Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Budgeted and actual fixed costs per month , Using  the  information below, ...

Using  the  information below, list profit statements  for June and July using  (a) margin costing and (b) absorption costing. A company produces and sells 1 product only which

Compute over and under absorption of variable overhead, Compute Over and Un...

Compute Over and Under Absorption of Variable and Fixed Overhead A company has a machine cost center for that the given information is available as a) Budget i. Budget

Margin safety ratio, Small Steps sells step stools. Their budget informatio...

Small Steps sells step stools. Their budget information is shown below. selling price: $40 per stool Variable expense:$30 per stool Fixed Expense:$24,000 use the above inform

Standard costing, STANDARD COSTING STANDARD COSTING is a method, which ...

STANDARD COSTING STANDARD COSTING is a method, which uses standards for costs and revenues for the idea of control by variance analysis. It can be used either through operation

Determine the expost returns, Calculate the skewness and kurtosis statistic...

Calculate the skewness and kurtosis statistics for your assignment portfolio. How do these reconcile with the assumptions behind Modern Portfolio Theory? Demonstrate analyticall

Sensitivity analysis, Sensitivity Analysis The only certain thing is th...

Sensitivity Analysis The only certain thing is that nothing is sure thing. Cost structures can be anticipated to vary over the time period. Management should vigilantly analyze

Calculate the weighted cost of capital calculation for firm, Ed Mettway was...

Ed Mettway was concerned about his firm's ability to acquire the necessary property, plant, and equipment to take advantage of steadily increasing sales. Touring Enterprises, estab

Calculate monthly excess returns, In this exercise you will familiarize you...

In this exercise you will familiarize yourself with index models, beta and CAPM estimation. Download the spreadsheet data_question3.xlsx from Sakai and use the data contained there

Audit plan, 1. You are required to download the latest annual report publis...

1. You are required to download the latest annual report published by one of the following institutions: - Adult Multicultural Education Services - Centre for Adult Education

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd