Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

What is emv and eol approach, Adele Weiss manages the campus flower shop. ...

Adele Weiss manages the campus flower shop. Flowers must be ordered three days in advance from her supplier in Mexico. Advance sales are so small that Weiss has no way to estimate

Net cash inflow, Holmes Electronics' Canadian Branch will help introduce in...

Holmes Electronics' Canadian Branch will help introduce into Canada the just developed new electronic device which, when mounted on an automobile, will tell the driver how many mil

Prepare the appropriate entries for january 1, A corporation acquired a tru...

A corporation acquired a truck on July 1, 2012, at a cost of $162,000. The truck has a six-year useful life and an estimated salvage value of $18,000. The straight-line method of d

Marginal costing, Please kindly post some problems along with solutions so...

Please kindly post some problems along with solutions so it is easy to understand..I am quite satisfied by the per-forma you have mentioned.. THANK YOU.

Calculate the direct labor, A CPA firm estimates that an audit will require...

A CPA firm estimates that an audit will require the following work: Type of Auditor Expected Hours Cost per Hour Standard Costs Manager 10 $50 $ 500 Senior 20 40 800 Staff 40 30

Determine the current price of shares, 2. Blue-Jay Sporting Goods is a star...

2. Blue-Jay Sporting Goods is a start-up company that expects to earn $3.00 per share next year. Since the firm currently retains 100 percent of earnings to finance future grow

Calculate the total direct labor cost & labor wage rate, Peter Coffin and P...

Peter Coffin and Paul Bearer own The Grave Undertaking, Inc. and their firm uses a predetermined overhead rate to apply overhead to the production of custom-built coffins.  They us

Method of bonus payment , from the following particulars calculate the earn...

from the following particulars calculate the earning of worker . rate per hours $0.50 standard time 200 hours time taken 140 hours

Prepare a cash budget, You have been asked to prepare a cash budget for Whi...

You have been asked to prepare a cash budget for Whitborrow plc for the next three months, October, November and December. The Managers are concerned that they may not have suffici

Determine internal rate of return and cash flow statement , A local deliver...

A local delivery company has purchased a delivery truck for $15,000.  The truck will be depreciated under MACRS as a five year property.  The trucks market value (salvage value)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd