Determine the preliminary settlement analysis, Civil Engineering

Assignment Help:

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stratum was 30 kN/m2.

If the following variations occurred in the assumptions, verify the revised value of ultimate settlement and the settlements at the end of the loading period and that at 3 years after the completion of the building.

(i) The loading period was 2 years, which was not considered in the preliminary analysis.

(ii) Borings shown 25% more thickness for the clay layer than originally assumed.

(iii) The water table got lowered permanently during construction by 1.5 metres.

 


Related Discussions:- Determine the preliminary settlement analysis

Transportation engineering, What areb the philosophical elements of strateg...

What areb the philosophical elements of strategic planning?

Define marine growth - underwater inspection of bridge, Define Marine growt...

Define Marine growth - underwater inspection of bridge? Generally, in seawater marine growth takes place. Acid generated by the marine growth attacks concrete. This can lead to

Soil testing, what is black cotton soil in dry condition

what is black cotton soil in dry condition

Bearing, convert the following whole circle bearing to QBs... WCB of AB=45 ...

convert the following whole circle bearing to QBs... WCB of AB=45 degree and 30 mintus

What are dissimilar applications of draglines, Question: What are dissi...

Question: What are dissimilar applications of draglines, backhoes and shovels? Answer: An excavator is distinct as a power-operated digging machine and it includes di

Road base and base course in flexible carriageway, Road base vs. base cours...

Road base vs. base course in flexible carriageway Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributi

Rectangular tie, how would you perform a rantangular tie ,using an optical ...

how would you perform a rantangular tie ,using an optical square

Shrinkage of concrete in prestressed members, Shrinkage of concrete in pres...

Shrinkage of concrete in prestressed members The shrinkage of concrete in prestressed members results in a shortening of ensioned wires and hence contributes to the loss of st

Determine the station and elevation of turning point, A -3.00% grade inters...

A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft.  A 350-ft vertical curve connects the two grades.  Determine the station and elevation of turning po

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd