Delay of bituminous laying on top of sub-base,, Civil Engineering

Assignment Help:

Question

In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base?


Answer


When there is a delay between bituminous laying of different bituminous layers such as roadbase, base course. A tack coat is applied on top of bituminous layers as it helps to improve better bonding between bituminous materials. If there is not enough bonding between adjacent bituminous layers, they perform as separate independent layers which are able to barely resist traffic loads. When applying tack coat, it have to be sprayed uniformly on bituminous surface and allowed for enough curing. Hot bituminous material laid on top of coat would soften it, enabling tack coat to partly fill voids in bituminous materials. For emulsified asphalt category tack coats, they are usually diluted with water in order to achieve an additional uniform application without excessive usage of asphalt. After subsequent compaction is carried out, coat would be interlocked with bituminous materials. On other hand, care should be taken to make sure that excessive coat will not be laid, or else slippage or shear cracks in bituminous material would occur due to relative thick layer of tack coat applied.

Though, for sub-base surface, priming coat in its place of tack coat might be applied in event of a delay in laying of bituminous layer on top of sub-base layer. Function of primer serves to maintain existing surface condition for a longer period and it also provides an impervious surface to stop ingress of water or water beating by evaporation.

Besides, it fills surface voids and protects sub-base from adverse weather setting. In adding up, it and helps to promote adhesion between adjacent road layers and to harden surface.

 


Related Discussions:- Delay of bituminous laying on top of sub-base,

Engineering Science, 1(a)Explain the difference between a concurrent and a ...

1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil

Dam, how can i prepare a project on dam

how can i prepare a project on dam

Use of stone aggregates in road construction, Use of Stone Aggregates in Ro...

Use of Stone Aggregates in Road Construction Stone aggregates are extensively used in roads in pavement layers. They are obtained from natural rock. The following geological

Influence of pressure in the soil, Q. Influence of Pressure in the Soil? ...

Q. Influence of Pressure in the Soil? Figure shows the stress state beneath a footing. The steady state situation prior to footing as well as qualitative variation of pressure

Determine about the prestressed concrete, Determine about the prestressed c...

Determine about the prestressed concrete In prestressed concrete the most important parameter is the prestressing force. Ifthe prestressing force reduces with time, prestresses

Difference between direct circulation and reverse drilling, Question Wh...

Question What is main difference between direct circulation drilling and reverse circulation drilling? Answer In straight circulation drilling and reverse circulati

Borrow pits - embankment construction, Borrow Pits Borrow pits are th...

Borrow Pits Borrow pits are the locations from where the embankment soil is obtained. The following guidelines govern the location of borrow pits : (a) They should be pref

Concrete, if the slump of concrete drops how to rectify it

if the slump of concrete drops how to rectify it

Estimating movement for movement joints, Question Should reversible moi...

Question Should reversible moisture movement be taken into account in estimating movement for movement joints ? Answer Size of concrete is affected by changes in dist

Explain the dupuit equations for unconfined aquifers, Explain the Dupuit Eq...

Explain the Dupuit Equations for Unconfined Aquifers   Using natural log: Q = ΠK((h 2 ) 2 - (h 1 ) 2 )/ln(r 2 /r 1 )  Using log 10 :   Q = K((h 2 ) 2 - (h 1 ) 2 )/((1055)l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd