Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Process costing procedure, Process Costing Procedure 1. The production...

Process Costing Procedure 1. The production factory is divided into a number of methods. 2. An account is maintained and opened for every process. 3. Every process accou

Trypanosoma, Place a prepared slide of Trypunosoma under tlic microscope an...

Place a prepared slide of Trypunosoma under tlic microscope and focus it under low power, You will observe large number of tiny spindle-shaped trypanosomes lying in the plasma alll

Estimate the growth rate of stock, Estimate the Growth rate of stock ...

Estimate the Growth rate of stock Data stock price = 53 rate of return= 12% expected dividend = 3.15 Formula : Expected return  = (dividend paid + capital

Cost accounting, raw an organization chart of any actual or hypothetical ma...

raw an organization chart of any actual or hypothetical manufacturing organization to show the position of management/cost accounting department within an organization and discuss

Describe time sheets and job cards, (a) Describe briefly how the following ...

(a) Describe briefly how the following are used in the accounting for labour: (i)   time sheets (ii)   job cards. (b) The following details relate to the labour in a produ

Standard cost and standard costing, Standard Cost and Standard Costing ...

Standard Cost and Standard Costing To effectively control the costs of a certain organization, we require a yard stick to measure the real performance against. Traditionally,

Determine the amount of depreciation expense, Waylander Coatings Company pu...

Waylander Coatings Company purchased waterproofing equipment on January 6, 2013, for $320,000.The equipment was expected to have a useful life of four years, or 20,000 operating ho

Advantages of average costing method, Average costing method has the follow...

Average costing method has the following main advantages: 1.It is a realistic costing method useful to management in analyzing operating results and appraising future production

Determine the cost of the finished goods inventory, Manufacturing statemen...

Manufacturing statements and cost behavior  Tampa Foundry began operations during the current year, manufacturing various products for industrial use. One such product is light-g

Why is it important for financial statements, Why is it important for finan...

Why is it important for financial statements and other external reports to be based on generally accepted accounting principles?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd