Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Find the total landed cost, What conclusion can you draw when comparing the...

What conclusion can you draw when comparing the total landed or delivered cost to the original purchase cost? What does this suggest about the importance of supply chain managem

Cost component, Identify the individual cost components and the total cost ...

Identify the individual cost components and the total cost of delivering the product from supplier to retailer.   Identify each cost in terms of the incremental addition to the pro

Calculate the opportunity costs, Suppose the Danny can prepare 50 pizzas or...

Suppose the Danny can prepare 50 pizzas or 100 sandwiches in an hour and Steve can produce 15 pizzas or 9 sandwiches. a) Draw each individual's PPF. b) Calculate the oppor

What is cost accounting, This can be explained as the process of accumulati...

This can be explained as the process of accumulating, calculating, analyzing, interpreting and reporting cost information that is both helpful and relevant to the internal and exte

Segment reporting, Juniper Ltd is a listed diversified company.  In prepari...

Juniper Ltd is a listed diversified company.  In preparing its financial statements in accordance with AASB 8, the chief operating officer has identified three operating segments:

Accounting case study, Accounting Case Study: The Champlain Career Con...

Accounting Case Study: The Champlain Career Consulting Corporation ("CCCC") is owned by three Trent graduates. Incorporated in 2009, CCCC provides a wide-range of career plann

Traditional Costing System and Job Order Costing System, Hello, I''m curren...

Hello, I''m currently doing a research on a company and planning an Activity Based Costing system since the company is using Traditional Costing system to allocate the overhead to

Development and research cost budget, Development and Research Cost Budget ...

Development and Research Cost Budget These are costs that are discretional in nature such as they are determined on need basis via the managers concerned. Research cost is the

What will be their allocated overhead?, Tyler's Consulting Company has purc...

Tyler's Consulting Company has purchased a new $15,000 copier. This overhead cost will be shared by the purchasing, accounting, and information technology departments since those a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd