Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Calculate the allocations and totals, A company wishes to devise a fair mea...

A company wishes to devise a fair means of allocating funds to its four main departments, namely Accounts, Production, Sales and Transport. The total allocation is to be £100,000.

Find interest and refunde, Gerona Company authorized the sale of $300,000 o...

Gerona Company authorized the sale of $300,000 of 10%, 10-year debentures on January 1, 2008. Interest is payable on January 1 and July 1. The entire issue was sold on April 1, 200

Prepare a direct material purchases budget., 1) The Svelte Jeans Company pr...

1) The Svelte Jeans Company produces two different types of jeans. One is called the "Simple Life" and the other is called the "Fancy Life". The company sales budget estimates that

Determine the current ratio, When firms enter into loan agreements with the...

When firms enter into loan agreements with their bank it is very common for the agreement to have a restriction on the minimum current ratio the firm has to maintain. So, it is imp

Labor transactions, Labor Transactions (i) Wages Paid in cash (ii) ...

Labor Transactions (i) Wages Paid in cash (ii) Wages incurred like a) Direct labor or else b) Indirect labor  In the Financial Books  In

Definitions of manufacturing concepts interstate, 3. Definitions of manufac...

3. Definitions of manufacturing concepts  Interstate Manufacturing produces brass fasteners and incurred the following costs for the year just ended:  Materials and supplies us

What is bep, BEP- Break Event Point: It shows no Loss and no Profit The ...

BEP- Break Event Point: It shows no Loss and no Profit The level of activity at which, total revenues equivalent total costs. A point at which there is no profit and no loss.

Budgeted and actual fixed costs per month , Using  the  information below, ...

Using  the  information below, list profit statements  for June and July using  (a) margin costing and (b) absorption costing. A company produces and sells 1 product only which

Mamufactuaring account, for the year ended31st dec 2008manufacturing accoun...

for the year ended31st dec 2008manufacturing accountshowing costof row material,manufacturing expenses and the cost of goods manufactured& tradind account where stock of row mater

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd