Earth work in high embankments, Civil Engineering

Assignment Help:

Q. Earth work in high embankments?

(a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the boundary.

(b) Borrow pits must be laid out as the Engineer directions. The pits must be rectangular. The sides of borrow pits next to the toe of bank must be sloped at one to two and else where at 1 to 1.

(c ) Where the ground is low end swampy, the outer or most distant half of the borrow pits is to be excavated first.

(d) In banks over 3 metres high, the outer halves only of the borrow pits are to be marked out.


Related Discussions:- Earth work in high embankments

Calculate the square foot of contact area for the formwork, A concrete crew...

A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

What is the dry density, Q. The field density of a compacted fill is deter...

Q. The field density of a compacted fill is determined by means of a core cutter whose empty weight is 1000 g and volume is 1000 cm 3 . The cutter full of soil weights 2890 g. If

Geotechnical Engineering, how to calculate the conduct pressure,settlement ...

how to calculate the conduct pressure,settlement e.t.c

Why we use air valves, Q. Why we use Air Valves? Air Valves - Air valve...

Q. Why we use Air Valves? Air Valves - Air valves of proper size and pressure rating at summits. Air valves ensure the safety of the pipe line against collapse when at points o

Define drag load test of shock transmission unit, Define Drag load test of ...

Define Drag load test of shock transmission unit? This test ensures that excessive load should not be transmitted to the structure by the STU. As per the test the STU shall hav

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Relief features, characteristics of ridge characteristics of escarpment cha...

characteristics of ridge characteristics of escarpment characteristics of plateau characteristics of knoll characteristics of conical hill

SETTLEMENT OF SOIL AND BRACING OF RETAINING WALL OF BASEMENT, STRUCTYRE IS ...

STRUCTYRE IS HAVING BASEMENT JUST WITH THE SIDE OF FOUNDATION WHICH CAUSED SETTLEMENT AND CRACKS IN THE STRUCTURES

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd