Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Sales revenue variance (srv), SALES REVENUE VARIANCE (SRV) The word 'Sa...

SALES REVENUE VARIANCE (SRV) The word 'Sales Variance' is indicated by the expression 'operating profit variance due to sales' by ICMA.  It is described as 'the difference betw

Estimate the required rate of return, a)     Company X is expected to maint...

a)     Company X is expected to maintain a constant 7% growth rate in their dividends, indefinitely. If the company has a dividend yield of 4%, what is the required return on their

Davids net state lottery gains, One month before she died on April 14, 2002...

One month before she died on April 14, 2002, Barbara Gent (Amy's aunt) gave Amy a coin collection. Based on careful records that Barbara kept, the collection had a cost basis of $9

Calculate manufacturing overhead for the year, Baka Corporation applies man...

Baka Corporation applies manufacturing overhead on the basis of direct labor-hours. At the beginning of the most recent year, the company based its predetermined overhead rate on t

Equity adjustment account, Partner A (50%) Partner B (50%) sharing profi...

Partner A (50%) Partner B (50%) sharing profits equally New partner introduced $13,000 total cash including $3000 as goodwill which is raised to its full value. Partner C

Prepare the bank reconciliation statement, As the Junior Bank Clerk of a bu...

As the Junior Bank Clerk of a business, one of your monthly tasks is to prepare the bank reconciliation statement. At the month ending 31 January 2012, the bank statement has be

Accounting records - nature and purpose of cost accounting, Accounting Reco...

Accounting Records - Nature and Purpose of Cost Accounting The quantitative information employed in the management and cost accounting systems can be obtained from with two ac

Cost drivers and predictors, why is determining the cost to manufacture a p...

why is determining the cost to manufacture a product quite a different activity from determining how to control such cost?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd