Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Identify the stakeholders and organization, i.   Identify the organization ...

i.   Identify the organization ii.  Identify the stakeholders iii. Give the major requirements for the IT application iv. Reflect on how difficult it was to do the require

Measuring performance in organization, list and discus the problem encounte...

list and discus the problem encountered in adopting profit as a yardstick in measuring performance

What is amount that lifo liquidation added to gross margin, Q. Given the be...

Q. Given the below information, what is the dollar amount that the LIFO liquidation added to gross margin?   Number of Units Price per Unit

Overhead variances, OVERHEAD VARIANCES Unlike labour and direct materia...

OVERHEAD VARIANCES Unlike labour and direct material, the manufacturing overhead is not completely variable with the level of production.   So, standard costs for factory overh

The managing director is dubious , A  firm of printers  is contemplating  j...

A  firm of printers  is contemplating  joining  the uniform  costing  system operated by  its Trade Association but the Managing Director is dubious about the benefits of becoming

Determine when to stock, Determine When to Stock It will be influence ...

Determine When to Stock It will be influence with the inventory system in place as given: 1. Periodic order system. The firm obtains a new order of the amo

Cash flow statement, In this section we have tried to develop the concept o...

In this section we have tried to develop the concept of flow of funds inside the organization. Starting along with the funds requirement for an organization, we have tried to trace

Why is the statement of cash flows useful, Explain:- Q Why is the statem...

Explain:- Q Why is the statement of cash flows useful? Q. How is it possible for a company to suffer a net loss for a given year, yet produce a positive net cash flow from opera

Foreign corrupt practices, Companies invest in overseas firms -- i.e.,...

Companies invest in overseas firms -- i.e., conduct M&As and joint ventures abroad for different reasons, just as the overall investment patterns (or FDI) of individual c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd