Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Prepare a statement of comprehensive income, Good Food Company is a local m...

Good Food Company is a local manufacturer of instant noodles. Established in 2005, their business has been growing steadily. Their products, which are available in 3 flavors, are s

Prepare trial balance for transactions, Encik Farid, a sole trader, started...

Encik Farid, a sole trader, started his business on 1 May 2010 under the name Farid Enterprise. The following are his business transactions for the month of May a. Encik Farid b

Calculate the rate of learning of initial production phase, Calculate the r...

Calculate the rate of learning at which the initial production phase profit target would be achieved, assuming no other cost savings can be made.   Assuming no other cost savi

Sales revenue variance (srv), SALES REVENUE VARIANCE (SRV) The word 'Sa...

SALES REVENUE VARIANCE (SRV) The word 'Sales Variance' is indicated by the expression 'operating profit variance due to sales' by ICMA.  It is described as 'the difference betw

Prepare an income statement for wadley''s car wash, Income Statement Prepar...

Income Statement Preparation The following information is taken from the records of Wadley's Car Wash for the year ended December 31, 2012. Income taxes . . . . . . . . . . .

Prepare cash flow statement, The following details are available from a com...

The following details are available from a company:                                                  2003                 2004                                      2003

Please show you calculation and explain the answer, In early July, Mike Got...

In early July, Mike Gottfried purchased a $70 ticket to the December 15 game of the Chicago Titans. (The Titans belong to the Midwest Football League and play their games outdoors

Cost sheet, 10% of the finished castings were to be defective in manufactur...

10% of the finished castings were to be defective in manufacture and were rectified by expenditure of additional works overhead charges to the extent of 20% on the proportionate di

Cost accounting, raw an organization chart of any actual or hypothetical ma...

raw an organization chart of any actual or hypothetical manufacturing organization to show the position of management/cost accounting department within an organization and discuss

What is the overhead variance, Morrow Company applies overhead based on dir...

Morrow Company applies overhead based on direct labor hours. At the beginning of the year, Morrow estimates overhead to be $620,000, machine hours to be 180,000, and direct labor h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd