Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Elements of manufacturing cost, i want some informations about elements of ...

i want some informations about elements of manufacturing cost

Cvp and computer applications, CVP and Computer Applications The broad...

CVP and Computer Applications The broad availability of personal computers encourages more managers to apply cost volume profit analysis. Computers can quickly create the comp

Overheadd anarlysis, Following figures are taken from annual budget of ABC ...

Following figures are taken from annual budget of ABC manufacturers for the year 2013: Fixed factory overhead Rs. 4,000,000 Factory overhead absorption rate Rs. 70 per direct labor

Cost-plus pricing, Computation of mark up and Target selling price in cost-...

Computation of mark up and Target selling price in cost-minus pricin

debt service fund and special revenue fund, For your assignment, discuss w...

For your assignment, discuss when the government and nonprofit organizations would use each of the following funds: Capital projects fund Debt service fund Special r

Determine the cost, Sanderson Company has the following production data for...

Sanderson Company has the following production data for March: no beginning work in process, units started and completed 28,030, and ending work in process 3,890 units that are 100

Tracking direct materials, Tracking Direct Materials Jack keeps full re...

Tracking Direct Materials Jack keeps full records of the material released to each job. When Donnie gathered up light bulbs, tape, breakers, wire, and wire nuts on the morning

Cost accountant and cost analysis, Cost Accountant and Cost Analysis ...

Cost Accountant and Cost Analysis Cost Accountant Is a member of chief accounting officers department? And he is responsible for collecting product costs and preparing ex

Applications of marginal costing, what is the importance and assumptions of...

what is the importance and assumptions of application of marginal costing

Batch costing, Batch Costing This is a kind of job costing that is uti...

Batch Costing This is a kind of job costing that is utilized when production consists of limited repetitive work and definite number of item manufactured in one batch.  A batc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd