An advertising project manager developed the network diagram shown below for a new advertising campagign. In addition, the manager gathered the time information for each activity, as shown in the below table.
Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.
Activity Optimistic Most likely Pessimistic Immediate Predecessor(s)
A 1 4 7 -
B 2 6 7 -
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A,C
F 6 8 16 B
G 1 5 6 E,F
Magnitude - Vector The magnitude, or length, of the vector v → = (a1, a2, a3) is given by, ||v → || = √(a 1 2 + a 2 2 + a 2 3 ) Example of Magnitude Illus
Easy Rider taxi service charges a pick-up fee of $2 and $1.25 for each mile. Luxury Limo taxi service charges a pick-up fee of $3.25 and $1 per mile. How many miles required to be
The points A,B,C and D represent the numbers Z1,Z2,Z3 and Z4.ABCD is rhombus;AC=2BD.if Z2=2+i ,Z4=1-2i,find Z1 and Z3 Ans) POI of diagonals: (3-i)/2. Using concept of rotation:
The subsequent force that we want to consider is damping. This force may or may not be there for any specified problem. Dampers work to counteract any movement. There are some w
what states and marketing tasks?
The order of a differential equation is the huge derivative there in the differential equation. Under the differential equations as listed above in equation (3) is a first order di
Arc Length with Polar Coordinates Here we need to move into the applications of integrals and how we do them in terms of polar coordinates. In this part we will look at the a
The 't' distribution is a theoretical probability distribution. The 't' distribution is symmetrical, bell-shaped, and to some extent similar to the standard normal curve. It has an
MATHEMATICS - IN OUR LIVES : What is the most obvious example of mathematics in your life? To many of us it is the maths that we studied in school. But is that all the mathemat
in 1970 a record 1.5 of rain fell in one minute at Basse Terre, guadaloupe in the caribbnean.at this rate, how much rain fell in 3 seconds or 0.05 of a minutes?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd