Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Will by means of fca save money, Q. WILL BY MEANS OF FCA SAVE MONEY? A...

Q. WILL BY MEANS OF FCA SAVE MONEY? Ans. It depends. in the end, the more departments know about what it obtain to deliver a unit of service, the more efficiently they can

Insurance of trust property-trust laws, INSURANCE Trustees may insure t...

INSURANCE Trustees may insure trust property against loss or damage by fire subject to the following conditions:   1. The insurance must not exceed the full value of the proper

Income received in advance, This is the income received but not earned thro...

This is the income received but not earned throughout the accounting period. Conversely, this is the income for those services are to be rendered in future. Such income is deducted

cost classification, Explain the value attached to this common exercise un...

Explain the value attached to this common exercise undertaken by Accountants.

Physical measure and net realizable value, Physical Measure and Net Realiza...

Physical Measure and Net Realizable Value Physical Measure/Unit Joint costs are assigned to the joint products according to the ratio of physical measurement of the outpu

Difference between expenses and expenditure, The difference among expenses ...

The difference among expenses and expenditure. Expense is the outflow from a profit oriented organization whereas expenditure is the outflow from non-profit organization.

Just in time, advantages and disadvantages of just in time

advantages and disadvantages of just in time

Close-end matching grants, RC School District has a large number of student...

RC School District has a large number of students in need of remedial instruction.  The superintendent of RC School System can allocated her budget between purchasing X units of re

Types of variances, TYPES OF VARIANCES Variances are computed for the e...

TYPES OF VARIANCES Variances are computed for the entire three basic elements of cost - direct labour, direct material, and overhead variance 1. Direct labour variance 2.

Algebra in cost accounting, I''m about to take my first cost accounting cl...

I''m about to take my first cost accounting class in college, Do i need algebra skills to do well on this class

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd