A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft and slopes at 2% grade. The grade rod reading at station 55+00 is most nearly:
Solution:
The Height of Instrument elevation can be calculated:
HI = 100.00-ft + 8.5-ft = 108.5-ft
The grade rod reading at station 50+00 is calculated by:
HI - station 50+00 elevation = 108.50-ft - 95.00-ft = 13.50-ft
The distance between station 50+00 and 55+00 is 500-ft
The slope is set at 2%, therefore; 2% x 500-ft = 10-ft elevation difference between stations.
Add the results of the proposed roadbed slope which is 10-ft to the grade rod reading at station 50+00 to obtain the grade rod reading at station 55+00 which is 23.50-ft.
what are the feature of single flemish bond?
Define the Cost per Square Foot of Contact Area The cost of concrete formwork is influenced by three factors: 1. Initial cost or fabrication cost that contains the cost of t
The design of flexible pavements how it is used
Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime
explain about single reinforced beams?
Determine the total Stopping Sight Distance in feet A motorist is travelling down a 6% grade at 65 mph and needs to stop because of a crash scene. Assuming a 2.0 sec PRT and 1
Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.
Measurement quantity of excavation, concrete, formwork as my assignment brief.
Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We
LIME It is significant binding material utilized in building construction. Lime has been utilized as the material of construction from ancient time. While it is mixed with san
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd