Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Calculate the total direct labor cost & labor wage rate, Peter Coffin and P...

Peter Coffin and Paul Bearer own The Grave Undertaking, Inc. and their firm uses a predetermined overhead rate to apply overhead to the production of custom-built coffins.  They us

Evaluate the discounted mean term, Evaluate the discounted mean term (DMT) ...

Evaluate the discounted mean term (DMT) of a bond redeemable at $120 nominal in 15 years time with annual coupons of 7% (based on a nominal bond of $100) at interest rates of 6% ,

Estimate cost of financing, Calculate the equal monthly payments and the co...

Calculate the equal monthly payments and the cost of financing on a 10-year mortgage. The cash value of the house today is $500,000. You are paying monthly at a fixed rate of 6% pe

Determine the net present value of proposed project, A foreign company plan...

A foreign company plans to clear several dozen acres of ecologically valuable mangrove swamp in Vietnam for the creation of a shrimp aquaculture facility.  This decision will creat

Determine the net book value, NSC Ltd. has a 31 May fiscal year-end. NSC di...

NSC Ltd. has a 31 May fiscal year-end. NSC disposed of its Information Systems Group (ISG) on 31 January 20X3. ISG had a net loss (after taxes) of $37,700,000 in 20X3, to the date

Machining costing, what are the factor for setting costing for a certain ma...

what are the factor for setting costing for a certain machining job

Prepare a regular income tax return, Facts:   James (age 58, SS# 123-34-...

Facts:   James (age 58, SS# 123-34-4439) and Martha (age 56; SS# 233-23-9050) Williams are married. James works at a major retailer as manager of the early shift. Martha is a nu

Purchase cost and ordering cost, Ordering cost is incurred whenever the ...

Ordering cost is incurred whenever the inventory is replenished. It includes costs associated with the processing and chasing of the purchase order transportation, inspec

Which of the following is a reason, . Which of the following is a reason wh...

. Which of the following is a reason why traditional product costing techniques have become obsolete in a lean operating environment? a. More complex accounting is required in a le

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd