A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft and slopes at 2% grade. The grade rod reading at station 55+00 is most nearly:
Solution:
The Height of Instrument elevation can be calculated:
HI = 100.00-ft + 8.5-ft = 108.5-ft
The grade rod reading at station 50+00 is calculated by:
HI - station 50+00 elevation = 108.50-ft - 95.00-ft = 13.50-ft
The distance between station 50+00 and 55+00 is 500-ft
The slope is set at 2%, therefore; 2% x 500-ft = 10-ft elevation difference between stations.
Add the results of the proposed roadbed slope which is 10-ft to the grade rod reading at station 50+00 to obtain the grade rod reading at station 55+00 which is 23.50-ft.
what are lab and field test carried on soil subgrade?
Question Geotechnical Instrumentation is often employed for monitoring state of reclamation . From time to time two piezometers are installed inside same borehole. What is mai
Cost-volume relationship: Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following
Q. Explain Foundation design discharge for a bridge? To provide for an adequate margin of safety against any abnormal flood exceeding the design discharge (Q), the foundations,
manufacture of cement by dry process
Q. State different types of chlorination processes available in Railway & market for disinfect ion of water. What type of chlorine used in the above different process. What do you
Formaldehyde and phenol are polymerised to resultant product that was known as Answer: This is known as bakelite.
Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near
Question Is procurement of third party insurance required to be incorporated in deal for construction works? Answer Purpose of third party insurance is to guard contra
I need this to be done perfectly . It is a civil engineering assignment. Please let me know if you can solve this perfectly within no more than 40 hours. Thanks.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd