Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Provision for bad and doubtful debts, A provision must be made in advance f...

A provision must be made in advance for those debts whose recovery is uncertain and to writing off bad debts. Each enterprise, depends on their past experience, make a provision fo

Period costs, Period Costs Some terms are difficult to define. In one s...

Period Costs Some terms are difficult to define. In one school of thought, period costs are the any costs that are not product costs. But, such a description is a stretch, beca

External sources of funds, These sources of funds are resources increased f...

These sources of funds are resources increased from outside the organization to augment funds availability for any of the utilizations to be discussed later. Generally, there are o

Why is the statement of cash flows useful, Explain:- Q Why is the statem...

Explain:- Q Why is the statement of cash flows useful? Q. How is it possible for a company to suffer a net loss for a given year, yet produce a positive net cash flow from opera

Calculate the monetary of the inventory, Learning Objective: After completi...

Learning Objective: After completing the project, the student will have gained familiarity, understanding and mastery of programming a realistic but simple application in Assembly

How much will alan save or lose, Hale Company makes sets of wrenches. They ...

Hale Company makes sets of wrenches. They are trying to decide whether to continue to make the case the wrenches are sold in, or to outsource it to another company. The direct mate

Overhead anaylysis, the annual overhead costs for abc ltd which has 3 produ...

the annual overhead costs for abc ltd which has 3 production centeres and 2 service centers are as follows. indirect wages & supervision X 2million Y 2million 3 production departme

The sales value basis., The following data relate to three joint products: ...

The following data relate to three joint products:                                                                               A                 B                     C

Advantages of average costing method, Average costing method has the follow...

Average costing method has the following main advantages: 1.It is a realistic costing method useful to management in analyzing operating results and appraising future production

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd