Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Determine the current ratio, When firms enter into loan agreements with the...

When firms enter into loan agreements with their bank it is very common for the agreement to have a restriction on the minimum current ratio the firm has to maintain. So, it is imp

#title.Budget., Ask The James Company, a wholesaler, budgeted the following...

Ask The James Company, a wholesaler, budgeted the following sales for the indicated months June 2004 July 2004 August 2004 Sales on account 1800,000 1,92

Manufacturing Overhead, Does Manufacturing Overhead include the following:1...

Does Manufacturing Overhead include the following:1)Material Handling - labour for Purchasing Material, Shipping (inbound for raw materials and outbound for finished product - also

Differential costing, What do you mean by differential costing ? How it dif...

What do you mean by differential costing ? How it differ from marginal costing ? explain its practical application with examples?

Calculate the profit maximizing quantity , Draw the relevant diagrams for a...

Draw the relevant diagrams for a typical farm, and for the market as a whole, when the market for wheat is in long run equilibrium. Assume the farm faces perfect completion. (hint,

Material costs, Material Costs Material refers to each physical input ...

Material Costs Material refers to each physical input into the production procedure. They involve the giving as: Raw material refers to bought in material that is used

Standard cost, Standard Cost It is especially serious that you establi...

Standard Cost It is especially serious that you establish a link between standard budgets and costs. At this point, you require putting in your mind to standard costs one the

Calculate the allocations and totals, A company wishes to devise a fair mea...

A company wishes to devise a fair means of allocating funds to its four main departments, namely Accounts, Production, Sales and Transport. The total allocation is to be £100,000.

Variance analysis, Variance Analysis This section describes how labour...

Variance Analysis This section describes how labour, material and overhead variances are calculated and what causes every of those variances. A chart is given also to describe

Direct labour budget, Direct Labour Budget It represents the forecasts...

Direct Labour Budget It represents the forecasts of indirect and direct labour requirements to meet the demands of the company throughout the budget period. Therefore the budg

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd