Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Illustrate process of radiographic examination, Q. Illustrate process of Ra...

Q. Illustrate process of Radiographic Examination? Radiographic examination of welded joints shall be performed when required by the Code or additionally when specified in this

Corrosion - erosion allowance, Q. Corrosion - Erosion Allowance? The re...

Q. Corrosion - Erosion Allowance? The required design life shall be based on written agreement between the user and the Engineering Contractor. Allowance specified shall be ba

Gripper design, what are the necessery calculation required to design a gri...

what are the necessery calculation required to design a gripper?

RC circuit, #question.I am doing a ,ini project on Hovercrafts .As i am fro...

#question.I am doing a ,ini project on Hovercrafts .As i am from mechanical i need assistance regarding control over brushless motors.

What is a positive displacement pump, A positive displacement pump is a liq...

A positive displacement pump is a liquid or gas to move by trapping a fixed amount of fluid or gas and then forcing (displacing) that trapped volume into the discharge pipe. Positi

Can you explain shell molds, Q. can you explain Shell molds? These mold...

Q. can you explain Shell molds? These molds are prepared by pouring a mixture of sand and thermosetting resin over the heated surface of a metallic pattern, which results into

Find minimum time for a vehicle to go from 0 to 60 mph, For a few of the fo...

For a few of the following problems the constant acceleration is due to gravity and will be notated as a = g = 32 ft/sec 2 . 'g' perhaps positive or negative depending on the conte

Sweep representations of two-dimensional area, Sweep Representations  T...

Sweep Representations  The simplest form of sweep is that produced by sweeping a two-dimensional area along an axis perpendicular to its plane. This form of sweep is most usefu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd