Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Marginal costing and marginal cost, Marginal Costing and Marginal Cost ...

Marginal Costing and Marginal Cost Marginal Costing is an optionally method of costing to absorption costing , In marginal costing, merely variable costs are charged like a

Calculate the equivalent annual cost, A plant is considering the replacemen...

A plant is considering the replacement of a piece of equipment in its materials handling system with a new piece. If the company's cost of capital is 10%. Should the present asset

Calculate manufacturing overhead for the year, Baka Corporation applies man...

Baka Corporation applies manufacturing overhead on the basis of direct labor-hours. At the beginning of the most recent year, the company based its predetermined overhead rate on t

Considerations in variance investigation, Considerations in Variance Invest...

Considerations in Variance Investigation As already notice above, not all variances are investigated; this is only the material and meaningful as for cost control reasons vari

Insurance of trust property-trust laws, INSURANCE Trustees may insure t...

INSURANCE Trustees may insure trust property against loss or damage by fire subject to the following conditions:   1. The insurance must not exceed the full value of the proper

Find the fixed cost, A firm's fixed costs for 0 units of output and its ave...

A firm's fixed costs for 0 units of output and its average total cost of producing different output levels are summarized in the table below. Complete the table to find the fixed c

Cvp analysis in situations subject to change, CVP Analysis in Situations Su...

CVP Analysis in Situations Subject To Change Revenue and Cost will change and also sales volume because of a number of factors involving: a) Increased competition may need

Determine marginal and average cost curves take a u shape, 1) A) In a compe...

1) A) In a competitive market place (pure competition) is it possible to continually sell your product at a price above the average cost of production?  Why or why not? B) Why d

Calculate the weighted average cost of capital, A company is investigating ...

A company is investigating the effect on its cost of capital with respect to the tax rate. Suppose there is a capital structure of 20% debt, 10% preferred stock, and 70% common sto

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd