Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Considerations in variance investigation, Considerations in Variance Invest...

Considerations in Variance Investigation As already notice above, not all variances are investigated; this is only the material and meaningful as for cost control reasons vari

First in first out or fifo, First in First Out or FIFO FIFO method is ...

First in First Out or FIFO FIFO method is based upon the assumption such stock purchased first is issued first. Prices of stock purchased first are employed to determine the v

Calculate the equivalent units of production, A company manufactures two pr...

A company manufactures two products, Product A manufactured in Process Y and Product B manufactured in Process Z. The following information is available for a period:

What are total fixed cost, Corporation has determined the contribution marg...

Corporation has determined the contribution margin ratio is 35% and the income tax rate is 40%. Required: A) Assume break-even volume in dollars is $1,500,000. What are total fixed

Flexible Budget, Flexible budgeting is a reporting system wherin the

Flexible budgeting is a reporting system wherin the

Exploration costs, are exploration cost treated as an asset or expense or b...

are exploration cost treated as an asset or expense or both?

Compute the internal rate of return, ABC bond is a 20-year bond with face v...

ABC bond is a 20-year bond with face value $1000. The coupon payment is $25 per 6 months. The semi-annual yield is 4%. Use the PV function in Excel (or equivalent) to Önd the price

Tracking direct materials, Tracking Direct Materials Jack keeps full re...

Tracking Direct Materials Jack keeps full records of the material released to each job. When Donnie gathered up light bulbs, tape, breakers, wire, and wire nuts on the morning

Business, Purchase of office supplies.

Purchase of office supplies.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd