Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Amortization of bond premium for the year, on the first day of the current ...

on the first day of the current fiscal year $2,000,000 of 10 year 7% bonds with interest payable annually, were sold for $2,125,000. Present enteries to record the following transa

prepare a simple balance sheet, Assume that Banc One receives a primary de...

Assume that Banc One receives a primary deposit of $1 million. The bank must keep reserves of 20 percent against its deposits. Prepare a simple balance sheet of assets and liabilit

Sgtatement of Cash Flow, “The statement of cash flows is the easiest of the...

“The statement of cash flows is the easiest of the basic financial statements to prepare because you know the answer before you start. You compare the beginning and ending balances

Determine the net book value, NSC Ltd. has a 31 May fiscal year-end. NSC di...

NSC Ltd. has a 31 May fiscal year-end. NSC disposed of its Information Systems Group (ISG) on 31 January 20X3. ISG had a net loss (after taxes) of $37,700,000 in 20X3, to the date

Estimate finished goods cost of goods sold , ln an attempt to conceal a the...

ln an attempt to conceal a thefi of funds, Kaito Kid, controller of Shinichi Products, lnc. placed a bomb in the company s record vault. The ensuing explosion left only fragments o

Which of the following are easy to trace to individual jobs, Which of the f...

Which of the following are easy to trace to individual jobs?:   A. direct materials and overhead B. direct materials and direct labor C. direct labor and overhead

Basic, sir i want to know the whole procress of costing

sir i want to know the whole procress of costing

Calculate the cash value financing interest rate , Calculate the today's ca...

Calculate the today's cash value of a car that can be leased with $5000 down, bi-weekly payments of $199 over 4 years and a buy-back value of $15,000 at the end of the lease if the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd