Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Issuance of stock - shares of common stock, 1. Issuance of stock Prepa...

1. Issuance of stock Prepare journal entries to record the issuance of 100,000 shares of common stock at $20 per share for each of the following independent cases: a. Jacks

What kinds of benefits have communities realized due to fca, Q. What kinds ...

Q. What kinds of benefits have communities realized due to FCA? Communities have understood the following benefits by using FCA: • Rates or tipping fees are set right and fa

Accrued liabilities, Accrued liabilities show expenses or obligations incur...

Accrued liabilities show expenses or obligations incurred in the earlier accounting period but the payment for similar will be made in the subsequent period. In several cases where

What is the dollar amount of direct material a, Win Corporation sells a sin...

Win Corporation sells a single product. Budgeted sales for the year are anticipated to be 609,725 units, estimated beginning inventory is 107,791 units, and desired ending inventor

Determine expected net income and net cash flow, Elite Company is planning ...

Elite Company is planning to add a new product to its line. To manufacture this product, the company needs to buy a new machine at a $300,000 cost with an expected four-year life a

Materials mix variance, M aterials mix variance :  It can be described a...

M aterials mix variance :  It can be described as that portion of direct material usage variance which is the variation between the actual quantities of ingredients used in a mi

CVP Break even analysis, Bottoms Up company produces high quality sports eq...

Bottoms Up company produces high quality sports equipment. the companie''s racket division manufactures three tennis rackets- the Standard, Deluxe and the Pro that are widely used

Objectives of cost accounting, OBJECTIVES OF COST ACCOUNTING 1)To help ...

OBJECTIVES OF COST ACCOUNTING 1)To help in the development of long range plans by provided that cost data that acts as a origin for projecting data for planning. 2)To make s

Prepare the consolidated balance sheet, H Bhd has a 75% holding in the ordi...

H Bhd has a 75% holding in the ordinary shares of S Sdn Bhd and 40% in A Sdn Bhd. Shares in S were acquired  in 2006 when its retained earnings were RM120 million.  The shares in A

Calculate the nominal interest rate, A 1- year Canadian bond with a face va...

A 1- year Canadian bond with a face value of 5000 can be purchased at 4800. a) Calculate the nominal interest rate in Canada. b) If the Canadian dollar is expected to depreci

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd