Define the finish-to-start dependency, Civil Engineering

Assignment Help:

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

  1. A constraint
  2. An assumption
  3. A start-to-finish dependency
  4. A finish-to-start dependency  

Solution: 4. the inspections must be finished before the sheet-rocking can start.


Related Discussions:- Define the finish-to-start dependency

Stiff or soft fenders be designed for berthing in piers, Question Is it...

Question Is it necessary that stiff or soft fenders be designed for berthing in piers? Answer Elasticity of fenders is related to ability to release stored energy duri

Durability requirements for concrete, Durability requirements for Concrete ...

Durability requirements for Concrete Even though the alkaline environment of concrete protects steel, carbonation of hydrated cement may decrease the effective protection. The

Determine the common ways to present the project schedule, Common ways to p...

Common ways to present the project schedule include all except: a. Gantt charts b. Milestone charts c. PERT charts D. Project Network Diagrams with dates added   So

Explain pressure balance method and compressed air method, Pressure balance...

Pressure balance method vs. compressed air method in pipe jacking Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutti

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Foundation, difference between raft and pile foundation question..

difference between raft and pile foundation question..

Stairs, describe details about stairs and its type also draw sketch?

describe details about stairs and its type also draw sketch?

Statics, Currently I am struggling with masteringengineering.com So is it f...

Currently I am struggling with masteringengineering.com So is it fine to give you my username and password so you could solve my problems. please show your work.

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd