Determine the preliminary settlement analysis, Civil Engineering

Assignment Help:

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stratum was 30 kN/m2.

If the following variations occurred in the assumptions, verify the revised value of ultimate settlement and the settlements at the end of the loading period and that at 3 years after the completion of the building.

(i) The loading period was 2 years, which was not considered in the preliminary analysis.

(ii) Borings shown 25% more thickness for the clay layer than originally assumed.

(iii) The water table got lowered permanently during construction by 1.5 metres.

 


Related Discussions:- Determine the preliminary settlement analysis

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

Flooring, construction detail of all types of flooring

construction detail of all types of flooring

Airport lighting, Airport Lighting: Lighting of Approach to Runway ...

Airport Lighting: Lighting of Approach to Runway A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed a

Determine the limit states of serviceability, Limit States of Serviceabilit...

Limit States of Serviceability These are those limit states which point out to the inability of a structure or a structural component in functioning properly as per the intende

Chemistry, What is the difference between scale and sludge

What is the difference between scale and sludge

Verify the coefficient of elastic uniform compression, Verify the coefficie...

Verify the coefficient of elastic uniform compression if a vibration test on a concrete block of 1 m cube gave a resonant frequency of 36 Hz in vertical vibration. The weight of

Dressing of stones.., what is dressing of stones and its various types

what is dressing of stones and its various types

Explain damage inspections - underwater inspection of bridge, Explain the D...

Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime

What is multiple-cell box girder, Q. What is Multiple-cell box girder? ...

Q. What is Multiple-cell box girder? Multiple-cell box girder: cells connected by top flanges vs. cells connected both by top and bottom flanges When the depth of a box gi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd