Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Purposes of overhead cost analysis, Purposes of Overhead Cost Analysis ...

Purposes of Overhead Cost Analysis There are a number of situations whether the analysis of overhead costs will assist in the satisfactory evaluation of the relevant cost data

Assumptions of cvp, Assumptions of CVP This chapter has given informati...

Assumptions of CVP This chapter has given information on how to apply CVP for the business analysis. Most of this analysis is keyed to the model of how profitability is impacte

Show the break-even charts, Q. Show the Break-even charts? Refers graph...

Q. Show the Break-even charts? Refers graphically profit and losses at different levels of sales volume achieved. When sales revenue is greater than total cost it m

Calculate the cash value financing interest rate , Calculate the today's ca...

Calculate the today's cash value of a car that can be leased with $5000 down, bi-weekly payments of $199 over 4 years and a buy-back value of $15,000 at the end of the lease if the

Cost Classification, What are the importance of cost classification

What are the importance of cost classification

Total landed cost, How many pounds of guava puree are required? a. In a ...

How many pounds of guava puree are required? a. In a month? b. How many in a year? In computing the Total Landed cost for mango concentrate, we are interested in the incre

Determine a cost system that uses estimated overhead costs, 1) Presented be...

1) Presented below is a list of terms, followed by definitions or descriptions of those terms. a. Cost pool b. Actual cost system c. Cost driver d. Manufacturing diver

Throughput Accounting, Image Is Everything, Inc. (IIE) is located in an eme...

Image Is Everything, Inc. (IIE) is located in an emerging market. It specializes in lithographic duplication, catering to demands from the nouveau riche for reproductions of paint

What was the cost of raw materials, Raw Materials: Manufacturing Overhead B...

Raw Materials: Manufacturing Overhead Bal 1/1: 36,000 Credits: ? Debits: 383,000 Credits: ? Debits: 470,000 Bal: 12/3: 156,000 Work in Process: Bal 1/1: 73,000 Credits: 770,000

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd