Design stairways - ladders and platforms, Mechanical Engineering

Assignment Help:

Q. Design Stairways - Ladders and Platforms?

Stairways, rather than ladders, should be provided for main access to elevated structures. Ladders should be reserved for isolated points which are visited infrequently. Ladders and platforms shall be provided as required for access to manways, operating valves, and instruments. Ladder arrangements should be established early in the project in order to avoid reworking and re-orientation. Ladders should be side step off rather than through.

Combined tower platforms shall be furnished when practical or economical on "lined-up" towers with common manway elevations, providing tower differential expansion permits. Platforms or catwalks joining two towers together should have a slide plate or hinged section to allow for vessel movement or expansion.

Side platforms are to be provided for access to manways, instruments, valves and equipment, and for cross-overs between ladders. The size of these platforms should be kept to a minimum. The width should be minimum 900 mm (3 ft.), but shall be enough to permit opening of the manway cover or to provide a minimum of 450 mm (1.5 ft.) clearance between the handrail and piping such as a level controller, gauge glass, level switch or safety valve. Platforms need not extend underneath valves and equipment to make them accessible.

Tower manways, depending on tray arrangement, access, and maintenance area for vessel, shall generally be located to the rear of the vessel (away from the pipe rack), with all manways on or about the same centerline of orientation. Manways shall be located to give good access to the tower drop down area, so that tower internals removed through the manway require minimum manhandling to access the davit or crane.


Related Discussions:- Design stairways - ladders and platforms

I-Section, An unsymmetrical I-Section as shown in figure below. If maximum ...

An unsymmetrical I-Section as shown in figure below. If maximum bending stress is not extend more than 40MPa in the section than find out the moment which it can bear

Conceptual engineering phase in project development, Q. Conceptual engineer...

Q. Conceptual engineering phase? During this phase, a conceptual engineering estimate will be prepared by Project Management with input from all disciplines. Activities at t

Newton''s ring, Explain construction and working process of newton''s ring

Explain construction and working process of newton''s ring

Pmi testing of alloy materials, Q. Show PMI testing of alloy materials? ...

Q. Show PMI testing of alloy materials? Suppliers and Construction Subcontractors are required to verify or conduct PMI testing of alloy materials that they procure and use and

Assignment, Need someone to help in doing a connecting rod for an engine by...

Need someone to help in doing a connecting rod for an engine by using abaqus software version12 or 6.11?

Project quality plan, Project Quality Plan Design verification require...

Project Quality Plan Design verification requirements for a project are to be established in the Quality Plan sub-section of the Project Execution Plan. The Lead Mechanical E

SFD AND BMD, what is SFD and BMD? EXPLAIN

what is SFD and BMD? EXPLAIN

Show the procedure of welding of vessels, Q. Show the procedure of Welding ...

Q. Show the procedure of Welding of vessels? Welding of vessels, including pressure retaining parts and attachments thereto, shall be performed utilizing Welding Procedures, We

Sada, Ask question #ccMinimum 100 words accepted#

Ask question #ccMinimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd