Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Price and quality aspect of variance, Price and Quality Aspect of Variance ...

Price and Quality Aspect of Variance At this point it is serious to understand that all variance has two aspects, a price aspect and a quantity aspect: these two aspects combi

Objectives of budgetary planning, Objectives of Budgetary Planning 1...

Objectives of Budgetary Planning 1) Coordination The budgetary process needs that visible detailed budgets are developed to cover every activity, function or department

Ms, Goga Ltd is busy building a five-star hotel in the area, they use the p...

Goga Ltd is busy building a five-star hotel in the area, they use the percentage of completion method to determine profits and would like to calculate the profit for the year. dra

What is the dollar amount of direct material a, Win Corporation sells a sin...

Win Corporation sells a single product. Budgeted sales for the year are anticipated to be 609,725 units, estimated beginning inventory is 107,791 units, and desired ending inventor

Direct materials and direct labor:, McDaniel Company manufactures 100-pound...

McDaniel Company manufactures 100-pound bags of fertilizer that have the following unit standard costs for direct materials and direct labor: Direct Materials (100 lbs. @ $1.00

Calculate the group profit and loss, Using the chosen company from Bursa Ma...

Using the chosen company from Bursa Malaysia, prepare a consolidated accounts assuming that the chosen company acquire Sure Cargo Behard at 80% of its ordinary shares. Given bel

Assignment Choice #2: Accounting for Byproducts (Quantitativ, Pyramid Print...

Pyramid Printing Company is a printer of magazines and retail inserts. In addition, there are two joint products (food wrapping and book covers) and one byproduct (shipping-box ins

Ppe, is ppe taxable

is ppe taxable

Profit analysis and cost volume or cvp analysis, Profit Analysis and Cost V...

Profit Analysis and Cost Volume or CVP Analysis CVP Analysis checks the relationship between profit, activity level and the cost. CVP Analysis assists in a broad range of p

Sgtatement of Cash Flow, “The statement of cash flows is the easiest of the...

“The statement of cash flows is the easiest of the basic financial statements to prepare because you know the answer before you start. You compare the beginning and ending balances

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd