Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Job-order costing, Division B uses  normal  costing in its job-order costin...

Division B uses  normal  costing in its job-order costing system, with manufacturing overhead  applied  based on direct labour hours.  You have obtained the following information a

Prepare cost sheet, The Pacific Manufacturing Company operates a job-order ...

The Pacific Manufacturing Company operates a job-order costing system and applies overhead cost to jobs on the basis of direct labor cost. Its predetermined overhead rate was based

Calculate the total revenue, Mandy Building Contractors Ltd signed a fixed-...

Mandy Building Contractors Ltd signed a fixed-price contract to build a bridge for Nelly Ltd for $110 million on 1 July 2012.  Contract costs are estimated as follows:

Find the total landed cost, What conclusion can you draw when comparing the...

What conclusion can you draw when comparing the total landed or delivered cost to the original purchase cost? What does this suggest about the importance of supply chain managem

Process cost report, Process Cost Report This is a commonly employed s...

Process Cost Report This is a commonly employed statement that traces the flow of units produced and costs incurred in the production process. The report is prepared for every

Bases of cost classification, Bases of Cost Classification These vario...

Bases of Cost Classification These various bases of cost classification are summarized in the diagram underneath as: Here, we will usually refer to either of these ter

Decision making cycle, Decision Making Cycle Steps in decision-making ...

Decision Making Cycle Steps in decision-making cycle are as: a) Clearly define the objective that is to be the focus of the decision. This is significant in order that the

WACC, formula for calculting WACC

formula for calculting WACC

Standard costing and variance analysis using kaizen costing, Discuss how SD...

Discuss how SD can use standard costing and variance analysis to prepare meaningful reports when using Kaizen Costing. By the use of standard costing and variance analysis, fr

Cash flow budget, the total (ie. aggregated) cashflows in respect to operat...

the total (ie. aggregated) cashflows in respect to operations, with details of annual cash inflows & annual outflows in respect to operations, the total (ie. aggregated) cashflo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd