Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Loop used to show properties, Normal 0 false false false ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4  A loop invariant is

What is fork, What is Fork Clk gets its value after 1 time unit, rese...

What is Fork Clk gets its value after 1 time unit, reset after 10 time units, enable after 5 time units, data after 3 time units. All the statements are executed in parallel.

Explain about common addressing modes, Q. Explain about common addressing m...

Q. Explain about common addressing modes? Most of machines use a set of addressing modes. The following tree displays common addressing modes: Figure: Common Addres

How many flip-flops are required to construct mod 30 counter, How many flip...

How many flip-flops are required to construct mod 30 counter ? Ans. Mod - 30 counter +/- requires 5 Flip-Flop as 30 5 . Mod - N counter counts overall ' N ' number of state

Find the largest and the smallest array values, Q. Find the Largest and the...

Q. Find the Largest and the Smallest Array Values? Write down a program to find the largest as well as the smallest numbers from a given array. This program uses JGE (jump grea

Recent parallel programming models, A model for parallel programming is an ...

A model for parallel programming is an abstraction in addition its machine architecture is independent. A model is able to be implemented on different hardware and memory architect

Simple maze game, The following is a requirements specification for a simpl...

The following is a requirements specification for a simple game based on a player moving through a maze of connected rooms from an entrance door to an exit door. The required sy

What is npblox framework, Designed, developed, tested and documented the de...

Designed, developed, tested and documented the demo created for NPBlox framework. NPBlox framework is a framework which enabled developers to create CLI/WEB/SNMP interfaces for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd