Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Disadvantages of standard costing, Disadvantages of Standard Costing ...

Disadvantages of Standard Costing 1. The system of standard costing is very expensive to install : A lot of money is spent in studying output requirements in terms of materia

What is cmm, CMM is an internationally recognized standard for calculating ...

CMM is an internationally recognized standard for calculating the maturity of an organization's software development processes and has become the primary benchmark multinational co

Which of the four types of costs would include ceo''s salary, Which of the ...

Which of the four types of costs would include a CEO's salary? A. Unit-Level B. Batch-Level C. Product Sustaining D. Facility Sustaining

Cvp analysis, the formula of culculating product cost per unit

the formula of culculating product cost per unit

Calculate the direct-material price and quantity variances, Quicksilver Com...

Quicksilver Compnay has set the follwoing standards for one unit of product: Direct material Quantity: 6.2 lbs per unit Price per lb: $11 per lb Direct Labor Quantity: 6 hrs

Example of profit volume graph, Example of Profit Volume Graph The sum...

Example of Profit Volume Graph The summary results of a company are given as: Product                        A B          C

Usefulness of variance analysis, Usefulness of Variance Analysis Caref...

Usefulness of Variance Analysis Carefully note that while prices are being charged to production, it can be done at the actual or standard price. For purposes of making varian

Prepare cash flow statement, The following details are available from a com...

The following details are available from a company:                                                  2003                 2004                                      2003

Advantages of average costing method, Average costing method has the follow...

Average costing method has the following main advantages: 1.It is a realistic costing method useful to management in analyzing operating results and appraising future production

Over And Under Absorption of Production Overhead Costs, Over And Under Abso...

Over And Under Absorption of Production Overhead Costs This may be analyzed beneath a) Activity This is level of the business or cost center. Expenditure on several item

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd