Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Cash budget - budgetary planning and control, Cash Budget - Budgetary Plann...

Cash Budget - Budgetary Planning and Control This can records the cash outflows and inflows that are expected to take place in respect of every functional budget. This may be

Which of the following is a reason, . Which of the following is a reason wh...

. Which of the following is a reason why traditional product costing techniques have become obsolete in a lean operating environment? a. More complex accounting is required in a le

Profit volume ratio, sales to profit volume ratio for three year

sales to profit volume ratio for three year

Abnormal loss account and abnormal gain account, A product is manufactured ...

A product is manufactured by passing through three processes: A, B and C. In process C a by-product is also produced which is then transferred to process D where it is completed. F

Purpose, what are the purposes of cost accounting

what are the purposes of cost accounting

Determine the total amount of product cost, Product and period costs; CGM; ...

Product and period costs; CGM; CGS On August 1, 2013, Sietens Corporation had the following account balances: Raw Material Inventory (both direct and indirect) :- $ 72,000 WIP Inve

Determine the cost that changes in total proportionately, Presented below i...

Presented below is a list of terms relating to cost behavior, followed by definitions of those terms: a. Rent on a factory building b. Engineering approach c. Fixed cost

Prepare an eps summary for income statement, You are thinking of investing ...

You are thinking of investing in one of two corporations, both in the same industry, the XYZ Corporation or the ABC Corporation. Selected data follows: Sales data for the year e

calculate the percent interest rate and effective cost, 1. The following t...

1. The following three one-year "discount" loans are available toyou: Loan A: $120,000 at a 7 percent discount rate Loan B: $110,000 at a 6 percent discount rate Loan

Internal sources of funds, While we are looking for sources funds it is oth...

While we are looking for sources funds it is other than natural to start searching from home. What do we have? During examining the requirement for working capital we could also ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd