Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Difference between balance sheet and income statement, (i) Describe the di...

(i) Describe the difference between the balance sheet and the income statement in financial statements of companies. (ii) Give two examples of intangible assets and two exampl

Material usage variance, Describe briefly the possible causes of: (i)   ...

Describe briefly the possible causes of: (i)   the material usage variance, (ii)  the labour rate variance, (iii)  the sales volume profit variance.

Purpose of cost estimation, Purpose of Cost Estimation In estimating i...

Purpose of Cost Estimation In estimating it assists the future expenditure as cost prediction like the expenditure will depend upon the cost of the respective activities a)

Overhead analysis, allocate the overheads to the three departments and do t...

allocate the overheads to the three departments and do the secondary allocation of service departments

What is operating income under absorption costing, Loring Company had the f...

Loring Company had the following data for the month: Variable costs per unit: Direct Materials $4 Direct Labor 3.20 Variable Overhead 1 Variable selling expense 0.40 Fixed Ov

Valuation of inventory or closing and issues stocks, Valuation of Inventory...

Valuation of Inventory or Closing and Issues Stocks Valuation of inventory aims on attaching a monetary value in the issued or stores for production. It is useful in producing

How many coupon bonds would you need to issue, 1. Suppose your company need...

1. Suppose your company needs to raise $30 million and you want to issue 30-year bonds for this purpose. Assume the required return on your bond issue will be 8 percent, and you're

Effective annual rate, The credit term from the supplier is 2/30, net 60. ...

The credit term from the supplier is 2/30, net 60. Requirements: Write the calculation Determine the effective annual rate if the firm does not take the discount.

QUESTION AND ANSWER, question and answer: XYZ trading purchased 6,850 killo...

question and answer: XYZ trading purchased 6,850 killos of material at a total cost of 21,920.00. The material price variance was 1,370.00 favorable. The standard price per killo w

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd