Example of production rate, Mechanical Engineering

Assignment Help:

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Find out the moment of inertia of an annular area, Find out the moment of i...

Find out the moment of inertia of an annular area: Find out the M. I. of an annular area among two circles where difference of radius is quite small, around any centroidal axi

Define the polyhedra and euler formula, Polyhedra and Euler's Formula T...

Polyhedra and Euler's Formula The b-rep of a polyhedra that are holomorphic to a sphere are topologically valid if they satisfy the following equations : F - E + V - L = 2 (

What are the instructions to charge a battery?, (a) How is specific gravity...

(a) How is specific gravity of electrolyte (battery water) measured and what should be the value of specific gravity? (b) How would you measure battery voltage and what is its reco

Heat treatment, #question.what are process of annealing? .

#question.what are process of annealing? .

Yes, Which type of study require for mechanial engineering

Which type of study require for mechanial engineering

Determine mean effective pressure, An oil engine works on the Dual cycle, t...

An oil engine works on the Dual cycle, the heat liberated at consent pressure being twice that liberated at consent volume. The compression ratio of the engine is 8 and the expansi

Solid modeling design, Solid Modeling Design Create a solid model for on...

Solid Modeling Design Create a solid model for one of the following case studies listed below (all subsystems/subassemblies are indicative): Use Solid Works CAD software. A- Ca

Show leak area preparation, Q. Show Leak Area Preparation? Clearly mark...

Q. Show Leak Area Preparation? Clearly mark the location of the leak on the flange with a permanent marker. Notes: 1. Depressurizing hydrocarbon lines in non-emergency event

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd