Determine the thermal efficiency, Mechanical Engineering

Assignment Help:

A combined cycle plant is designed to develop 200MW power. The air is obtained by the compressor at 300K and 1 bar pressure. The maximum temperature of the gas turbine cycle is limited to 800'C. The pressure ratio is 8.

The data for steam plant is as follows:-

The exhaust gas coming out of gas turbine is heated to 800 degree C before entering boiler furnace. Steam is generated at sober and 600 degree C. The exhaust gas temperature is limited to 200 degree Celsius. Suppose pressure is 0.05 bar.

Consider isentropic efficiencies of compressor and turbine, determine the following:-

a) Thermal efficiency of each plant and combined plant.

b) Ratio of air supplied to the compressor to the steam generated in the boiler.


Related Discussions:- Determine the thermal efficiency

Determine the stress in composite bar, Determine the stress in composite ba...

Determine the stress in composite bar: How do you determine the stress in composite bar? What is Modular Ratio? Sol.: It becomes essential to have a compound tie or strut

Reinforced concrete design, You are tasked with the analysis and design of ...

You are tasked with the analysis and design of the gravity and wind framing system for a 6-story office building. A part plan of the building is attached.  The plan dimensions o

Objectives of tools and equipment , Objective: After studying tools and eq...

Objective: After studying tools and equipment, you should be able to list various tools, measuring equipment required in a motorcycle workshop, and identify and use ap

Special casting methods, Special Casting Methods: 1. Die casting : D...

Special Casting Methods: 1. Die casting : Die casting is a permanent mould casting techniques in which molten metal is forced in the mould cavity under a pressure of 700 to

Calculate mass of the shoes, A centrifugal clutch is to be prepared to tran...

A centrifugal clutch is to be prepared to transmit 15 KW at 900 r.p.m. The shoes are four in number. The speed at which the engagement begins is 3/4 th of the running speed. The in

Final year project, Project is about Heat exchanger kit named TE 93.....Pro...

Project is about Heat exchanger kit named TE 93.....Project guide has told us to do something with it..without modifying the project largely.....i came up with change of material o

Sand blasting handling method, Sand blasting handling method:        ...

Sand blasting handling method:             On last experiment we had decided to use 3.0 bars as it shown better result. Now we had to investigate the sand blasting handling

Evaluate tension in the string, A smooth sphere of radius 15 cm and weight ...

A smooth sphere of radius 15 cm and weight 2 N is supported in contact with a smooth vertical wall by a string whose length simlar the radius of sphere. The string joins a point on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd