Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Reconciliation of profits, Reconciliation of Profits Reconciliation of...

Reconciliation of Profits Reconciliation of profits disclosed by Financial Accounts and Costing Accounts in an interlocking system, While interlocking cost accounting system

Capital expenditure budget, Capital Expenditure Budget This represent...

Capital Expenditure Budget This represents the expenditure on all fixed assets throughout the budget period.  Addition intended to profit future accounting periods, or expend

Compute the cost of goods - periodic inventory method, Beginning inventory ...

Beginning inventory on March 1 consisted of 2,000  units each costing $11.20 . During March, the following was purchased for inventory: Date Purchase

Labour, what is rowan incentive system

what is rowan incentive system

Tracking direct materials, Tracking Direct Materials Jack keeps full re...

Tracking Direct Materials Jack keeps full records of the material released to each job. When Donnie gathered up light bulbs, tape, breakers, wire, and wire nuts on the morning

Determine the optimum cost-time schedule , You have just been assigned to r...

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted,

What was the market rate of interest, Q. Given the below, partial bond accr...

Q. Given the below, partial bond accretion table, what was the market rate of interest when the bond was issued?     Cash     Interest

Describe time sheets and job cards, (a) Describe briefly how the following ...

(a) Describe briefly how the following are used in the accounting for labour: (i)   time sheets (ii)   job cards. (b) The following details relate to the labour in a produ

Determine the ratio of the sales, 1) Jodie received a $2000 college entranc...

1) Jodie received a $2000 college entrance scholarship. Nine month later Brian was awarded a $2100 academic proficiency scholarship for his outstanding grades in the first year of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd