Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Master budget framework, Master Budget Framework The master budget is ...

Master Budget Framework The master budget is the overall quantifications of the budgeting plan. In this, functional budgets are not corporate. A functional budget is a budget

Overhead anaylsis sheet, how do we prepare an overhead analysis sheet when ...

how do we prepare an overhead analysis sheet when the data given is already apportioned

Determine firms short run cost curve, Q. A firm uses capital and labor to p...

Q. A firm uses capital and labor to produce a single output good. The production function is given by F(K, L) = K 2 L where K is the amount of capital and L is the amount of labo

Business process re-engineering help to improve the profits, MLC, which was...

MLC, which was established in year 1998, manufactures a range of garden sheds and summerhouses using timber purchased from a various suppliers.The recently appointed managing direc

Advantages and disadvantages of designing an ic, Discuss the advantages and...

Discuss the advantages and disadvantages of designing an IC using VHDL and synthesis compared with the traditional design approach using schematic capture, simulation and layout.

Service cost centres, Service Cost Centres Since no production cost un...

Service Cost Centres Since no production cost units pass via the service cost centers, it is essential to apportion the service department costs; to the production cost center

Compute the cost per unit, Fosson Furniture uses a process cost system to a...

Fosson Furniture uses a process cost system to account for its chair factory. Beginning inventory consisted of 5,000 units (100% complete as to material, 55% complete as to labor)

Assumptions of break-even analysis, Assumptions of Break-Even Analysis ...

Assumptions of Break-Even Analysis 1. The break-even chart is fundamentally a static analysis; commonly changes can merely be displayed by drawing a new chart or a series of c

Capital initial investment, Now along with the illustration of Ramsons at h...

Now along with the illustration of Ramsons at hand, this is not tough for us to understand that Ramsons have invested the 'money to make money'. Where has Ramsons invested the mone

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd