Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

First in first out or fifo method - work in progress, First In First Out or...

First In First Out or FIFO Method - Work in Progress This method considers merely those costs incurred throughout the recent period.  Equivalent units are calculated given a

Utility of break even point in managerial decision making, UTILITY OF BREAK...

UTILITY OF BREAK EVEN POINT IN MANAGERIAL DECISION MAKING 1. It assists in determination of sales mix 2. It assists in exploring new markets 3. It assists in deciding abo

Plot janitorial labor cost produced on a scattergraph, The number of workd...

The number of workdays varies from month to month due to the number of weekdays, holidays, days of vacation, and sick leave taken in the month. The number of units produced in a

Prepare a statement of comprehensive income, Good Food Company is a local m...

Good Food Company is a local manufacturer of instant noodles. Established in 2005, their business has been growing steadily. Their products, which are available in 3 flavors, are s

Absorption costing and marginal costing, Absorption Costing and Marginal Co...

Absorption Costing and Marginal Costing Product costs are costs identified along with goods produced or purchased for resale. That costs are initially identified like part of

Calculate the monetary of the inventory, Learning Objective: After completi...

Learning Objective: After completing the project, the student will have gained familiarity, understanding and mastery of programming a realistic but simple application in Assembly

Algebra in cost accounting, I''m about to take my first cost accounting cl...

I''m about to take my first cost accounting class in college, Do i need algebra skills to do well on this class

Shrinkage - production process, Shrinkage - Production Process This re...

Shrinkage - Production Process This refers to a disappearance or loss of material inputs utilized throughout the production process. It happens mainly via the evaporation. Thi

Break even point, Campground Inc. is considering the production and sale of...

Campground Inc. is considering the production and sale of propane lamps. Annual fixed costs associated with the project are expected to total $60,000. In addition, each lamp would

Depreciation (to be computed) by slm method, sabonis consmetics co. purchas...

sabonis consmetics co. purchased machinery on december 31,2011, paying $50,000 down and agreeing to pay the balance in four equal installments of $40,000 payable each dec 31. an as

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd