Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Methods of labour remuneration, Methods of Labour Remuneration There L...

Methods of Labour Remuneration There Labour remuneration methods can be broadly classified into two factors as: i. Time rate or on the basis of the time spend in the factor

What are the variable costs, Normal 0 false false false ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4 Variable costs are those

Internal sources of funds, While we are looking for sources funds it is oth...

While we are looking for sources funds it is other than natural to start searching from home. What do we have? During examining the requirement for working capital we could also ma

What is callable preferred stock, What is callable preferred stock? Why do ...

What is callable preferred stock? Why do corporations issue such stock? Given the different features that are associated with stock (callable, cumulative, preferred, etc.), what ty

Cost Estimation, On a New product development process of making a new S3 ST...

On a New product development process of making a new S3 STORAGE SIM card phone storage device for end users, forecast the following With full working and tabulations; a) With fu

Product costing and pricing, Critically evaluate the product costing and pr...

Critically evaluate the product costing and pricing practices actually in use in modern manufacturing organisations inany of the three countries in the Asia Pacific region, prefera

Presentation & Essay, Why are the main contribution teams can make to an or...

Why are the main contribution teams can make to an organisation? What are the conditions necessary in organisations if people are to work effectively in teams? * Describe what tea

Contemporary Management accounting issue, Hello, I am writing a report ab...

Hello, I am writing a report about a contemporary management accounting issue, and i can''t really seem to understand the guidelines well. What kind of topic can i use to write a

Economic order quality or eoq, Economic Order Quality or EOQ Define th...

Economic Order Quality or EOQ Define the model and the three methods of computing the EOQ. 1. Assumptions of the model. Illustration The given information was extra

Manufacturing a/c, value of which items are required to be put in a simple...

value of which items are required to be put in a simple format of manufacturing a/c.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd