Determine the Machining Time in Milling Operation
An HSS slab mill of 100 mm diameter and 150 mm width is used on a Horizontal milling machine to mill C50 steel. The milling cutter has 8 teeth. Determine the machining time assuming that the entire stock can be removed in one depth of 2 mm. The cutting speed V = 20 m/min and feed rate f = 0.13 mm/tooth. The cut length = 150 mm.
Solution
Given Z = 8
D = 100 mm
d = 2 mm
V = 20 m/min
f = 0.13 mm/tooth
Approach distance A =
Spindle speed
N = (1000 × 20) / (π× 100 )= 63.66 ≅ 65 rev/min
Time for machining t = (l + 2 × A)/ f z n = (150 + 2 × 14) / (0.13 × 8 × 65)
= 2.633 min.
Future Trends Ceramics and glasses contain wide ranging applications in domestic use and even wider application in manufacturing technology. The properties that are related wit
Determine the ratio between moment and load: Any close coiled helical spring of circular section extends 1 mm while subjected to an axial load of W and then given an angular r
A piston-cylinder assembly fitted with a paddle wheel contains air, initially at p1=30 lbf/in2, T1=540 °F, and V1=4 ft3. The air undergoes a process to a final state where p2=20 lb
why can''t we use petrol as a fuel for diesel engines?
Velocity acquired by block - system released from rest: T wo blocks shown in the figure given below, have masses A = 20N and B = 10N and the coefficient of friction between
Write down the uses of following tools and make neat sketches of the same : (a) Vernier Caliper (b) Steel Rule
Find distance through which the body will penetrates: A body having mass 25kg falls on the ground from height of 19.6m. The body penetrates into ground. Find distance through
the component of computer integrated manufacturing with the diagram
What is the aim of PDES The aim of PDES is to provide an interface which permits the exchange of data of the entire product development cycle and production cycle, see also PDE
Information Phase: Step: To secure all and complete information and gather facts and from best sources. Our project is selected based on the current problem face by the
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd