Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Construct p&l statement , You are considering starting a walk-in-clinic.  ...

You are considering starting a walk-in-clinic.  Your financial projections for the first year of operations are as follows: Revenues (10,000 visits) $400

Compute the indirect production costs, The manufacturing division of an ele...

The manufacturing division of an electronics company uses activity-based costing. The company has identified three activities and the related cost drivers for indirect production c

Giardia, Place a prepared slide of Giardia first under tlie low power and t...

Place a prepared slide of Giardia first under tlie low power and then under the high power of the microscope and observe tlie followilig characters. i) Bilaterally symmetrical

Job costing, Job Costing This is a costing method that is applied whe...

Job Costing This is a costing method that is applied when a job or cost unit is relatively of small size, is undertaken to fit the customer's specifications and is of compara

Presentation & Essay, Why are the main contribution teams can make to an or...

Why are the main contribution teams can make to an organisation? What are the conditions necessary in organisations if people are to work effectively in teams? * Describe what tea

Determine the current profits, Two firms compete in a homogenous product ma...

Two firms compete in a homogenous product market where the inverse demand function is P = 10 - 2Q (quantity is measured in millions). Firm 1 has been in business for 1 year, while

Compute the industry volume variance for each product, The next year's budg...

The next year's budget for Benny, Inc., is given below: Product 1 & 2 Sales $945,000 & 688500 Variable costs 459,900 & 297,000 Fixed costs 300

Standard costing, STANDARD COSTING STANDARD COSTING is a method, which ...

STANDARD COSTING STANDARD COSTING is a method, which uses standards for costs and revenues for the idea of control by variance analysis. It can be used either through operation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd