Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Process of setting standards in standard costing, Process of Setting Standa...

Process of Setting Standards in Standard Costing Establishing correct a standard is extremely important due to the accuracy of the standards usually finds out the success of t

Calculate the bad debt estimation, Q. 1. The 31st December 2009 trial balan...

Q. 1. The 31st December 2009 trial balance of Anika Co. reported the following information. Dr. Cr. Allowance for Bad Debts........................... $1,300 During the year 201

Materials variance, The following standard costs were developed for one of ...

The following standard costs were developed for one of the products of Ferrars Company: Standard Cost Card Per Unit Materials: 4 feet x $14.25 per foot $ 57.00 Direct labor: 8 hour

Process costing, Process Costing It is a costing method, which is appl...

Process Costing It is a costing method, which is applied wherever there are standard operations along with continuous production of homogeneous as identical units. Consequentl

WACC, formula for calculting WACC

formula for calculting WACC

Last in first out or lifo, Last in first out or LIFO LIFO is based upo...

Last in first out or LIFO LIFO is based upon the assumption such the stock purchased last is issued first. Stock valuation should here be based upon the prices ruling on acqui

Prepare the purchases ledger control account, You work for a firm of accoun...

You work for a firm of accountants as a junior accounts assistant and part of your role is to prepare clients' ledgers accounts from incomplete records. A client of the firm you

Calculate the cash flow - capital cost, A company is evaluating the followi...

A company is evaluating the following lease or buy option.  A four year lease with annual payments of $25,000 payable at the beginning of the year. The tax shield is available a

Typical causes of labour variances, Typical Causes of Labour Varian...

Typical Causes of Labour Variances Labour Rate Variances a) Higher rates being paid than planned because of wage raise awards. b) Lower or Higher grade of work

Calculate labour time or efficiency variance, standard hours = 5000 standa...

standard hours = 5000 standard wages = Rs.3/hr actual hours worked = 5600 hrs actual wages paid = 17920

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd