Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Operating cost, 1.Assume that Abel business corporation is purchasing new e...

1.Assume that Abel business corporation is purchasing new equipment, for 350,000$ at the beginning of 2014. Assume that Abel business corporation is in the 30% corporate tax bracke

Period costs, Period Costs Some terms are difficult to define. In one s...

Period Costs Some terms are difficult to define. In one school of thought, period costs are the any costs that are not product costs. But, such a description is a stretch, beca

Differential costing, explain the practical application of differential cos...

explain the practical application of differential costing with the help of suitable example.

Assessment item 2, QUESTION 1 Job costing Create a spreadsheet solution to...

QUESTION 1 Job costing Create a spreadsheet solution to the following problem. Follow the template provided. Play the Job cost podcasts and work through the example problem in tho

What was the cost of supplies cal farm, Cal Farms reported a supplies expen...

Cal Farms reported a supplies expense of $2,000,000 a year. The supplies amount decreased by 200,000 during the year to an ending balance of $400,000. What was the cost of supplies

What is the amount of overhead applied, Morrow Company applies overhead bas...

Morrow Company applies overhead based on direct labor hours. At the beginning of the year, Morrow estimates overhead to be $620,000, machine hours to be 180,000, and direct labor h

.inventory, what are thereasons for holding inventories

what are thereasons for holding inventories

Support department allocation, how do you allocate the support department c...

how do you allocate the support department costs to production departments using the direct method when given percentages

Example of flexible and fixed budget, Example of Flexible and Fixed Budget ...

Example of Flexible and Fixed Budget A company has budgeted to produce and sell 100,000 units of cakes throughout the next period. The selling price per cake is Sh. 20 and var

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd