Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Calculate the equivalent annual cost, A plant is considering the replacemen...

A plant is considering the replacement of a piece of equipment in its materials handling system with a new piece. If the company's cost of capital is 10%. Should the present asset

Required ledgers in financial system, Required Ledgers in Financial System ...

Required Ledgers in Financial System In the financial Systems the Required ledgers are as: The General Ledger Debtors Ledger Creditors Ledger

Balance sheet and income statement, First of all, look at the balance sheet...

First of all, look at the balance sheet and income statement as a whole and spot the problem with it. Answer all questions given in the question + dig into each element of the bala

Uses of funds, Dividends                                                   ...

Dividends                                                                                        ................ Non-operating losses not passed through P and L A/c

Cost estimation methods, using the high low method how do i calculate the c...

using the high low method how do i calculate the costs that are expected when the output expected is out of the range given for example cost prdctn volume 110000

Find the total amount of product costs, for financial accounting purposes, ...

for financial accounting purposes, what is the total amount of product costs incurred to make 10,000 units?

How would i calculate the debt amortization, How would I calculate the debt...

How would I calculate the debt amortization for a bond issued at discount with a maturity of 12 years, market interest rate at issue 10% annually, 5% semi annually, and has a state

Describe time sheets and job cards, (a) Describe briefly how the following ...

(a) Describe briefly how the following are used in the accounting for labour: (i)   time sheets (ii)   job cards. (b) The following details relate to the labour in a produ

Calculate the net effective yield, A Government issued a number of index-li...

A Government issued a number of index-linked bonds on 1 June 2000 which were redeemed on 1 June 2002.  Each bond had a nominal coupon rate of 3% per annum, payable half yearly in a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd