Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Explain with examples and cite were needed, What are the distinguishing cha...

What are the distinguishing characteristics of these types of stock- describe any one of them. What is the difference between par value, book value and market value of stock? Expla

Budgeted, Question: Yamba Home Products is just beginning its fourth quar...

Question: Yamba Home Products is just beginning its fourth quarter, in which peak sales occur. The company has requested a $12,000, 90-day loan from its bank to help meet cash re

Regression Analysis and Cost Estimation, High-Low method of cost estimation...

High-Low method of cost estimation and Number of Photocopies as the cost driver, what would be the resulting cost equation for Maintenance Costs?

Calculate monthly excess returns, In this exercise you will familiarize you...

In this exercise you will familiarize yourself with index models, beta and CAPM estimation. Download the spreadsheet data_question3.xlsx from Sakai and use the data contained there

Manufacturing Overhead, Does Manufacturing Overhead include the following:1...

Does Manufacturing Overhead include the following:1)Material Handling - labour for Purchasing Material, Shipping (inbound for raw materials and outbound for finished product - also

Mr, Extracts from P Co''s records for last month are as follows: ...

Extracts from P Co''s records for last month are as follows: BUDGET ACTUAL PRODUCTION 7,000 UNITS 7,200 UNITS Direct Material $42,000 $42,912 Calculate

Find the amount capitalized for the patent account, Gomez incurred $350,000...

Gomez incurred $350,000 of research and development costs to develop a product for which a patent was granted on January 2, 2008. Legal fees and other costs associated with the re

Internal sources of funds, While we are looking for sources funds it is oth...

While we are looking for sources funds it is other than natural to start searching from home. What do we have? During examining the requirement for working capital we could also ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd