Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Prepare of the final accounts of a business, You are assisting the accounta...

You are assisting the accountant on the preparation of the final accounts of a business with a year-end of 31 December. A trial balance has been drawn up and a suspense account ope

Job order costing, XYZ Company is a family-owned bicycle manufacturing comp...

XYZ Company is a family-owned bicycle manufacturing company located in Stow, Ohio.  Until recently,it had maintained slow but steady growth in producing and marketing its only pr

Determine sales revenue and net income, Students will prepare a Comprehensi...

Students will prepare a Comprehensive Master Budget and Budgeted Financial Statements for Earrings Unlimited for the three-month period ending June 30. This includes: Sales Budg

What is chargeback, A process in the industry where a wholesaler needs an a...

A process in the industry where a wholesaler needs an amount that is the difference among the manufacturer's price to the wholesaler and the contract price to the resale customer.

Job costing, according to a factory cost ledger, job no 51 has incurred the...

according to a factory cost ledger, job no 51 has incurred the following costs: direct material - 30

Overhead variances, OVERHEAD VARIANCES Unlike labour and direct materia...

OVERHEAD VARIANCES Unlike labour and direct material, the manufacturing overhead is not completely variable with the level of production.   So, standard costs for factory overh

Estimating the number of shares with returns less, The file A1Q1 contains d...

The file A1Q1 contains data for the percentage change in the price of 50 shares selected at random from the Australian Stock Exchange. The data refer to the percentage change in th

Determine operating cash flow, What are the missing amounts for the below a...

What are the missing amounts for the below amortization table, given the following information? -  A firm borrows $100,000 from a bank. -  The terms of the loan require the f

Process costing procedure, Process Costing Procedure 1. The production...

Process Costing Procedure 1. The production factory is divided into a number of methods. 2. An account is maintained and opened for every process. 3. Every process accou

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd