Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Example of economic order quantity, Example of Economic Order Quantity ...

Example of Economic Order Quantity The EOQ model supposes : - Annual demand is recognized - Hold costs are constant and recognized - Ordering costs are recognized a

Utility of break even point in managerial decision making, UTILITY OF BREAK...

UTILITY OF BREAK EVEN POINT IN MANAGERIAL DECISION MAKING 1. It assists in determination of sales mix 2. It assists in exploring new markets 3. It assists in deciding abo

Decision analysis , can you guys do a project which is due in 2 weeks

can you guys do a project which is due in 2 weeks

Internal users of accounting information, Describe the ways in which the ne...

Describe the ways in which the needs of internal and external users of accounting information are the same and different.

Standard cost card, Standard Cost Card It is a card record of the Stan...

Standard Cost Card It is a card record of the Standard or expected costs in producing a specified output.  This gives the physical quantities of inputs and also their monetary

#title, compare tradition costing and activity costing methods of overhead...

compare tradition costing and activity costing methods of overheads abpsrption based on production units,labour hourd and machine hours

Process losses, Process Losses Most manufacturing processes result in ...

Process Losses Most manufacturing processes result in several portion of the raw materials utilized not being transformed into a reliable half losses.  These losses may take t

Compute the variable cost, A soft drink maker wants to expand into a neighb...

A soft drink maker wants to expand into a neighboring country.  They want the product bottled in that country to avoid political issues and to enhance the local image of the produc

Absorption costing, how to treat an increase in output on marginal costing

how to treat an increase in output on marginal costing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd