Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Discount model of stock valuation-ddm, Value one stock using the dividend d...

Value one stock using the dividend discount model of stock valuation with two periods of constant growth (not the simple one period growth model).  See chapter 18 of the textbook

Compute the net cash used, Martinez Corporation engaged in the following ca...

Martinez Corporation engaged in the following cash transactions during 2012. Sale of land and building $186,710 Purchase of treasury stock 42,130 Purchase of land 39,130

What is the net operating income, A manufacturing company that produces a s...

A manufacturing company that produces a single product has provided the following data concerning its most recent month of operations: selling price $140 units in begining in

Calculate the receivable turnover ratio, Presented here is the basic financ...

Presented here is the basic financial information from the 2009 annual reports of Intel and Advanced Micro Devces (AMD), the two primary manufacturers of silicon chips for personal

Methods of work in progress, Methods of Work in Progress The two main ...

Methods of Work in Progress The two main methods used for purposes of valuing the opening work in progress: 1. Weighted Average Method 2. FIFO or First In First out Meth

Interest earned on down payment, You sell a machine for $600,000. You allow...

You sell a machine for $600,000. You allow the client to pay 1/3 at the time of the sale and 1/3 at the end of year one and 1/3 at the end of year two. The company earns 10% on ass

Calculate break-even level of sales volume and revenue, Q. Calculate break-...

Q. Calculate break-even level of sales volume and revenue? Z-Boxes sell for £299 and their variable production cost is £99. Research and development, and fixed production overh

Relationship among financial accounting and cost accounting, Relationship a...

Relationship among Financial Accounting and Cost Accounting The difference among management and cost accounting may be highlighted by using a number of questions namely as;

Utility of break even point in managerial decision making, UTILITY OF BREAK...

UTILITY OF BREAK EVEN POINT IN MANAGERIAL DECISION MAKING 1. It assists in determination of sales mix 2. It assists in exploring new markets 3. It assists in deciding abo

Objectives of budgetary planning, Objectives of Budgetary Planning 1...

Objectives of Budgetary Planning 1) Coordination The budgetary process needs that visible detailed budgets are developed to cover every activity, function or department

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd