Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

What is the cost of goods manufactured, information for the year ended Dece...

information for the year ended December 31, 2010: Direct labor $16,840 Direct material used 16,300 General and administrative expenses 14,240 Indirect production costs 16,780 Selli

Features of jit, What are the major features of JIT?

What are the major features of JIT?

Calculate direct labour hour, Manson Manufacturing applies manufacturing ov...

Manson Manufacturing applies manufacturing overhead at a rate of $30 per direct labour hour a)when during the year was this rate computed b)Describe briefly how this rate was

Process costing, what is accounting treatment for material losses due to ab...

what is accounting treatment for material losses due to abnormal reasons

Determine the cost of the finished goods inventory, Manufacturing statemen...

Manufacturing statements and cost behavior  Tampa Foundry began operations during the current year, manufacturing various products for industrial use. One such product is light-g

Profit an economic profit, Johnson Farms owns valuable farm land that permi...

Johnson Farms owns valuable farm land that permits it to make wheat at a lower cost than its competitors. The company reports large profits every year on its accounting statements.

Determine firms short run cost curve, Q. A firm uses capital and labor to p...

Q. A firm uses capital and labor to produce a single output good. The production function is given by F(K, L) = K 2 L where K is the amount of capital and L is the amount of labo

Calculate the inventory turnover ratio, The following information is availa...

The following information is available for the automotive division of Ford Motor Company for 2009.  The company uses the LIFO inventory method.

Overapplied or underapplied overhead: manufacturer, Budgeted direct labour ...

Budgeted direct labour cost 75000 hours @ $16 per hour Budgeted manufacturing overhead 80 000 hours @ $17.50 per hour Actual direct labour cost $997 500 Budgeted manufa

Allocation of scarce resourses, LaNora White received her accounting degree...

LaNora White received her accounting degree in 1992. Since graduating, she has obtained significant experience in a variety of job settings. Her skills include auditing, income and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd