Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Face recognition using java, how we get a perfect tutorial for face recogn...

how we get a perfect tutorial for face recognition using java

What are handshaking signals, a. Explain the hardware mechanism for handlin...

a. Explain the hardware mechanism for handling multiple interrupt requests. b. What are handshaking signals? Describe the handshake control of data transfer during input and out

#artificial intelligence, does matlab contain procedures for knoledge repre...

does matlab contain procedures for knoledge representation? if yes where can i find it?

Pipelining - computer architecture, Pipelining - computer architecture: ...

Pipelining - computer architecture: The Pipeline Defined According to John Hayes "A pipeline processor consists of a sequence of processing circuits, called stages or

Clocked sr flip flop, Clocked SR flip flop A clock pulse is a...

Clocked SR flip flop A clock pulse is a sequence of logic 0, logic 1, and logic 0 occuring on the CLK input. Time t n occurs before the clock pulse and time t n+1

What is span of control, Q. What is span of control? Span of control te...

Q. What is span of control? Span of control tells the ratio among superiors and subordinates. Generally organizations are having two different types of spans. They are Wide Spa

What is commitment unit, What is commitment unit? When out-of-order exe...

What is commitment unit? When out-of-order execution is permitted, a special control unit is required to guarantee in-order commitment. This is known as the commitment unit. It

Java Programming, How to parse n size depth node in java and create output ...

How to parse n size depth node in java and create output in same tree format?

Can we change the color of the worksheet tabs in my workbook, In a word,you...

In a word,you can't. It would certainly be helpful to be able to color-code your worksheet tabs. For some reason, Microsoft hasn't executed this feature, which has been available i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd