Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Integrated ledger system, Integrated Ledger System An integrated accou...

Integrated Ledger System An integrated account ledger system, which has a number of features that may be viewed as preferable to the interlocking ledger system. In present dec

Application of a hand-held clinical thermometer, In an application of a han...

In an application of a hand-held clinical thermometer for the National Health Service it is required to use disposable temperature sensors and digital read out of temperature betwe

Compute variances for variable costs and fixed costs, The Houston Chamber O...

The Houston Chamber Orchestra presents a series of concerts throughout the year. Budgeted fixed costs total $300,000 for the concert season; variable costs are expected to average

Determine the allocation of dividends, Sleep Corporation was organized on J...

Sleep Corporation was organized on January 1, 2011. During its first year, the corporation issued 40,000 shares of $5 par value preferred stock and 400,000 shares of $1 par value c

Determine marginal and average cost curves take a u shape, 1) A) In a compe...

1) A) In a competitive market place (pure competition) is it possible to continually sell your product at a price above the average cost of production?  Why or why not? B) Why d

WACC, formula for calculting WACC

formula for calculting WACC

Irr, The following data pertains to an investment proposal: Required invest...

The following data pertains to an investment proposal: Required investment $400,000 Annual cost savings $105,700 Projected life of investment 6 years Projected salvage value $0 Req

Allocation of joint costs, Allocation of Joint Costs Whereas two or mo...

Allocation of Joint Costs Whereas two or more products of relatively high value emerge simultaneously from a single process, they are named as joint products.  The processes s

Tracking direct materials, Tracking Direct Materials Jack keeps full re...

Tracking Direct Materials Jack keeps full records of the material released to each job. When Donnie gathered up light bulbs, tape, breakers, wire, and wire nuts on the morning

Determine cost, . Alice Company has received a special order from Jo...

. Alice Company has received a special order from John. John wishes to buy 100 units of Alice's product at a price of $48. The regular price is $65. The unit cost informati

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd