Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Flash butt welding, Flash Butt Welding The two pieces to be welded are ...

Flash Butt Welding The two pieces to be welded are pressed against each other by applying a pressure. To whatever finish the faces are machined, there will be some protuberance

Determine the reactions at the points of supports, Two identical rollers, e...

Two identical rollers, each of weight W= 1000N are placed by an inclined plane and a vertical wall as shown below. Determine the reactions at the points of supports A, B, and C. Su

RC circuit, #question.I am doing a ,ini project on Hovercrafts .As i am fro...

#question.I am doing a ,ini project on Hovercrafts .As i am from mechanical i need assistance regarding control over brushless motors.

Explosive welding i cladding, EXPLOSIVE WELDING I CLADDING In this pr...

EXPLOSIVE WELDING I CLADDING In this process, two pieces of metal are impacted together at an extremely high velocity of impact achieved by the detonation of an explosive cha

Processes , example on operation sheet?

example on operation sheet?

Production test rings, Q. Production Test Rings? The frequency for the ...

Q. Production Test Rings? The frequency for the tests shall be as follows: • One sample at the 10th joint • One sample at the 75th joint • One sample at the 300th join

Cantilever beam - shear force diagrams, Cantilever beam - shear force diagr...

Cantilever beam - shear force diagrams: Illustrate the shear force & bending moment diagrams for the cantilever beam illustrated in Figure. Figure Solution

Governor, what is the formula of sensitivity of governor?

what is the formula of sensitivity of governor?

M.o.s, Draw the shear force and bending moment diagrams for overhanging bea...

Draw the shear force and bending moment diagrams for overhanging beam subjected to pont load at its free end

Calculate the probable wall thickness of the tank, The background for the o...

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd