Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Determine the current share price - shareholder, Most corporations pay quar...

Most corporations pay quarterly dividends on their common stock rather than annual dividends. Barring any unusual circumstances during the year, the board raises, lowers, or mainta

Elements of cost, Elements of Cost Nearly there are three elements of c...

Elements of Cost Nearly there are three elements of cost - labor, material, and expenses. These are additional divided into indirect and direct material, indirect and direct la

Select the correct answer, If fixed costs are $743,122 and variable costs a...

If fixed costs are $743,122 and variable costs are 69% of sales, what is the break-even point in sales dollars? Select the correct answer. A. $512,754 B. $2,397,168 C. $1,255,876 D

Calculate the allocations and totals, A company wishes to devise a fair mea...

A company wishes to devise a fair means of allocating funds to its four main departments, namely Accounts, Production, Sales and Transport. The total allocation is to be £100,000.

Accounting for job order costing - direct materials, Accounting for Job Ord...

Accounting for Job Order Costing - Direct Materials Direct materials (i) Dr Stores ledger control Account Cr Cash Account - for cash purchasers              X (ii) D

Changes in variable cost and selling price per unit, Changes in Variable Co...

Changes in Variable Cost and Selling Price per Unit The contribution sales ratio is affected by any change in variable cost or selling price per unit. This ratio is a mea

Compute break even assuming direct materials cost, Below find production an...

Below find production and sales information for Herrestad Company. We will use this same company for all the SLPs in this course.  Product information

Calculate cost of direct manufacturing labour, Dixon Corporation was establ...

Dixon Corporation was established on January 1, Year 1.  The firm has 2 divisions, Division A and Division B.  Division A manufactures standard carpets, and Division B manufactures

Compute the total amount of current assets, Balance Sheet Classi?cations an...

Balance Sheet Classi?cations and Relationships: Shelley and Co. has the following balance sheet elements as of December 31, 2012. Land. . . . . . . . . . . . . . . . . . . . . .

measure the idle time variance, PH plc operates a modern factory that chan...

PH plc operates a modern factory that changes chemicals into fertilizer. Due to the the demand for  its product  is  seasonal,  the  company expects  that  there will be an average

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd