Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Collision free network, Hello Sir/Mam, Actually i am trying to implement th...

Hello Sir/Mam, Actually i am trying to implement the concept of MAC layer protocols in NS2..... But unfortunately i am not able to do that.... and not even able to get the code fo

C++, find the minimum total number of shelves including the loading process...

find the minimum total number of shelves including the loading process

Explain conditions under which a deadlock situation arise, What are conditi...

What are conditions under which a deadlock situation may arise? A deadlock situation can arise if the following four conditions hold concurrently in a system:  a. Mutual exc

Working of compact disk - computer architecture, Working of compact disk: ...

Working of compact disk: A CD is built from 1.2 mm thick, approximately all-pure polycarbonate plastic and its weighs is approximately 15-20 grams. From the core outward compo

Set up the site structure, Structuring the Web site is first step towards b...

Structuring the Web site is first step towards building the corporate Web site. Structuring includes creating a folder that includes all our picture files, text files and database

Comparison between centralized and distributed spc, Explain the principles ...

Explain the principles of operation of centralized SPC and distributed SPC and compare their performance. All the control equipment is replaced with a single processor that mus

?????, c program??????????

c program??????????

Programming, how can compare alphabates of two words in c programming ?????...

how can compare alphabates of two words in c programming ?????

What is the use of unions in c ?, Unions allow the same area of memory to b...

Unions allow the same area of memory to be accessed as different data types. The insurance example above would not work. Unions are useful (often in embedded programming) when i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd