Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Fixed overhead variance (fov), F ixed Overhead Variance (FOV) Fixed...

F ixed Overhead Variance (FOV) Fixed overhead variance has been described by ICMA, London, as 'the variation between the standard cost of fixed overhead absorbed in the pro

Cash Budgeting, Stopover industries ltd, a recently incorporated company pl...

Stopover industries ltd, a recently incorporated company plans to go into production next year. the following standard cost matrix has been assembled for one of the products it pro

EXPECTED CASH COLLECTIONS.PRACTICE QUESTIONS, WORKED EXAMPLES OF EXPECTED C...

WORKED EXAMPLES OF EXPECTED CASH COLLECTIONS PATTERNS

Modified accelerated cost recovery system, Assume new instruments for a fir...

Assume new instruments for a firm cost $18,000 with an additional installation fee of $2,000, both of which are depreciable. Finish the depreciation schedule shown below using the

What are the variable expenses per unit, Superior Door Company sells pre-hu...

Superior Door Company sells pre-hung doors to home builders. The doors are sold for $60 each. Variable costs are $42 per door and fixed costs total $450,000 per year. The company i

Compute overhead rate per hour, Reamer Company uses a predetermined overhea...

Reamer Company uses a predetermined overhead rate based on machine-hours to apply manufacturing overhead to jobs. The company has provided the following estimated costs for next ye

Give annual report project, Give Annual report project: You will pick ...

Give Annual report project: You will pick a publically trade company to do the analysis on with approval of the professor . the following is an outline of what should be in th

Which of the four types of costs would include ceo''s salary, Which of the ...

Which of the four types of costs would include a CEO's salary? A. Unit-Level B. Batch-Level C. Product Sustaining D. Facility Sustaining

Just in time, advantages and disadvantages of just in time

advantages and disadvantages of just in time

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd