problem for the concurrent or Non concurren

Thermal Systems Analysis and Design, Create Visual Basic function ffactor(R...

Create Visual Basic function ffactor(Re, rr) that calculates the Darcy-Weisbach friction factor in a pipe or duct, where Re is the Reynolds No. and rr is the relative roughness, us

Determine the value of shunt connected capacitance, An electric heating ele...

An electric heating element is rated at 4.0kW when connected to a single phase 240Vrms, 50 Hz AC supply, and is known to have a power factor of 0.833 lagging. 1. Calculate the c

Beam and types of beam - support reaction, Beam: Sol.: A beam can be...

Beam: Sol.: A beam can be defined as a structural element which has one dimension (length) considerable larger As compared to the other two direction, which is breadth an

Natural frequency-degree of freedom-conservative system , Natural Frequency...

Natural Frequency: This is the frequency of vibration of a system that is undamped and without external excitation while it is disturbed. Forced Vibration: This is the vibra

Calculate the time required to complete the job, Five jobs are performed fi...

Five jobs are performed first-on Machine-I and then on Machine-II. Time in hours taken by each job on each machine is given below :

Joule''s law and enthalpy - thermodynamics, Joule's Law and Enthalpy - Ther...

Joule's Law and Enthalpy - Thermodynamics: Joule ' s Law Joules law experiment is based on the constant volume process, and it state that I.E. of perfect gas is a fun

Design a pipeline and pump station to pump water, Design Problem:  Design a...

Design Problem:  Design a pipeline and pump station to pump 100 MGD of water to the Mississippi river.  To reduce the required horsepower of the pumps, the flow will be pressurized

Assignment, history of electronics materials

history of electronics materials

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd