Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Prepare the appropriate entries for january 1, A corporation acquired a tru...

A corporation acquired a truck on July 1, 2012, at a cost of $162,000. The truck has a six-year useful life and an estimated salvage value of $18,000. The straight-line method of d

Compute the total amount of current assets, Balance Sheet Classi?cations an...

Balance Sheet Classi?cations and Relationships: Shelley and Co. has the following balance sheet elements as of December 31, 2012. Land. . . . . . . . . . . . . . . . . . . . . .

Purpose, what are the purposes of cost accounting

what are the purposes of cost accounting

Analyse the data and prepare a report, The data set for the assignment is a...

The data set for the assignment is about breast cancer.  Some of these data have been changed for the purposes of this assignment so the results from the analysis of this file may

Compute break even assuming direct materials cost, Below find production an...

Below find production and sales information for Herrestad Company. We will use this same company for all the SLPs in this course.  Product information

Bases of cost classification, Bases of Cost Classification These vario...

Bases of Cost Classification These various bases of cost classification are summarized in the diagram underneath as: Here, we will usually refer to either of these ter

The managing director is dubious , A  firm of printers  is contemplating  j...

A  firm of printers  is contemplating  joining  the uniform  costing  system operated by  its Trade Association but the Managing Director is dubious about the benefits of becoming

Find the discount rate and wacc, 1. A company is considering a project that...

1. A company is considering a project that requires an initial investment of $100 million and will pay $20 million of each of the next 10 years, and nothing thereafter. The company

Example of high - low method of cost estimation, Example of High - Low Meth...

Example of High - Low Method of Cost Estimation Based on the performance, such you have been provided along with the given information regarding ABC Ltd for the year ended on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd