Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Job costing, the features and scopes of job costing

the features and scopes of job costing

Calculate the cost of capital and units of capital, The owner of the Hughes...

The owner of the Hughes Car Wash believes that the relationship between the number of cars washed and the amount of labor employed is Q = 0.8 + 4.5 L - 0.3 L2 where Q = the num

Process accounts, What is the easiest of calculate equivalents before produ...

What is the easiest of calculate equivalents before producing a process account 2

Describe the concept of full cost recovery with illustrative, Describe the ...

Describe the concept of full cost recovery with illustrative examples.

Realized gain or loss on the exchange, Pauline's Pastry Shop decides to rem...

Pauline's Pastry Shop decides to remodel its offices this year. As part of the remodeling, Pauline's trades furniture with a cost of $12,000 that had been expensed in the year of p

Calculate the variable cost, Workmen shoes accumulated the following produc...

Workmen shoes accumulated the following production and cost data for the past 5 months. i)  Using the high/low method calculate the variable cost per unit and the fixed cos

Prepare the amortization schedule, Logan Corporation issued $800,000 of 8% ...

Logan Corporation issued $800,000 of 8% bonds on October 1, 2006, due on October 1, 2011. The interest is to be paid twice a year on April 1 and October 1. The bonds were sold to y

Determine the current share price - shareholder, Most corporations pay quar...

Most corporations pay quarterly dividends on their common stock rather than annual dividends. Barring any unusual circumstances during the year, the board raises, lowers, or mainta

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd