A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft and slopes at 2% grade. The grade rod reading at station 55+00 is most nearly:
Solution:
The Height of Instrument elevation can be calculated:
HI = 100.00-ft + 8.5-ft = 108.5-ft
The grade rod reading at station 50+00 is calculated by:
HI - station 50+00 elevation = 108.50-ft - 95.00-ft = 13.50-ft
The distance between station 50+00 and 55+00 is 500-ft
The slope is set at 2%, therefore; 2% x 500-ft = 10-ft elevation difference between stations.
Add the results of the proposed roadbed slope which is 10-ft to the grade rod reading at station 50+00 to obtain the grade rod reading at station 55+00 which is 23.50-ft.
Design of Flexible Pavements: The design of flexible pavements is done by the CBR method. The CBR test, described further, gives an indication of the supporting power of the
You have been selected to assist the structural engineer for a bridge replacement project. Your task is to design the size of the footing for an interior bridge pier, based on the
Define Cleaning for Underwater Inspection of Bridge? Before any structure can be inspected, it is necessary to expose the surface material of the structure. Wherever there is m
State the term - Failure Due to Strain In most of the cases of pre-stressed concrete construction, the failure of underreinforced and lightly reinforced members shall take pla
Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .
Question Shall layer of wearing course or additional thickness be designed on surface of piers ? Answer In designing of piers , considerations have to be given to
If the resultant forces are resolved in the three co-ordinate directions and divided by the area of the face of the cube we have the general state of 3-dimensional stress as shown.
how to find degree of kinematic indeterminacy
1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%. The final volume of the compacted
spiral curves?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd