Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

West Industries, West Industries is a highly decentralized corporation with...

West Industries is a highly decentralized corporation with independent operating divisions. Each division is evaluated and rewarded based on its total net income. One of the divisi

Marginal cost curves, A firm operates two plants with the marginal cost cur...

A firm operates two plants with the marginal cost curves given by MC 1 = 50 + 2Q 1 , MC 2 = 90 + Q 2 . If the firm's total output must be 80 units, how much will it produce a

Example of flexible and fixed budget, Example of Flexible and Fixed Budget ...

Example of Flexible and Fixed Budget A company has budgeted to produce and sell 100,000 units of cakes throughout the next period. The selling price per cake is Sh. 20 and var

Principle of accounting, what is the implication of applying accounting pr...

what is the implication of applying accounting principle wrongly

Flexible budget, Flexible Budget Flexible budget is a budget that is d...

Flexible Budget Flexible budget is a budget that is designed to change in accordance along with the level of activity attained. It includes budgeting at various levels in anti

Purchase cost and ordering cost, Ordering cost is incurred whenever the ...

Ordering cost is incurred whenever the inventory is replenished. It includes costs associated with the processing and chasing of the purchase order transportation, inspec

Cash Budgeting, Stopover industries ltd, a recently incorporated company pl...

Stopover industries ltd, a recently incorporated company plans to go into production next year. the following standard cost matrix has been assembled for one of the products it pro

Prepare the draft sfp for the fiscal year, Prime Essentials Limited is a sm...

Prime Essentials Limited is a small private corporation. The owner plans to approach the bank for an additional loan or a line of credit to facilitate expansion. The company bookke

Government and nonprofit accounting, I need project help in Government and ...

I need project help in Government and nonprofit accounting, can you help me in look out this problems?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd