Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Goods and services tax, William Potter is a plumber currently operating as ...

William Potter is a plumber currently operating as a Sole Trader in Levin. William has approached you, a tax accountant, for your advice on certain tax matters. William's brothe

Bad debts, These are losses on account of uncollectable debts. While the am...

These are losses on account of uncollectable debts. While the amount due from debtors is irrecoverable, it is termed as bad debts. Bad debts, being loss are closed through transfer

Labor transactions, Labor Transactions (i) Wages Paid in cash (ii) ...

Labor Transactions (i) Wages Paid in cash (ii) Wages incurred like a) Direct labor or else b) Indirect labor  In the Financial Books  In

explain your calculation of relevant net cash flows, Polycorp Limited Stee...

Polycorp Limited Steel Division is considering a proposal to purchase a new machine to manufacture a new product for a potential three year contract.  The new machine will cost $1

Draw the demand curve - quantity of trash, The total demand (marginal benef...

The total demand (marginal benefit) curve for visiting Yosemite is as follows: Price = 5000-10*NumberOfTrips -10*TonsOfVisibleTrash.     a. Suppose the quantity of trash=100 ton

What is amount that lifo liquidation added to gross margin, Q. Given the be...

Q. Given the below information, what is the dollar amount that the LIFO liquidation added to gross margin?   Number of Units Price per Unit

You should be willing to pay the worker , You are the manager of a firm tha...

You are the manager of a firm that sells output at a price of $40 per unit. You are interested in hiring a new worker who will increase your firm's output by 2,000 units per year.

Cost-plus pricing, Computation of mark up and Target selling price in cost-...

Computation of mark up and Target selling price in cost-minus pricin

Job order costing, the folloeing job order cost sheets were purchased for t...

the folloeing job order cost sheets were purchased for three jobs that were in production during january job 97 job 98 job 99 material

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd