Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Determine less propagation delay in synchronous-ripple ckt, You have two co...

You have two counters counting up to 16, built through negedge DFF, First circuit is synchronous and second is "ripple" as cascading, which circuit has a less propagation delay? Wh

Difference between abstract class and interface, Abstract class: Abstract c...

Abstract class: Abstract classes are the class where one or more methods are abstract but not essentially all method has to be abstract. Abstract methods are the methods, which are

What is meant by "method-wars" in programming, Before 1994 there were dissi...

Before 1994 there were dissimilar methodologies like Rumbaugh, Booch, Jacobson, and Meyer etc who followed their own notations to mould the systems. The developers were in a di

Explain how presentation layer helps in establishing, Explain how presentat...

Explain how presentation layer helps in establishing and processing data in End to End layers. The idea of the presentation layer is to stand for information to the communicati

Show the example of internet address, Q. Show the example of internet addre...

Q. Show the example of internet address? The following can be a typical person understandable address on Internet: VVS @ expertsmind.us VVS is an username which in gene

Computer architecture, 6.How can we improve the performance of pipeline pro...

6.How can we improve the performance of pipeline processing

Explain open-systems interconnections architecture model, Q. Explain Open-s...

Q. Explain Open-systems interconnections architecture model The most common network architecture model is the open-systems interconnections (OSI). Figure shows the ISO (Intern

Is the process before and after the swap are the same, Is the Process befor...

Is the Process before and after the swap are the same? Give reason. Process before swapping is residing in the primary memory in its original form. The regions (text, data and

How linq is beneficial than stored procedures, There are couple of benefit ...

There are couple of benefit of LINQ over stored procedures.   1. Debugging - It is really very difficult to debug the Stored procedure but as LINQ is part of .NET, you can us

Design a memory buffer of limited size, Extend task 1 so that it now suppor...

Extend task 1 so that it now supports a memory buffer of limited size. Provide the same functionality as task 1 except now make the server work with a limited buffer size. Like

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd