Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Cost accounting, raw an organization chart of any actual or hypothetical ma...

raw an organization chart of any actual or hypothetical manufacturing organization to show the position of management/cost accounting department within an organization and discuss

Absorption Costing Techniques, If the net income under marginal costing is ...

If the net income under marginal costing is #100,000, calculate absorption costing, if opening and closing inventories are #20,000 and #15,000

Determine a cost system that uses estimated overhead costs, 1) Presented be...

1) Presented below is a list of terms, followed by definitions or descriptions of those terms. a. Cost pool b. Actual cost system c. Cost driver d. Manufacturing diver

Limitations of standard costing, L I M I T A T I O NS OF STANDARD ...

L I M I T A T I O NS OF STANDARD COSTING 1.     It may be very difficult to fix standards for all operations. 2.     Incorrect standards may result in wastage of mo

Determine firms short run cost curve, Q. A firm uses capital and labor to p...

Q. A firm uses capital and labor to produce a single output good. The production function is given by F(K, L) = K 2 L where K is the amount of capital and L is the amount of labo

Budgeting, traditional budgeting systems are incremental in nature and tend...

traditional budgeting systems are incremental in nature and tend to focus on cost centres..explain the weakness of the incremental budgeting system and explain ways of adressing th

Advantages and disadvantages of group bonus plan, Advantages and Disadvanta...

Advantages and Disadvantages of Group Bonus Plan Benefits associated along with group bonus schemes involve i. It encourages teamwork and cooperation among workers ii.

Calculate development cost, Candler Inc a computer software development fir...

Candler Inc a computer software development firm has stock outstanding as follows: 40,000 shares of $2 nonparticipating, noncumulative preferred stock of $10 par, and 250,000 share

Prepare a direct material purchases budget., 1) The Svelte Jeans Company pr...

1) The Svelte Jeans Company produces two different types of jeans. One is called the "Simple Life" and the other is called the "Fancy Life". The company sales budget estimates that

Materials purchased, The Clash Company uses Normal Job-Order Costing in its...

The Clash Company uses Normal Job-Order Costing in its individual production department.  Overhead is applied to jobs by a predetermined rate, which is depend on machine hours.  Th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd