Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Activity based costing or abc, Activity Based Costing or ABC Absorptio...

Activity Based Costing or ABC Absorption costing shows to be relatively straightforward way of adding overhead costs to units of production utilizing, more often than not, a v

Bad debts, These are losses on account of uncollectable debts. While the am...

These are losses on account of uncollectable debts. While the amount due from debtors is irrecoverable, it is termed as bad debts. Bad debts, being loss are closed through transfer

Marginal and absorption costing, on june 2005 20 units of the product in st...

on june 2005 20 units of the product in stock the following is extracted from the companys books direct material-200 per unit,direct labour 150 per unit, variable production overhe

Cost data determination, Cost Data Determination How does one decide th...

Cost Data Determination How does one decide the cost data for products and the services which are the end result of the productive processes? The response to this question is m

Marginal cost, Marginal Cost Marginal cost is the change in a firm's co...

Marginal Cost Marginal cost is the change in a firm's cost of production. It is related to a unit change in its output, or the added cost of producing the next unit. The margin

Find the breakeven discount rate, The government of a small South Pacific i...

The government of a small South Pacific island is considering whether to allow development of a small but valuable deposit of phosphate rock. Not having the resources to develop an

Absorbtion of overheads, interaction with an expert/cost accountant to kno...

interaction with an expert/cost accountant to know the overhead absorbtion policies and procedure followed

What are the total units to be accounted for on the cost of, The Butchering...

The Butchering Department of the Santa Fe Meat Packing Corporation (a process costing corporation, FIFO costing) had 1,500 units, 1/3 completed at the beginning of the period and 1

Marginal cost, Role f marginal costing in management information system

Role f marginal costing in management information system

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd