Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Wacc under every of the capital structures, Imperial Sandwich Plc is to be ...

Imperial Sandwich Plc is to be established shortly. The founders are considering their options with regard to capital structure. A total of £5 m will be required to establish the b

Controllable and non controllable costs, Controllable and Non Controllable ...

Controllable and Non Controllable Costs Controllable costs can be influenced on the level of authority at that they are being analyzed when non-controllable costs cannot.

#title, compare tradition costing and activity costing methods of overhead...

compare tradition costing and activity costing methods of overheads abpsrption based on production units,labour hourd and machine hours

What amount of amortization expense, Day Corporation purchased a patent on ...

Day Corporation purchased a patent on January 1, 2012 for $360,000. The patent had a useful life of 10 years at that date. In January of 2013, Day successfully defends the patent

Find out the cost per unit, Find Out the Cost per Unit Material A is ...

Find Out the Cost per Unit Material A is added at the start of a production process. Overheads and Labor are added continuously throughout the production process. At the endi

Application of a hand-held clinical thermometer, In an application of a han...

In an application of a hand-held clinical thermometer for the National Health Service it is required to use disposable temperature sensors and digital read out of temperature betwe

Direct materials total variance, Direct Materials Total Variance Direc...

Direct Materials Total Variance Direct materials total variances refer to the difference between the standard direct material cost of the actual production volume and the actu

Required cost of goods manufactured statement, These balances for a company...

These balances for a company x Raw materials $40,000 Work in process $30,000 Finished goods $60,000 for the current year the company estimated that it would work 150.000 m

Decision analysis , can you guys do a project which is due in 2 weeks

can you guys do a project which is due in 2 weeks

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd