Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Why communities begin using fca, Q. Why communities begin using FCA? Th...

Q. Why communities begin using FCA? There are several reasons why communities start by means of FCA. For instance: • To elucidate more evidently MSW costs to people. • It is

Evaluate the overhead allocation rate, Vintage Auto Company manufactures pa...

Vintage Auto Company manufactures parts to order for antique cars. Vintage Auto makes everything from fenders to engine blocks. Each customer order is treated as a job. Vintage Aut

Direct materials total variance, Direct Materials Total Variance Direc...

Direct Materials Total Variance Direct materials total variances refer to the difference between the standard direct material cost of the actual production volume and the actu

Product costing methods, What are the strengths and weaknesses of the vario...

What are the strengths and weaknesses of the various costing methods and which would you recommend for a manufacturing enterpris? 2000word assay plus appendix

Calculate the profit maximizing quantity , Draw the relevant diagrams for a...

Draw the relevant diagrams for a typical farm, and for the market as a whole, when the market for wheat is in long run equilibrium. Assume the farm faces perfect completion. (hint,

Compute the days'' sale, Year Ending April 2009, 2009 April 30, 2008 Net Sa...

Year Ending April 2009, 2009 April 30, 2008 Net Sales $10,148,082 $10,070,778 Accs Receivable 1,171,797 1,161,481 Assume that the accounts receivable (in thousands) were $996,852 a

allocate the support departments costs , Support Department Cost Allocatio...

Support Department Cost Allocations. Riverside Furniture Company manufactures unfinished furniture for sale to retailers. Riverside has two support departments, Maintenance and Hu

Government and nonprofit accounting, I need project help in Government and ...

I need project help in Government and nonprofit accounting, can you help me in look out this problems?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd