Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Methods of allocating service costs, Methods of Allocating Service Costs ...

Methods of Allocating Service Costs Direct Method The service costs are merely allocated to the production department according to the usage of the services given. St

What is the optimal price without price discrimination, We consider two reg...

We consider two regions A and B. Each market has the same size (i.e. number of consumers) but differs in the willingness to pay for one unit of the good proposed by the firm. On ma

Find interest and refunde, Gerona Company authorized the sale of $300,000 o...

Gerona Company authorized the sale of $300,000 of 10%, 10-year debentures on January 1, 2008. Interest is payable on January 1 and July 1. The entire issue was sold on April 1, 200

Cost Estimation, On a New product development process of making a new S3 ST...

On a New product development process of making a new S3 STORAGE SIM card phone storage device for end users, forecast the following With full working and tabulations; a) With fu

Profit an economic profit, Johnson Farms owns valuable farm land that permi...

Johnson Farms owns valuable farm land that permits it to make wheat at a lower cost than its competitors. The company reports large profits every year on its accounting statements.

Explain with examples and cite were needed, What are the distinguishing cha...

What are the distinguishing characteristics of these types of stock- describe any one of them. What is the difference between par value, book value and market value of stock? Expla

Disadvantages of standard costing, Disadvantages of Standard Costing ...

Disadvantages of Standard Costing 1. The system of standard costing is very expensive to install : A lot of money is spent in studying output requirements in terms of materia

Budget, budget preparation

budget preparation

Economic order quality or eoq, Economic Order Quality or EOQ Define th...

Economic Order Quality or EOQ Define the model and the three methods of computing the EOQ. 1. Assumptions of the model. Illustration The given information was extra

Calculate the cost of direct material used during the period, A company add...

A company adds overhead costs to jobs at the rate of $8 per direct labor hour. It accumulates overhead costs in a seperate manufacturing overhead account and uses normal costing to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd