Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

The overhead cost variances , The following facts have been extracted fr...

The following facts have been extracted from the standard cost card for product X:

Standards in standard costing, Standards in Standard Costing 1) The ty...

Standards in Standard Costing 1) The type of standard utilized basic, attainable, ideal, current directly affects the level of the variances that can arise, and the meaning th

Gross rental revenue, Operating Income 1. Operating Income is derived f...

Operating Income 1. Operating Income is derived from two sources, Rental Income from businesses operating in the warehouse complex and Interest Income of the project operating

What is bep, BEP- Break Event Point: It shows no Loss and no Profit The ...

BEP- Break Event Point: It shows no Loss and no Profit The level of activity at which, total revenues equivalent total costs. A point at which there is no profit and no loss.

Distinction between absorption and marginal costing, Distinction between Ab...

Distinction between Absorption and Marginal Costing These are two approaches of arriving at the cost of production or total profit for a specified period. The major difference

Why does rent control result in a shortage of rental unit, 1. Why does rent...

1. Why does rent control result in a shortage of rental units. 2. How does price elasticity of demand affect how much of a tax is passed on to the consumer and how much is absor

Estimate the selling price and profit, Slash and Burn is a monopolist that ...

Slash and Burn is a monopolist that can sell its output at these prices and with these total costs:                    Output             Price        Total Cost

Engineering method of cost estimation, Engineering Method of Cost Estimatio...

Engineering Method of Cost Estimation This method is based on a detailed study of each operation whereas careful requirement is made for materials, labour and equipment essent

What is the division''s margin, Eckels Wares is a division of a major corpo...

Eckels Wares is a division of a major corporation. The following data are for the latest year of operations: Sales

Variable overhead variance (vohv), Variable Overhead Variance (VOHV) VO...

Variable Overhead Variance (VOHV) VOHV is defined by ICMA, London, as 'the variation between the standard variable production overhead absorbed in the production achieved, whet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd