Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Issues to consider when making decisions, Q. Issues to consider when making...

Q. Issues to consider when making decisions? At activity level A it can be seen from diagram that sales revenue line intersects the total cost line specifying that this is the

Definition of budget, DEFINITION OF BUDGET As per the Institute of Cos...

DEFINITION OF BUDGET As per the Institute of Cost & Management (ICMA), London, a BUDGET is 'a quantitative statement and / or financial, prepared and approved prior to a defin

What are the dimensions of the box with the minimum cost, A manufacturing c...

A manufacturing company wants to package its product in a rectangular box with a square base and a volume of 32 cubic inches. The cost of the material used for the top is $.05 squa

Controllable and non controllable costs, Controllable and Non Controllable ...

Controllable and Non Controllable Costs Controllable costs can be influenced on the level of authority at that they are being analyzed when non-controllable costs cannot.

Calculate the range of monthly financing rates, Calculate the range of mont...

Calculate the range of monthly financing rates for which the schedule of monthly cash flows is profitable: Month Cash Flow, $ -------------------- 0 -10,100 1 +23,000 2 -13,

Costs and revenues over a range of activity levels, 1. Single product or si...

1. Single product or single mix of products 2. Variable cost, fixed cost and selling price are constant 3. The level of production will equal the level of sales Example:

Angle of incidence, ANGLE OF INCIDENCE:   It is an angle that is created wh...

ANGLE OF INCIDENCE:   It is an angle that is created when the entire sales line intercepts the entire cost line from below in the breakeven chart. It is inferred that higher the an

Determine the expost returns, Calculate the skewness and kurtosis statistic...

Calculate the skewness and kurtosis statistics for your assignment portfolio. How do these reconcile with the assumptions behind Modern Portfolio Theory? Demonstrate analyticall

Marginal costing, MARGINAL COSTING As per the Chartered Institute of Ma...

MARGINAL COSTING As per the Chartered Institute of Management Accountants, London, the phrase 'Marginal cost' means - 'the amount at every given volume of output through which

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd