Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Information technology or information system, Information Technology or Inf...

Information Technology or Information System Before going further we need to clarify what we mean by the term information system. It is easy to confuse terminology as many tex

The files in tif format, Image Capturing Download the following grey lev...

Image Capturing Download the following grey level 512x512 standard images in TIF format: a-Lena       b-Baboon     c-Bridge       d-Airfield Use Matlab to decrease the siz

Bi polar junction transistor, draw input and output charectoristics of BJT ...

draw input and output charectoristics of BJT and justify CE configuration provides large current amplification

Multi-threaded processors, The use of distributed shared memory in parallel...

The use of distributed shared memory in parallel computer architecture however the use of distributed shared memory has the problem of accessing the remote memory that results in l

How do you perform functional testing under load, Functionality under load ...

Functionality under load can be tested by running various Vusers concurrently. By enhancing the amount of Vusers, we can verify how much load the server can sustain.

Enumerate about the trackball device, Enumerate about the trackball A t...

Enumerate about the trackball A trackball is a two-dimensional positioning device, a spaceball provides six degrees of freedom. Unlike the trackball, a spaceball does not actua

What is reduction, What is reduction?  A reduction is a way of changing...

What is reduction?  A reduction is a way of changing one problem into another in such a way that a solution to the second problem can be used to explain the first problem.

Mention the two subsystem relationship, Mention the two subsystem relations...

Mention the two subsystem relationship. The relationship among two subsystems can be: Client-server Peer-peer

Show the properties of text box, Q. Show the properties of Text Box? Th...

Q. Show the properties of Text Box? The tag is used to specify where user input is expected. It has several attributes, of which TYPE attribute is used to specify th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd