You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Capital initial investment, Now along with the illustration of Ramsons at h...

Now along with the illustration of Ramsons at hand, this is not tough for us to understand that Ramsons have invested the 'money to make money'. Where has Ramsons invested the mone

Prepare a cash flow forecast, 1.  Prepare a cash flow forecast for the prop...

1.  Prepare a cash flow forecast for the proposal to launch SafeCus in 2010 for a three-year period from 1 January 2010 using the data in the body of the Case Study and discount at

Journal entry for sale of machinery, Rayya Co. purchases and installs a mac...

Rayya Co. purchases and installs a machine on January 1, 2013, at a total cost of $105,000. Straight-line depreciation is taken each year for four years assuming a seven-year life

Cost, product mix decisions with capacity constraint

product mix decisions with capacity constraint

Uses of funds, Dividends                                                   ...

Dividends                                                                                        ................ Non-operating losses not passed through P and L A/c

Cost variance and schedule variance, (i) In terms of cashflow, which month ...

(i) In terms of cashflow, which month will be the most costly for your project? (ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took

Explanation of sales revenue line, The sales revenue line demonstrates the ...

The sales revenue line demonstrates the amount of sales earned throughout the different level of activities. It can be observed that between zero and somewhere between activity B a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd