Example of Production Rate
The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.
Solution
Given Number of machines n = 6
Number of shifts per week S = 10
Number of hours per shift H = 8
Production rate Rp = 17
Production capacity = n x S x H x Rp
∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk
Steps for solving the problems when more than two coplanar forces are acting on the rigid body: The steps are as; 1. Check the Problem for the concurrent or Non concurren
Create Visual Basic function ffactor(Re, rr) that calculates the Darcy-Weisbach friction factor in a pipe or duct, where Re is the Reynolds No. and rr is the relative roughness, us
What is tool economics?
An electric heating element is rated at 4.0kW when connected to a single phase 240Vrms, 50 Hz AC supply, and is known to have a power factor of 0.833 lagging. 1. Calculate the c
Beam: Sol.: A beam can be defined as a structural element which has one dimension (length) considerable larger As compared to the other two direction, which is breadth an
Natural Frequency: This is the frequency of vibration of a system that is undamped and without external excitation while it is disturbed. Forced Vibration: This is the vibra
Five jobs are performed first-on Machine-I and then on Machine-II. Time in hours taken by each job on each machine is given below :
Joule's Law and Enthalpy - Thermodynamics: Joule ' s Law Joules law experiment is based on the constant volume process, and it state that I.E. of perfect gas is a fun
Design Problem: Design a pipeline and pump station to pump 100 MGD of water to the Mississippi river. To reduce the required horsepower of the pumps, the flow will be pressurized
history of electronics materials
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd