Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Financial accounting, Financial Accounting It is the analysis, and rec...

Financial Accounting It is the analysis, and recording and classification of financial transactions and the ascertainment of how that information will be reported to the diffe

Variable costs, Variable Costs Are costs such raise or fall proportio...

Variable Costs Are costs such raise or fall proportionately along with the level of activity that is such portion of the cost of an activity which changes along with the leve

Prepare a master budget, Pecos Canyon Winery is a small vineyard/winery loc...

Pecos Canyon Winery is a small vineyard/winery located in the Big Bend area of West Texas. The initial cabernet grape vines were planted in the spring of 2004 with the first wine p

Types of overhead absorption rate, Types of Overhead Absorption Rate ...

Types of Overhead Absorption Rate NB: Overheads incurred are generally absorbed on the basis of budgeted or estimated figures. The given basis may be applied leading to the

Attainable standards and current standards, Attainable Standards and Curren...

Attainable Standards and Current Standards Although the standard must be set high sufficient that achievable and it has to be worked for. Attainable standards must provide a c

Determine which project is more lucrative - investment , The Zooline Compan...

The Zooline Company (Pty) Ltd is an American based company that focuses on the LSM 8 -10 markets. They do vehicle interiors, raise or lower suspensions and install top end sound sy

Ms, Goga Ltd is busy building a five-star hotel in the area, they use the p...

Goga Ltd is busy building a five-star hotel in the area, they use the percentage of completion method to determine profits and would like to calculate the profit for the year. dra

Draw the demand curve of marginal benefit, The total demand (marginal benef...

The total demand (marginal benefit) curve for visiting Yosemite is as follows: Price = 5000-10*NumberOfTrips -10*TonsOfVisibleTrash. a. Suppose the quantity of trash=100 tons. D

Cost unit, explain various type of cost ccounting

explain various type of cost ccounting

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd