Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Emerging cloud computing technology, A chart illustrating the differences a...

A chart illustrating the differences among the new cloud-based technologies (Workday) and the traditional . a. The new cloud-based solutions benefit Workday from every facet wh

Define a structure, Define a structure. A structure having an ordered g...

Define a structure. A structure having an ordered group of data objects. Unlike the elements of an array, the data objects within a structure can have varied data types. Every

What is the cih, CIH, also known  as Chernobyl or Spacefiller, is a Microso...

CIH, also known  as Chernobyl or Spacefiller, is a Microsoft Windows computer virus which first emerged in 1998. It is one of the most damaging viruses, overwriting critical inform

Show network topology in digital system, Q. Show Network Topology in digita...

Q. Show Network Topology in digital system? This deals with the geometrical arrangement of nodes (endpoints consisting of physical devices such as terminals, printers, PCs, and

What is an operating system, What is an operating system? An operating...

What is an operating system? An operating system is system software which provides interface between hardware and user. The operating system gives the means for the proper uti

Discussion., Functionality first and then Security?

Functionality first and then Security?

E-R DIAGRAM, In academic year a researcher can either be employed as a prof...

In academic year a researcher can either be employed as a professor or a lab assistant.there are three kinds of professors: assistant,associate and full professors.drow E-R DIAGRAM

Write hit policies, Write Hit Policies: Write through o   Upd...

Write Hit Policies: Write through o   Update next level on every write o   Cache is always clean o   A lots of traffic to next level (mostly write) Write

What are the types of assemblies, There are two types of assemblies:- 1...

There are two types of assemblies:- 1. Private Assemblies 2. Shared Assemblies

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd