Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk


Related Discussions:- Example of production rate

Torque transmission-various factors in clutch design , Torque Transmission ...

Torque Transmission : The clutch should be able to transmit the maximum torque of the engine under all conditions. It is usually designed to transmit 125 to 150 percent of the max

What are the benefits of value engineering, Normal 0 false fa...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Boiler, parameters specified in a steam boiler

parameters specified in a steam boiler

Aircraft characteristics - military and civil aircraft, Aircraft Characteri...

Aircraft Characteristics For planning and designing airport facilities, it is necessary to be conversant with the following important characteristics: (a) speed (b) size

Types of fermentation and scales of operation, Those that produce microbial...

Those that produce microbial cells e.g.Baker's yeast or mycoprotein. Those that produce microbial enzymes e.g. alpha amylase for starch processing, glucose isomerase for the pro

Risk Management in Construction Projects, What is the turnaround time for a...

What is the turnaround time for a 10-page assignment?

Theory of machines, What'' is balancing and vibration in machines Need of ...

What'' is balancing and vibration in machines Need of balancing? Causes of vibration and their harmful effects and remedies?

Improvement of existing airport, Improvement Of Existing Airport: The ...

Improvement Of Existing Airport: The improvements that are usually needed for existing airports fall under the following categories : (a)        Extension of runway to acco

Show pneumatic test, Q. Show Pneumatic Test? Pneumatic testing presents...

Q. Show Pneumatic Test? Pneumatic testing presents hazards that must be addressed as part of the engineering design of the pressure vessel. Due to the additional hazards of

Determine minimum von mises stress, In this assignment you will apply what ...

In this assignment you will apply what you have learned in previous training. Consider the part in figure, which constructed from a solid tube. The bracket is supported at surface

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd