Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

WACC, formula for calculting WACC

formula for calculting WACC

Close-end matching grants, RC School District has a large number of student...

RC School District has a large number of students in need of remedial instruction.  The superintendent of RC School System can allocated her budget between purchasing X units of re

Reasons for cost allocation, Reasons for Cost Allocation 1. To provide...

Reasons for Cost Allocation 1. To provide comparison along with externally provided services:  It helps in assessing where to continue the contact or service outsiders. 2.

Purchase procedure, what is the procedure of purchase of materials in large...

what is the procedure of purchase of materials in large organisation?

#investment appraisal techniques, #what is the formula for calculating payb...

#what is the formula for calculating payback period and what are its limitations ?

What is the total cost of the work in process, The Cutting Department of th...

The Cutting Department of the Rock Island Custom Cabinetry Corporation (a process costing production) had no work in process at the beginning of the period, 12,000 units were compl

Define the marginal, Total profit means the total revenue excluding the tot...

Total profit means the total revenue excluding the total cost of the certain products. Average profit defines the profit which comes and achieved after selling each unit. Total

Contingent liabilities, These should be distinguished from estimated liabil...

These should be distinguished from estimated liabilities. Estimated liabilities are identified liabilities where the amount is uncertain. Contingent liabilities conversely are not

Development and research cost budget, Development and Research Cost Budget ...

Development and Research Cost Budget These are costs that are discretional in nature such as they are determined on need basis via the managers concerned. Research cost is the

Standard costing, behavioral aspect of standard costing

behavioral aspect of standard costing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd