Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

What are the variable expenses per unit, Superior Door Company sells pre-hu...

Superior Door Company sells pre-hung doors to home builders. The doors are sold for $60 each. Variable costs are $42 per door and fixed costs total $450,000 per year. The company i

Calculate the fixed costs to the two products, Herrestad Company does produ...

Herrestad Company does produce and sell two products and the details below will be used to prepare a segmented income statement (showing the income for each product and the total)

calculate the percent interest rate and effective cost, 1. The following t...

1. The following three one-year "discount" loans are available toyou: Loan A: $120,000 at a 7 percent discount rate Loan B: $110,000 at a 6 percent discount rate Loan

Ledger accounting system, Q. Is it possible to execute fca in the deficienc...

Q. Is it possible to execute fca in the deficiency of a general ledger accounting system ? Ans. Yes. FCA can be executed for whichever solid waste management system and whi

Labour variances, Labour Variances From our basic data, we can ca...

Labour Variances From our basic data, we can calculate the labour variances as given as: i. Labour Rate Variance = (AH x AR) - (AH  x SR)

Case study, Ask q6) The Net Sales revenue reported is derived from the sale...

Ask q6) The Net Sales revenue reported is derived from the sale of products. Each year Findley records from cash sells, sells on account and completed purchase orders. During 2016

Forecasting future cash flow and implement capital budgeting, It is the yea...

It is the year 2012. The Chief Executive of XYZ Systems Plc, a growing firm in the telecommunication sector, has called your team for an important meeting. "We are expanding": he s

Determine equivalent units of the product, Determine Equivalent Units of th...

Determine Equivalent Units of the Product Let assume there are 4,000 units of a product in ending inventory out of that 60 percent are fully complete whereas the remaining are

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd