Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Where pneumatic system is used, Any system needs redundancy in work needs p...

Any system needs redundancy in work needs pneumatics, because the compressor of the pneumatic system has periodical operations (intermittent work, not as hydraulic pump). The compr

Write the differences between reaction and impulse turbine, (a) Show that t...

(a) Show that the force exerted by a jet of water on an inclined fixed plate in the dissection of jet is given by fx = .a.v 2 . sin 2 θ. Where a is area of jet, v is velocity of j

How to drill 500 sheets paper , How to drill 500 sheets paper ?in 4 mm dia ...

How to drill 500 sheets paper ?in 4 mm dia , holes are same distance as its dia (4mm) in one line.

Applications and disadvantages of electro chemical machining, Applications ...

Applications and Disadvantages of Electro Chemical Machining Disadvantage of Electro Chemical Machining 1. The tools are more difficult to design. 2. Initial cost is hi

What is conformance testing, What is Conformance Testing Conformance Te...

What is Conformance Testing Conformance Testing : There was no mechanism for testing processors or resolving errors between two processors.

Thermodynamics, You wish to boil 1.2 kg of water, which has a specific heat...

You wish to boil 1.2 kg of water, which has a specific heat capacity of 4186 J/kg-K. The water is initially at room temperature (293 K). Water boils at 373 K. How much energy must

Determine the dead load - sewer construction, Determine the dead load: ...

Determine the dead load: A 250 mm diameter sewer is placed in a 2.75 m deep rectangular trench that is 0.65 m wide. This trench is backfilled with saturated clay having a unit

Track renewal, Track Renewal: Need for Track Renewal Normal m...

Track Renewal: Need for Track Renewal Normal maintenance is able to keep up the track standards only to a limited extent. The track gets overaged or the speeds and tr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd