Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Types of coated electrodes-low hydrogen electrodes, Low Hydrogen Electrodes...

Low Hydrogen Electrodes Low hydrogen electrodes are so called because their covering is low in hydrogen bearing compounds and only traces of hydrogen or moisture are present in t

Explain working of steam drum, Q.Explain working of Steam Drum? Total so...

Q.Explain working of Steam Drum? Total solids concentration in the steam at steam manifold outlet shall not exceed 0.5 ppm during steady operation at MCR.  Fabricator must indic

Design a remote controlled buggy, You are required, as part of a small team...

You are required, as part of a small team, to design a remote controlled buggy that can be made to move forwards, backwards and from side to side. The basic buggy and motors are pr

Heat transfer and temperature distribution, Derive the mathematical express...

Derive the mathematical expression for heat transfer and temperature distribution through infinite long fin?

Load shared by concentric springs, Load shared by concentric springs: ...

Load shared by concentric springs: Two concentric springs are subjected to an axial load of 60 kN. The maximum permissible deflection of the springs is 45 mm & the solid lengt

Air-gas cross-limiting and air-gas ratio control, Q. Air-Gas Cross-Limiting...

Q. Air-Gas Cross-Limiting and Air-Gas Ratio Control? The Steam Generator firing demand signal is directed to two discrete signal selectors. A low signal selector ensures that

Refrigeration, A refrigeration system produces 40 kg/hr of ice at 0oC from ...

A refrigeration system produces 40 kg/hr of ice at 0oC from water at 25oC. Find the refrigeration effect per hour and TR. If it consumes 1 kW of energy to produce the ice,

Maths, Physical meaning of gradient of 2 nd order tensor?

Physical meaning of gradient of 2 nd order tensor?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd