Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Marginal costing and break evan point analysis, what is marginal costing an...

what is marginal costing and explain concept of marginal costing

Debt-equity ratio, Allie forms Broadbill Corporation by transferring land (...

Allie forms Broadbill Corporation by transferring land (basis of $125,000, fair market value of $775,000), which is subject to a mortgage of $375,000. One month prior to incorporat

Computation of overhead recovery rate, Compute the rate to be used in each ...

Compute the rate to be used in each department for applying overhead in both departments Budegeted Cost sheet   Amount in $

Idea behind activity-based costing, Idea behind Activity-Based Costing ...

Idea behind Activity-Based Costing The most important ideas behind activity-based costing are as given as: Activities cause costs; activities involve ordering, ma

Determine the incremental cost, Determine the Incremental Cost A compa...

Determine the Incremental Cost A company currently makes a component that has the given unit cost structure Direct Material Shs. 100

Compute the second years tax amortization, Smith Corporation purchased an i...

Smith Corporation purchased an intangible asset for $110,000. Compute the second year's tax amortization. The second year would be a full year's amortization. The company estimates

Difference between cost accounting and financial accounting, The difference...

The difference among "cost accounting" and "financial accounting are terms demote to the accounting techniques used internally by a company's management to explain the costs of run

Business and the generation of accounting standards, This time of year we a...

This time of year we all here about football. For me it is the bad news of how poorly the Buffalo Bills are performing. Hopefully your favorite team is doing well. One thing we

Stores layout and location - material handling, Stores layout and location ...

Stores layout and location - Material Handling The layout of stores must ensure as a) For movement of material, ease of access out and in of stores b) The issue of peris

Calculate the monetary of the inventory, Learning Objective: After completi...

Learning Objective: After completing the project, the student will have gained familiarity, understanding and mastery of programming a realistic but simple application in Assembly

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd