Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Decision analysis , can you guys do a project which is due in 2 weeks

can you guys do a project which is due in 2 weeks

Labour cost, labour cost related case study with solution

labour cost related case study with solution

Interest rates and adjust rates, The Federal Reserve adjusts short term int...

The Federal Reserve adjusts short term interest rates based upon their perceptions of the needs in the economy.  Please describe the ways the Federal Reserve can influence interest

Prepare journal enteries to record the requisition slips, Stine Company use...

Stine Company uses a job order cost system. On May 1 st , the company has a balance in Work in Process Inventory of 3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 4

ECONOMICS, #ques Case Study Electron Control, Inc., sells volt...

#ques Case Study Electron Control, Inc., sells voltage regulators to other manufacturers, who then customize and distribute the products to quality assurance labs for

What is the amount of cost of goods manufactured, Wayne Company's beginning...

Wayne Company's beginning and ending inventories for the month of June were as follows: June 1 June 30 Work in progress $145,000 171,000 Finished Goods 85,000 78,000 Production

Exploration costs, are eploration costs of a mining industry regarded as an...

are eploration costs of a mining industry regarded as an asset or expense or both?

Process costing, Process Costing It is a costing method, which is appl...

Process Costing It is a costing method, which is applied wherever there are standard operations along with continuous production of homogeneous as identical units. Consequentl

Total variable overheads variances, Total Variable Overheads Variances ...

Total Variable Overheads Variances  If Variable Overhead Expenditure Variance =  Shs.1, 330 Variable Overhead Efficiency Variance = Shs.320 Then total variable overheads

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd