Draw an activity-on-arrow network diagram for the project, Project Management

Assignment Help:

Question:

(a) Back~to~Future International, a recently setup non-profit organization by the students of Fashion & Design Institute, has decided to organize a fashion show. The objective of the event will be to give members of the organization opportunities to express their hidden and innovative talents. The event will be held at the Moteelall International Convention Centre.

A project team has been set up and the main activities and precedence for the project have been identified and the estimated durations assessed as follows:

1654_Draw an activity-on-arrow network diagram for the project.png

i. Draw an activity-on-arrow network diagram for the project. Include full information on earliest and latest event times.

ii. Determine the minimum completion time and the critical path.

(b) Describe how each of the following changes to task durations (on their own) would affect the critical path and project duration.

i) Task A - reduced to 3 weeks
ii) Task E - increased to 5 weeks
iii) Task G - reduced to 8 weeks

(c) List 2 advantages and 2 disadvantages of using an activity-on-node diagram for a project plan in comparison with using a Gantt chart.

(d) Why do we carry out monitoring and control on a project?

(e) Project managers often have to create routine reports for example weekly or monthly. List 2 reports that the project manager may have to write that are not routine.

(f) In order to decide if the project is on schedule what four key pieces of information must the project manager possess?


Related Discussions:- Draw an activity-on-arrow network diagram for the project

Drivers of the age of project management, Question 1: (a) Elaborate on...

Question 1: (a) Elaborate on the drivers of the ‘Age of Project Management'. (b) Differentiate between the terms ‘Project Management' and ‘Line Management'. (c) Expla

What are the contents of post completion report, What are the contents of p...

What are the contents of post completion report? Contents of a PC (post completion) report: a. Outcomes documented through staff appraisals undertaken b. Stakeholder surv

Implementing tqm techniques, IMPLEMENTING TQM TECHNIQUES IN LIBRARY AND INF...

IMPLEMENTING TQM TECHNIQUES IN LIBRARY AND INFORMATION CENTRE MANAGEMENT: Total Quality Management (TQM) as a management tool needs to radically rethink the way in which a lib

Work breakdown structure, got a case study of IKEA..have to make ghantt cha...

got a case study of IKEA..have to make ghantt chart and work breakdown structure

Disadvantages of participative management, Disadvantages of participative m...

Disadvantages of participative management: There are also disadvantages to participative decision-making.  Implementation of the tough decisions taken by the  management th

Data input errors, Discuss the typical data input errors in project managem...

Discuss the typical data input errors in project management.

Process of diagnosing the system, Question 1: What are the steps involv...

Question 1: What are the steps involved in the process of diagnosing the system? Steps involved in the process of diagnosing the system. Question 2: What are the maj

Modification of supply - aggregate planning, Modification of Supply - Aggre...

Modification of Supply - Aggregate Planning Some of the methods by which we can modify the supply to match the demand are: a.Hiring and Lay off of Employees: As this poli

Managing project quality as per pmi, M a n a ging Project Quality as pe...

M a n a ging Project Quality as per PMI Project Management Institute (PMI) is a global organisation for the project management profession; it is engaged in setting professi

How important are the stakeholders, Q. How important are the stakeholders? ...

Q. How important are the stakeholders? The most significant stakeholder of course is your client or customer. Conversely that perhaps in excess of one person that the sponsor a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd