Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Calculate the re-negotiate the part-time trainers cost, a.    If you could ...

a.    If you could pick a single source of cash for your business, what would it be? Why? b.    How can a business earn large profits but have a small balance in Retained Earnin

Calculate the net effective yield, A Government issued a number of index-li...

A Government issued a number of index-linked bonds on 1 June 2000 which were redeemed on 1 June 2002.  Each bond had a nominal coupon rate of 3% per annum, payable half yearly in a

Controllable and non controllable costs, Controllable and Non Controllable ...

Controllable and Non Controllable Costs Controllable costs can be influenced on the level of authority at that they are being analyzed when non-controllable costs cannot.

Cost, what is traditional costing system

what is traditional costing system

Prepare the capital accounts, Shirley and Ken are in partnership, trading i...

Shirley and Ken are in partnership, trading in the construction industry. The year end for the partnership business is 30 June. You are the Assistant Accountant and have been as

Calculate the atm fee should the bank charge - marginal cost, A bank in a m...

A bank in a medium-sized midwestern city, Firm X, currently charges $1 per transaction at its ATMs.  To determine whether to raise price, the bank managers experimented with a n

Relevant costs and decision-making, Relevant Costs and Decision-Making ...

Relevant Costs and Decision-Making The relevance of costs will depend upon the purpose for that they are being utilized. Relevance is related to future decisions. The relevanc

Flexible budget, Flexible Budget Flexible budget is a budget that is d...

Flexible Budget Flexible budget is a budget that is designed to change in accordance along with the level of activity attained. It includes budgeting at various levels in anti

Prepare an income statement for the current year, The assets and liabilitie...

The assets and liabilities of Amos Moving Services at May 31, 2011, the end of the current year, and its revenue and expenses for the year are listed below.  On April 1, 2010, the

Current overhead cost allocation system, Sam Edwards has been the accountin...

Sam Edwards has been the accounting manager for Jade Manufacturing in a highly competitive international market for ten years. Jade Manufacturing produces heavy equipment for two m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd