Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Compute over and under absorption of variable overhead, Compute Over and Un...

Compute Over and Under Absorption of Variable and Fixed Overhead A company has a machine cost center for that the given information is available as a) Budget i. Budget

Calculate the price of regular bonds, XYZ Inc. plans to raise $5,000,000 ex...

XYZ Inc. plans to raise $5,000,000 external financing through issuing bonds, and is considering two options: regular bonds and zero couple bonds.  The regular bonds will have coupo

Budgets, how can a poorly controlled budget cause problesm for a business?

how can a poorly controlled budget cause problesm for a business?

Classification, what is the classification of cost & how it is done?

what is the classification of cost & how it is done?

Determine difference between results using marginal costing, Determine Diff...

Determine Difference between Results Using Marginal Costing and Absorption Costing The overhead absorption rate for product X is Ksh.10 per machine hour. All unit of product X

Use account analysis to determine fixed cost, Reef Office Supplies is inter...

Reef Office Supplies is interested in estimating the cost involved in hiring new employees. The following information is available regarding the costs of operating the Human Resour

Variable overhead expenditure variance, Variable Overhead Expenditure Varia...

Variable Overhead Expenditure Variance Budget for December 2003; Shs. Fixed Overheads 11,480 Variable Ov

#title., how does idle capacity effect cost behavior patterns and factory o...

how does idle capacity effect cost behavior patterns and factory overhead application methods

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd