Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Calculate the weighted cost of capital calculation for firm, Ed Mettway was...

Ed Mettway was concerned about his firm's ability to acquire the necessary property, plant, and equipment to take advantage of steadily increasing sales. Touring Enterprises, estab

Explain development cost, With the introduction of computer-generated anima...

With the introduction of computer-generated animated films (CGI), there has been much discussion of the impact on the movie industry. For example, illustrators need to have differe

Cgs, asdfdf afd s

asdfdf afd s

Which of the floowing is not capital budgeting decision, 1. when using the ...

1. when using the internal rate of return method to evaluate capital spending on a new project, the project will be accepted if the internal rate of return is equal to or greater t

Break even point, Campground Inc. is considering the production and sale of...

Campground Inc. is considering the production and sale of propane lamps. Annual fixed costs associated with the project are expected to total $60,000. In addition, each lamp would

Calculate the put price, Question: Suppose that the stock now sells at ...

Question: Suppose that the stock now sells at $80, and the price will go up by 5% or down by 5% at the end of first six month (t = ½).  Then, the price will either go up by 10%

Calculate the manufacturing cost per unit, the following activities relatin...

the following activities relating to indirect production costs: Activity Activity Costs Cost Drivers Machine Setup $180,000 1,500 setup hours Materials Handling $50,000 12,500 poun

You should be willing to pay the worker , You are the manager of a firm tha...

You are the manager of a firm that sells output at a price of $40 per unit. You are interested in hiring a new worker who will increase your firm's output by 2,000 units per year.

Calculate manufacturing overhead for the year, Baka Corporation applies man...

Baka Corporation applies manufacturing overhead on the basis of direct labor-hours. At the beginning of the most recent year, the company based its predetermined overhead rate on t

Prepare a forecast of cashflow, A company is to produce an IC and a chip si...

A company is to produce an IC and a chip size of 120mm2 has been estimated, based on using a full-custom nMOS technology on 8" wafers. The process has a 92% yield at the wafer fab

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd