Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Slope deflection equations, Slope Deflection Equations for a Member: I...

Slope Deflection Equations for a Member: In this section, we will develop a few general equations needed for further discussion in the moment distribution context. Fig

Determine a sample rate required for telephone conversation, A sample rate ...

A sample rate of            is required for a good quality representation of telephone conversation. A sample rate of 50 times/second /mile of distance travelled are needed fo

Define the programmable logic devices (pld), Define the Programmable logic ...

Define the Programmable logic devices (PLD)? In the world of digital electronic systems there are three essential kinds of devices 1.memory, 2.microprocessors, and 3.logic. The

What is chattering as applied to mechanical switches, What is chattering as...

What is chattering as applied to mechanical switches used in digital systems and why do they occur?  What is its effect on the functioning of a sequential circuit? Ans Chat

Determine the boolean expression using k-map, Reduce the following equation...

Reduce the following equation using k-map Y = BC‾D‾ + A‾BC‾D + ABC‾D + A‾BCD + ABCD Ans. Multiplying the first term with (A+A') Y = A'BC'D' + ABC'D' + A'BC'D + ABC'D + A'BCD +

Which electro mechanical switch had fewer moving parts, The             el...

The             electro mechanical switch (developed in 1938) had fewer moving parts than earlier switches. (A)  No. 1ESS                                 (B)  Strowger (

Hypertext markup language, Web pages or materials which are in the form of ...

Web pages or materials which are in the form of hypermedia documents accessed through Internet can be located anywhere in world. No matter from where they originated, most Web d

Security, We now consider the relation between passwords and key size. For ...

We now consider the relation between passwords and key size. For this purpose consider a cryptosystem where the user enters a key in the form of a password. Assume a password consi

Explain dos function call with one illustration, Explain DOS function call ...

Explain DOS function call with one illustration DOS function call In order to use DOS function calls, always place function number into register AH and load all other re

Dram simm, The most common type of non-volatile memory is the ROM device. T...

The most common type of non-volatile memory is the ROM device. This device is read only and the data is masked into the chip during manufacture. Variations of the ROM are one off p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd