Determine the preliminary settlement analysis, Civil Engineering

Assignment Help:

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stratum was 30 kN/m2.

If the following variations occurred in the assumptions, verify the revised value of ultimate settlement and the settlements at the end of the loading period and that at 3 years after the completion of the building.

(i) The loading period was 2 years, which was not considered in the preliminary analysis.

(ii) Borings shown 25% more thickness for the clay layer than originally assumed.

(iii) The water table got lowered permanently during construction by 1.5 metres.

 


Related Discussions:- Determine the preliminary settlement analysis

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

Determine the flow rate if the pump is turned at 100 rpm, One pump lifts st...

One pump lifts storm water from a storage tunnel wet well a constant vertical distance of 150 ft. The equivalent length Le of the 14 in diameter piping is 1,000 ft. Pressure drop d

Flemish bond, what is the advantages of Flemish bond

what is the advantages of Flemish bond

Tack coat – emulsified asphalts vs cutback asphalts, Tack coat - emulsified...

Tack coat - emulsified asphalts vs. cutback asphalts Emulsified asphalt is a suspension of asphalt in water by employing an emulsifying agent that imposes an electric charge o

Length is constructed in first phase of construction, In construction of a ...

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

Classification of timber based on availability:, Classification Based on Av...

Classification Based on Availability: Forest departments categorized timbers based on the availability as X=Most common. 1415 m 3 or more per year Y=Common. 355 m 3 to 1415

Airport management, Airport Management: Airlines (a)        Adequ...

Airport Management: Airlines (a)        Adequate space for each airline for ticketting, check-in and baggage handling, and (b)       Adequate space for airline staff.

Surveying, length of the line measured with 20m chain found to be 250m.calc...

length of the line measured with 20m chain found to be 250m.calculate true length if the chain was 10cm long

Measurements, Explain the concept of average velocity

Explain the concept of average velocity

Concrete, what are the appropriate methods of concreting

what are the appropriate methods of concreting

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd