Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Qualitative characteristic of understandability means, The enhancing qualit...

The enhancing qualitative characteristic of understandability means that information should be understood by a those who are experts int eh interpretation of financial informat

Chapter 4 Fundamentals of Cost Analysis for Decision Making, 31. Special Or...

31. Special Orders Maria’s Food Service provides meals that nonprofi t organizations distribute to handicapped and elderly people. Here is her forecasted income statement for April

Prepare a forecast of cashflow, A company is to produce an IC and a chip si...

A company is to produce an IC and a chip size of 120mm2 has been estimated, based on using a full-custom nMOS technology on 8" wafers. The process has a 92% yield at the wafer fab

What is cmm, CMM is an internationally recognized standard for calculating ...

CMM is an internationally recognized standard for calculating the maturity of an organization's software development processes and has become the primary benchmark multinational co

Calculate the equivalent annual cost, A plant is considering the replacemen...

A plant is considering the replacement of a piece of equipment in its materials handling system with a new piece. If the company's cost of capital is 10%. Should the present asset

What is operating costing, Describe Operating Costing The Chartered Ins...

Describe Operating Costing The Chartered Institute of Management Accountants, London defines "operating cost" as "the cost of providing a service." Services performed may be in

Government and nonprofit accounting, I need project help in Government and ...

I need project help in Government and nonprofit accounting, can you help me in look out this problems?

Determine the economic order quantity, A retailer knows the annual demand f...

A retailer knows the annual demand for one of its product is 100,000 units, the ordering costs are £25 per order and the average carrying cost per unit is 35 pence. You are require

Direct material price variances, Direct Material Price Variances The t...

Direct Material Price Variances The two direct material price variances can be summarized given as: From our basic data first before the beginning of the discussion on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd