Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

ECONOMIC ORDER QUANTITY, ANNUAL DEMAND = 2400 UNITS ORDERING COST PER UNIT ...

ANNUAL DEMAND = 2400 UNITS ORDERING COST PER UNIT = RS.4.00/- UNIT PRICE = RS 2.40/- STORAGE COST = 2% P.A INTEREST RATE = 10 % P.A LEAD TIME = HALF MONTH CALCULATE ECONOMIC ORDER

Contribution, CONTRIBUTION : It is the variation between the marginal cost ...

CONTRIBUTION : It is the variation between the marginal cost of sales and sales and it contributes towards fixed profit and expenses.  It is differ from the profit which is the net

Exploration costs, are exploration cost treated as an asset or expense or b...

are exploration cost treated as an asset or expense or both?

Equity or debt securities investments, a.         What are the major equity...

a.         What are the major equity and/or debt securities investments? What amounts are reported in the balance sheet? How significant are those amounts to the company's overall

Break even analysis, B REAK EVEN ANALYSIS Break even analysis is a bro...

B REAK EVEN ANALYSIS Break even analysis is a broadly used technique to study cost-volume-profit relationship.  It can be explained as - 'a system for determination of that le

Compute the annual depreciation charges, On January 1, 2012, a machine was ...

On January 1, 2012, a machine was purchased for $197,100. The machine has an estimated salvage value of $13,140 and an estimated useful life of 5 years. The machine can operate for

Absorption costing, how to treat an increase in output on marginal costing

how to treat an increase in output on marginal costing

Standard costing and variance analysis using kaizen costing, Discuss how SD...

Discuss how SD can use standard costing and variance analysis to prepare meaningful reports when using Kaizen Costing. By the use of standard costing and variance analysis, fr

Cost audit, what is cost audit? types of cost audit explain

what is cost audit? types of cost audit explain

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd