Earth work in high embankments, Civil Engineering

Assignment Help:

Q. Earth work in high embankments?

(a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the boundary.

(b) Borrow pits must be laid out as the Engineer directions. The pits must be rectangular. The sides of borrow pits next to the toe of bank must be sloped at one to two and else where at 1 to 1.

(c ) Where the ground is low end swampy, the outer or most distant half of the borrow pits is to be excavated first.

(d) In banks over 3 metres high, the outer halves only of the borrow pits are to be marked out.


Related Discussions:- Earth work in high embankments

Explain statically indeterminate structures, Explain Statically Indetermina...

Explain Statically Indeterminate Structures  Fall into two categories:   1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected

Define reinforcing steel - limitations of ultrasonic system, Define Reinfor...

Define Reinforcing Steel - Limitations of Ultrasonic System? The sound velocity measurement taken parallel to the reinforcing bars embedded in the concrete will be markedly hig

What is imp rest stores, Q. What is Imp rest Stores? Material obtained ...

Q. What is Imp rest Stores? Material obtained not for specific works but as a standing advance for the purpose of material urgent requirements as and when they arise should wit

Surveying, What''re the procedures of contouring by graphical interpolation...

What''re the procedures of contouring by graphical interpolation

Minimum and maximum area of reinforcement, Q. Minimum and maximum area of r...

Q. Minimum and maximum area of reinforcement? Minimum area of reinforcement vs. maximum area of reinforcement Beams can be designed to be larger than required for strength

Shape and soundness test - testing of aggregates, Shape and Soundness Test ...

Shape and Soundness Test - Testing of aggregates: Shape For providing a good interlock and strength, the aggregates should be cubical in shape. Elongated and flaky pa

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Irrigation, what is a balancing depth

what is a balancing depth

Max. moment at cantilever, max. moment at cantilever in up or down of suppo...

max. moment at cantilever in up or down of support or free of end

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd