A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft and slopes at 2% grade. The grade rod reading at station 55+00 is most nearly:
Solution:
The Height of Instrument elevation can be calculated:
HI = 100.00-ft + 8.5-ft = 108.5-ft
The grade rod reading at station 50+00 is calculated by:
HI - station 50+00 elevation = 108.50-ft - 95.00-ft = 13.50-ft
The distance between station 50+00 and 55+00 is 500-ft
The slope is set at 2%, therefore; 2% x 500-ft = 10-ft elevation difference between stations.
Add the results of the proposed roadbed slope which is 10-ft to the grade rod reading at station 50+00 to obtain the grade rod reading at station 55+00 which is 23.50-ft.
Define Special considerations for underwater inspection? Once a diver enters the water, there environment changes completely. Visibility decreases and is often reduced to near
Step by step rehabilitation strategies with drawing, figures, and illustrations
Define Friction Pendulum Bearing? In friction pendulum bearings, the lateral displacement is permitted at the interface of the bearing element between the superstructure and th
Drainage of Embankment Slopes: Slopes of high embankments get eroded by rain water. Deep rain cuts are formed, which endanger the pavement. In such cases, it is customary to
Explain Designation of bearings. Calculate included angle from bearings
material which can endures vibrations and saline conditions
What is mean by battening and lacing
Q. Specification of Water bound macadam road? Formation - The embankment for road shall be made to the cross section shown on the drawing. The bank shall be raised in regular
procedure for designing of sewage scheme
Reasons of ground heaving during pipe-jacking It is commonly recognized that ground settlement is one of the significant concern in pipe jacking operation. Though engineer mus
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd