Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Absorbtion, when one firm purchase other and take over its all assets.balan...

when one firm purchase other and take over its all assets.balance sheet of absorbed firm shows goodwill,should we goodwill as well?

Calculate cost of debt and cost of preferred shares, You have been asked by...

You have been asked by Mogul-Basher (MB) Ltd., a manufacturer of snowboards, to evaluate its capital structure. As a first step, you need to estimate MB's current weighted average

Prepare the appropriate entries for december 31, A corporation acquired a t...

A corporation acquired a truck on July 1, 2012, at a cost of $162,000. The truck has a six-year useful life and an estimated salvage value of $18,000. The straight-line method of d

Break even analysis, B REAK EVEN ANALYSIS Break even analysis is a bro...

B REAK EVEN ANALYSIS Break even analysis is a broadly used technique to study cost-volume-profit relationship.  It can be explained as - 'a system for determination of that le

Calculate the cost of job - manufacturing overhead, Cube Manufacturing bega...

Cube Manufacturing began two jobs during May 200X. The company had no beginning inventory. The following information is available:

Bases of cost classification, Bases of Cost Classification These vario...

Bases of Cost Classification These various bases of cost classification are summarized in the diagram underneath as: Here, we will usually refer to either of these ter

Goods and services tax, William Potter is a plumber currently operating as ...

William Potter is a plumber currently operating as a Sole Trader in Levin. William has approached you, a tax accountant, for your advice on certain tax matters. William's brothe

Overhead analysis, what do i need to know before the overhead preparation?

what do i need to know before the overhead preparation?

Determine the amount of depreciation expense, Waylander Coatings Company pu...

Waylander Coatings Company purchased waterproofing equipment on January 6, 2013, for $320,000.The equipment was expected to have a useful life of four years, or 20,000 operating ho

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd