Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is concurrent control, What is concurrent control? Control resides...

What is concurrent control? Control resides concurrently in various independent objects, every a separate task. A task can wait for input but other task continues implementatio

What is a rendezvous point?, You insert rendezvous points into Vuser script...

You insert rendezvous points into Vuser scripts to imitate heavy user load on the server. Rendezvous points instruct Vusers to wait during test implementation for multiple Vusers t

Explain the concept of top-down design for a program, Explain the concept o...

Explain the concept of top-down design for a program. Top down Design: A top-down approach is fundamentally breaking down a system to gain insight into its compositional s

Network for digital methods in the arts and humanities, Network for Digital...

Network for Digital Methods in the Arts and Humanities: Europe has seen a signifi cant investment in the digitisation of its cultural heritage as part of the worldwide establi

Shared memory and distributed memory, Shared Memory Refers to the memor...

Shared Memory Refers to the memory part of a computer system in which the memory can processed directly by any of the processors in the system. Distributed Memory Refer

What is reentrant tasks and functions, What is reentrant tasks and function...

What is reentrant tasks and functions Tasks and functions without optional keyword automatic are static , with all declared items being statically allocated. These items will b

What is presentation layer, Q. What is Presentation layer? Presentatio...

Q. What is Presentation layer? Presentation layer: When two hosts are communicating with each other they might use different coding standards and character sets for represent

Propositional inference rules, Propositional Inference Rules: Proposit...

Propositional Inference Rules: Propositional Inference Rules Equivalence rules are mostly useful because of the vice-versa aspect, that means like we can search backwards and

Explain about zip drive, Q. Explain about Zip Drive? Zip Drive: Loads...

Q. Explain about Zip Drive? Zip Drive: Loads of files, Volumes of data have definitely increased onus on today's computer user and protection of this data is what bugs every

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd