Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Activity based costing, As controller for Edmonton Cosmetic Hospital, you a...

As controller for Edmonton Cosmetic Hospital, you are looking into the possibility of utilizing Activity- Based-Costing to assign overhead costs to patient surgeries. As a first st

Material usage variance (muv), Material Usage Variance (MUV): This is t...

Material Usage Variance (MUV): This is the variation between the actual quantity of material consumed and standard quantity which should have been consumed, expressed in terms

Cost classifications and estimation, Cost Classifications and Estimation ...

Cost Classifications and Estimation Cost classification may be defined like 'the arrangement of cost items in a logical sequence having concern to their nature and reason to b

Uses of funds, Dividends                                                   ...

Dividends                                                                                        ................ Non-operating losses not passed through P and L A/c

What was the cost of supplies cal farm, Cal Farms reported a supplies expen...

Cal Farms reported a supplies expense of $2,000,000 a year. The supplies amount decreased by 200,000 during the year to an ending balance of $400,000. What was the cost of supplies

Application of a hand-held clinical thermometer, In an application of a han...

In an application of a hand-held clinical thermometer for the National Health Service it is required to use disposable temperature sensors and digital read out of temperature betwe

Equity adjustment account, Partner A (50%) Partner B (50%) sharing profi...

Partner A (50%) Partner B (50%) sharing profits equally New partner introduced $13,000 total cash including $3000 as goodwill which is raised to its full value. Partner C

Calculate the minimum annual sales, a factory operates a small canteen but ...

a factory operates a small canteen but its annual operation has consistently shown a loss:

External sources of funds, These sources of funds are resources increased f...

These sources of funds are resources increased from outside the organization to augment funds availability for any of the utilizations to be discussed later. Generally, there are o

Prepare journal enteries to record the requisition slips, Stine Company use...

Stine Company uses a job order cost system. On May 1 st , the company has a balance in Work in Process Inventory of 3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 4

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd